Deck beam sizing: reading the DCA 6 span tables

The beam is what turns a row of joists into a deck on posts. The American Wood Council’s DCA 6 guide sizes beams with two span tables: Table 3A for built-up and solid dimension lumber, and Table 3B for glued laminated timber. Here is how to read them, with sample rows and the rules that sit around the tables.

Quick answer

Pick the beam by two inputs: the species and size of the beam, and the joist span it carries. The table returns the longest allowed distance between posts. Example from DCA 6 (2015 edition, p. 6): a 3-ply 2×10 southern pine beam carrying joists up to 6 ft spans 12 ft 9 in. between posts. Checked Nov. 23, 2026.

Sample rows from Table 3A (DCA 6, 2015 edition, p. 6)

BeamJoists to 6 ftTo 8 ftTo 10 ftTo 12 ftTo 14 ftTo 16 ftTo 18 ft
Southern pine, 2-2×1010′-1″8′-9″7′-9″7′-1″6′-6″6′-1″5′-9″
Southern pine, 3-2×1012′-9″11′-0″9′-9″8′-9″8′-3″7′-8″7′-3″
DF-L, hem-fir, SPF and others, 3×10 or 2-2×108′-1″7′-0″6′-3″5′-8″5′-3″4′-10″4′-5″
DF-L, hem-fir, SPF and others, 4×109′-8″8′-4″7′-5″6′-9″6′-3″5′-10″5′-5″
DF-L, hem-fir, SPF and others, 3-2×1011′-9″10′-2″9′-1″8′-3″7′-7″7′-1″6′-8″

These are selected rows only. The guide’s full table also has 2×6, 2×8 and 2×12 rows (p. 6), which we did not reproduce. The “others” group in the table is Douglas fir-larch, hem-fir, SPF, redwood, western cedars, ponderosa pine and red pine. The table assumes a 40 psf live load, 10 psf dead load, L/360 deflection, No. 2 grade lumber and wet service, and it assumes incising for Douglas fir-larch, hem-fir and SPF. Our text of the guide came through a text-extraction tool, so check any number you build from against the PDF page.

Glued laminated beams (Table 3B, p. 7)

ItemWhat the source states
Sample beamBalanced 24F-1.8E glulam, Douglas fir-larch or southern pine, 3-1/2 in. wide by 11-7/8 in. deep.
Spans by joist length17′-5″ (joists to 6 ft), 15′-10″ (8 ft), 14′-8″ (10 ft), 13′-9″ (12 ft), 13′-1″ (14 ft), 12′-6″ (16 ft), 12′-0″ (18 ft).
Other optionsUnbalanced and cedar glulam beams are also tabulated on p. 7.
Preservative factorIf the glulam is not treated with an oil-borne preservative, multiply the tabulated span by 0.89 (footnote 1).
Cap for footing designBeam spans are limited to 18 ft for footing design (footnote 5).

Rules around the tables

ItemWhat the source statesSource and edition
Beam overhang past a postUp to one-fourth of the beam span, written LB/4.AWC DCA 6, 2015 edition, p. 5
Joist bearingJoists either bear on the beam, with overhang limited to the lesser of the table overhang or one-fourth of the joist span, or hang from the beam side with hangers.AWC DCA 6, 2015 edition, pp. 5-7
Opposite sidesJoists must not frame into opposite sides of the same beam.AWC DCA 6, 2015 edition, pp. 5-7
Beam depth with hangersBeam depth must be at least the joist depth (footnote 4).AWC DCA 6, 2015 edition, p. 6
Ply nailingTwo rows of nails at 19 in. on center along each edge of the beam.Penn State handout, 2018 IRC, slide 38
SplicesLocated at an interior post.Penn State handout, 2018 IRC, slide 38
Beam cantileverUp to one-fourth of the actual beam span.Penn State handout, 2018 IRC, slide 38

How to use the tables in order

1. Find the joist span

Use the joist span from your joist table, face of support to face of support. Round up to the next column, not down. A joist span between two columns uses the longer column.

2. Pick a species and size

Read across to a beam that gives a post spacing at least as long as you want. If the number is short, go to a bigger beam, add a ply, or add a post.

3. Check the post and footing

The same beam span and joist span feed the post height and footing tables, so a longer beam span makes bigger footings. See post height limits and bracing.

Practical notes from the field

Treat the table as a ceiling, not a target. A beam that spans exactly the table distance leaves no margin for a post set a little off the layout line, so shortening a span by moving one post costs little and buys room for field error. The table values also assume the materials are the stated species and grade, so a mixed bundle of lumber is a reason to size up.

Plan the joist connection before you size the beam. If you hang joists from the beam side with hangers, the beam must be at least as deep as the joist, which rules out a shallow beam under a deep joist. If you bear the joists on top, the overhang rule applies. Never run joists in from both sides of one beam.

Keep the splice over a post. A built-up beam made from shorter boards is common, and the handout’s rule is that splices land at an interior post, not mid-span where the beam is working hardest. Stagger them so every ply does not break at the same post.

Edition caution, not engineering or legal advice. The sample numbers here come from AWC DCA 6, 2015 edition. The ply nailing and cantilever points come from Penn State’s handout on the 2018 IRC, and other sources we saw give different nailing patterns, so verify the figure with your code office. Pennsylvania’s UCC moved to the 2021 IRC effective Jan. 1, 2026, per our IRC rules page. We did not locate a 2021 edition of DCA 6 on awc.org. Use an engineer for a beam outside the tables.

Related: post-to-beam connections, joist spans and bearing and the beam glossary entry.

Questions

How far can a deck beam span between posts?

It depends on species, size and the joist span it carries. In DCA 6 (2015 edition, p. 6), a 3-ply southern pine 2×10 beam carrying joists up to 6 ft spans 12 ft 9 in. between posts, and the same beam carrying joists up to 18 ft spans 7 ft 3 in.

How far can a beam cantilever past the last post?

The AWC guide allows a beam to extend past a post by up to one-fourth of the beam span. Penn State’s handout says the same, one-fourth of the actual beam span.

Can joists frame in from both sides of a beam?

No. The AWC guide does not allow joists to frame in from opposite sides of the same beam.

Do glulam beams span farther than lumber beams?

Often they do. The sample 3-1/2 in. by 11-7/8 in. balanced glulam in Table 3B spans 17 ft 5 in. for joists up to 6 ft, versus 12 ft 9 in. for the sample 3-ply southern pine 2×10. Multiply by 0.89 if the glulam is not oil-borne treated.

Sources: American Wood Council, DCA 6 (2015 edition), pp. 5-7; Penn State Housing Research Center, deck design handout (2018 IRC), slide 38; our IRC rules page. Checked Nov. 23, 2026.

Muthler Landscaping & Construction · Lock Haven, PA

Planning a deck in central PA?

We build decks and site work across Clinton, Centre, Lycoming and Union counties, and we handle the permits that go with them.

Get a free estimatePennsylvania guide

Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.

Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.

Cite as: Muthler Landscaping & Construction, “Deck Beam Sizing: How to Read the DCA 6 Beam Span Tables,” https://muthlerlandscaping.com/state-guides/pennsylvania/deck-beam-sizing-dca6-tables/ (page updated November 23, 2026).