L&I Plan Review and Inspection in Opt-Out Municipalities: Permit Types, Submittals and Inspection Paperwork

In a Pennsylvania municipality that has opted out of enforcing the Uniform Construction Code (UCC), who reviews a commercial building plan? The answer, for many projects, is the Department of Labor and Industry itself. The Department has a long guidance page on plan review and inspection requirements that lays out what it handles, how a plan package moves through review, which permit types exist and what paperwork the inspections need. This page is a plain-language summary of that guidance, checked on November 23, 2026 on pa.gov. Verify forms, numbers and addresses against the current Department page. For the regulation side of commercial permits, see our page on 34 Pa. Code 403.42 and 403.42a.

Quick answer

  • Jurisdiction: the Department reviews plans, issues permits, inspects and issues certificates of occupancy for commercial construction, signs, demolitions and all state-owned buildings
  • Residential: in opt-out municipalities the Department does not approve residential work; that goes through a certified third-party agency
  • Intake: minor gaps put a project in temporary holding; if information is not received within 10 calendar days, plans are returned
  • Resubmittal: three revised sets, cloud-marked changes and a revision narrative, with no added review fee
  • Deferred systems: fire alarm and sprinkler plans go in as plan revisions at least two weeks before installation

What does the Department review?

The Department reviews plans, issues permits, inspects and issues certificates of occupancy for commercial construction (buildings other than one- or two-family dwellings of three stories or less), sign construction, demolitions and all state-owned buildings wherever located. It also approves accessibility plans and inspections where a municipality lacks a State-certified accessibility inspector or plan examiner. The applicable codes are listed as 34 Pa. Code Chapters 401 to 405 and the 2018 I-Codes, with electrical work following NFPA 70-2017. Existing buildings undergoing repairs, alterations, occupancy changes, additions or relocation must comply with the 2018 International Existing Building Code, and that applies only to legally occupied buildings. Pennsylvania began enforcing the 2021 International Codes on Jan. 1, 2026; check the current regulation text and your code office for the edition that applies. Health care facilities need Department of Health plan and occupancy approvals before UCC permits issue. See our page on 34 Pa. Code 403.21 for the adopted codes.

How does a plan package move through review?

Packages are mailed to the Department, and fees cover plan review and all inspections. Intake checks for completeness; grossly deficient packages are mailed back, while minor gaps place the project in temporary holding. If the requested information is not received within 10 calendar days, plans are returned. Complete applications are reviewed in order of receipt, and the page lists three outcomes:

OutcomeResult
Non-design changes onlyApproved plans with red-marked changes, plus a permit
Multiple or significant deficienciesRejection with a deficiency list
Approvable with changes, short of rejectionA change list and a request for three revised sets

Resubmissions require three revised sets, cloud-marked changes, a revision narrative and dated changes, and disagreements need written explanations. There is no added fee for a resubmitted review. Expedited review, within seven days of a written request, costs extra, and expedited plans that are rejected or resubmitted require paying the expedited fee again. Refunds are available on written request for rejected plans not resubmitted, less the base application fee and expedited fees, for new construction, additions and renovations only. The page gives a Department phone number for questions; use the current number on the page.

Which permit types does the page describe?

The page lists twelve permit categories. In short:

