Pennsylvania Home Improvement Contract: Cancellation, Arbitration Clauses and Voidable Terms

The first half of Section 7 of Pennsylvania’s Home Improvement Consumer Protection Act (Act 132 of 2008, 73 P.S. 517.1 et seq., “HICPA”) lists what a contract must contain; we cover that on our required contract terms page. The second half, subsections (b) through (g), deals with what an owner can do after signing and which clauses a contractor should not put in the paper at all. This page uses the act as published by the General Assembly, checked on November 23, 2026. Verify against the current statute text before you draft or rely on any clause.

Quick answer

  • Rescission, 7(b): an individual can cancel without penalty within three business days of signing, wherever it was signed
  • Copy, 7(c): a completed copy goes to the owner at signing, free
  • Arbitration, 7(d): six formatting and content conditions, or a court may void the clause
  • Voidable clauses, 7(e): if the contract has any listed clause, the owner may void the contract
  • Recovery, 7(g): a compliant contractor may still seek the reasonable value of requested work

What is the three-day right to cancel?

Section 7(b) says an individual may rescind a home improvement contract without penalty within three business days of signing, no matter where it was signed. The emergency provisions of Section 7 of the Unfair Trade Practices and Consumer Protection Law are carved out. Notice of this right is one of the thirteen required contract items in Section 7(a)(13). The act’s wording is “three business days,” so a weekend does not count toward the period; check how your own calendar falls before telling a customer a date. Our deposit limits guide discusses the same right alongside the deposit cap.

Arbitration clauses: six conditions

Section 7(d) lets a court set aside an arbitration clause on any ground Pennsylvania law allows. If the contract has one, the act sets conditions, and a court may void the clause on either party’s motion filed before arbitration begins if they are not met:

ConditionParaphrase
1The text is in capital letters
2It is in 12-point boldface and sits on a separate page from the rest of the contract
3Each party has a separate line to show assent
4It takes effect only when both sign and date it, and the date is the execution date
5It says whether the decision is binding or can be appealed to the court of common pleas
6It says whether the facts, related documents and decision are confidential

The practical lesson: an arbitration paragraph buried in the middle of a form is exactly what this subsection is aimed at. If you want arbitration, give it its own page, its own signature lines and clear answers on binding effect and confidentiality. If you do not need it, leaving it out removes a point of attack.

Which clauses let an owner void the contract?

Section 7(e) says the owner may void the contract if it contains any of these:

  • a hold harmless clause;
  • a waiver of federal, state or local health, life, safety or building code requirements;
  • a confession of judgment clause;
  • a waiver of the right to a jury trial;
  • an assignment of, or order for, wages or other pay for services;
  • a provision barring the owner from raising claims or defenses arising from the contract;
  • a provision awarding the contractor attorney fees and costs;
  • a clause relieving the contractor of liability for its or its agents’ acts in collecting payments or repossessing goods;
  • a waiver of any rights under the act; and
  • an automatic or recurring renewal provision, unless the owner can opt out by first-class mail postmarked no later than three business days before renewal, that procedure is clearly and conspicuously disclosed, and the contractor must mail a notice not earlier than 20 days and not later than ten days before renewal describing the renewal and the right to cancel.

The subsection also has a reserved paragraph. Two items surprise contractors most: the ban on contractor attorney-fee clauses and the ban on jury waivers. Stock forms copied from commercial work often include both. Review any form against this list before using it with a homeowner. Because voiding the contract is the owner’s option, the risk sits with the contractor.

Does the owner get a copy?

Section 7(c) says the contractor or salesperson must hand over a completed copy when the contract is executed, free of charge, including all required notices. A blank or partly filled form does not meet that description.

Retailers and the recovery safety valve

Section 7(f) applies a parallel set of contract requirements to home improvement retailers with a net worth over $50,000,000 and to their employees who do not perform home improvements. It is not aimed at a small contracting company. Section 7(g) matters more to contractors: one who complied with subsection (a) may still recover for work performed, based on the reasonable value of services the owner requested, if a court finds that denial would be inequitable.

What to do with this

  • Contractors: audit your form against the 7(e) list and remove anything on it before the next homeowner contract.
  • Contractors: if you keep arbitration, format it to the six conditions, and have an attorney confirm the wording.
  • Contractors: record the signing date and tell the owner when the three business days end.
  • Owners: keep your copy, and note the date you signed.
  • Both sides: if a dispute turns on a voidable clause, talk to a Pennsylvania attorney before sending any notice.

Sources

Home Improvement Consumer Protection Act, Act 132 of 2008, Section 7, text published by the Pennsylvania General Assembly (PDF). Checked Nov. 23, 2026. Verify against the current statute text before relying on any clause or deadline.

FAQ

How long does a homeowner have to cancel a Pennsylvania home improvement contract?

Section 7(b) gives an individual three business days from signing to rescind without penalty, wherever the contract was signed, with an exception for emergency work under the Unfair Trade Practices and Consumer Protection Law.

Can a home improvement contract include an attorney fee clause for the contractor?

Section 7(e) lists a provision awarding the contractor attorney fees and costs among the clauses that let the owner void the contract.

What format must an arbitration clause follow?

Section 7(d) calls for capital letters, 12-point boldface on a separate page, separate assent lines, effect only when both sign and date it, and statements on whether the decision is binding or appealable and whether it is confidential.

Questions about a project in central Pennsylvania? Muthler Landscaping & Construction LLC, 913 Bellefonte Avenue, Lock Haven, PA 17745, PA HIC #PA212584, (570) 397-9800.

This is a plain-English summary of what the official sources state, not legal advice. Statutes get amended and courts interpret them, so talk to a Pennsylvania attorney about your own situation before you rely on any of it.

Related: Pennsylvania guide · Required contract terms · Contractor deposit limits · HICPA prohibited acts.