  • Phased construction: early work such as foundations before full plans are approved, with no guarantee of a later permit and revisions generally not allowed.
  • Accessibility permits: for commercial projects in municipalities without a certified accessibility official, with a form from the municipal building code official required.
  • Alterations Level 1: simple alterations to legally occupied buildings, such as replacing or covering existing materials, certain window and door additions, facade work and roof replacement, with fourteen categories listed. A sealed structural statement is required for structural changes.
  • Annual permits: for annual alterations to previously approved installations.
  • Building, structure and facility permits: new buildings, additions and alterations beyond Level 1, with three drawing sets, a specification set, site plans, a code analysis and other attachments.
  • In-home day care: one- or two-family dwellings caring for 4 to 12 children, under 24 hours a day, as a secondary use.
  • Modular construction: new modular buildings other than one- or two-family dwellings, with limited inspections when a sealed compliance letter is supplied.
  • Uncertified buildings (Act 95 of 2005): buildings constructed before April 27, 1927 are deemed certified, with only changes of use or alterations triggering compliance.
  • Demolition: required before demolishing any building or structure in an opt-out municipality, not required when demolition is concurrent with a replacement building application.
  • Signs: required before erecting signs in opt-out municipalities unless exempt under Appendix H of the 2009 IBC.
  • Partial occupancy certificates: a portion of a building may get a certificate if it independently meets UCC requirements; see our page on the certificate of occupancy sections.
  • Building shell permits: for speculative buildings with unknown tenants.

The demolition note on the page adds that a permit does not waive other obligations such as asbestos remediation, DEP and EPA notices, historic preservation and capping sewer and water connections. For excavation-related work on a demolition site, see our excavation protective systems page.

What do inspections and revisions require?

Permit holders receive an inspection log (Form UCC-7) listing required inspections and the assigned inspector, and must call the inspector within the timeframe in Form UCC-9. The log must stay on site. Contractors installing sprinkler, fire alarm, smoke control and evacuation, emergency lighting or hood extinguishing and ventilation systems must complete Form UCC-12, which stays on site and must be shown on request. The page warns that continuing work without required approvals may jeopardize occupancy and require removal and reconstruction of noncompliant installations. After permit issuance, changes need approval before work proceeds. Fire alarm and sprinkler plans and calculations are submitted as plan revisions at least two weeks before installation, with a design professional statement, while certified truss shop drawings need no revision or fee but must be on hand at the framing inspection. Our page on required UCC inspections gives general background.

Practical steps

  • Confirm that your municipality has opted out and that the project is one the Department handles.
  • Pick the permit type first; the submittal list depends on it.
  • Answer holds quickly, because the 10-day clock returns plans.
  • Keep the inspection log and any required certification forms on site.
  • Do not install deferred systems until the revision is approved.

Limits of this summary

The Department’s page is long and detailed. We have left out form-by-form submittal lists, sheet sizes, drawing scales and fee mechanics; read the Department page for those. Addresses, contacts and forms change. This page is general information, not legal advice or design advice. For a rejected plan, a denied permit or a deadline dispute, talk to a design professional and a Pennsylvania attorney.

Sources

PA Department of Labor and Industry, Plan Review and Inspection Requirements. Checked Nov. 23, 2026. Verify against the current Department page.

FAQ

Does L&I review residential permits in opt-out municipalities?

No. The Department does not approve residential work in opt-out municipalities, so that work goes through a certified third-party agency.

What happens if my plan package is missing information?

Minor gaps place the project in temporary holding, and if the requested information is not received within 10 calendar days, plans are returned.

Do I need a permit to demolish a building in an opt-out municipality?

The page says a demolition permit is required before demolishing any building or structure in an opt-out municipality, except where demolition is concurrent with a replacement building application.

When must fire alarm and sprinkler plans be submitted?

As plan revisions at least two weeks before installation, with a statement from the design professional in responsible charge.

This is a plain-English summary of what the official sources state, not legal advice. Regulations get amended and agencies and courts interpret them, so talk to a Pennsylvania attorney about your own situation before you rely on any of it.

Related: Pennsylvania guide · Work that doesn’t need a UCC permit · Pennsylvania building code · UCC opt-in vs opt-out.

Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.

Cite as: Muthler Landscaping & Construction, “L&I Plan Review and Inspection in Opt-Out Municipalities: Permit Types, Submittals and Inspection Paperwork,” https://muthlerlandscaping.com/state-guides/pennsylvania/ucc-lni-plan-review-permit-types-opt-out-municipalities/ (page updated November 23, 2026).