Philipsburg Borough, PA: Land Use and Zoning Permit, UCC Building Permit and Code Enforcement
Philipsburg Borough, in Centre County, posts its code chapters online, and the chapter text defines fences and retaining walls as structures. Its Code Enforcement page lists a Code Enforcement Officer, links the borough’s code chapters as PDFs, and the Chapter 5 PDF sets out two separate permits: a Uniform Construction Code (UCC) building permit and a local Land Use and Zoning Permit. This page paraphrases the borough’s Code Enforcement, Forms, home and Contact pages and the Chapter 5 PDF, and it says plainly where they are silent or disagree. Everything below was checked on November 23, 2026. For county-level offices, see our Centre County guide.
Quick answer
- Code Enforcement Officer: Rhonda Swartz, code@pburg.comcastbiz.net
- Borough office: 4 North Centre Street, Philipsburg, PA 16866, (814) 342-3440
- UCC building permit: Chapter 5, Part 1; the borough chooses its code official or agency by Council resolution
- Land Use and Zoning Permit: Chapter 5, Part 2; required for buildings and structures that do not need a UCC permit; “structure” is defined to cover fences and retaining walls
- Fees: set by Borough Council; the current schedule is on file with the Borough Secretary, and no amounts are posted online
- Start and finish: work must start within six months of issuance and be completed within 12 months
Who handles permits in Philipsburg?
The borough’s Code Enforcement page names Rhonda Swartz as Code Enforcement Officer and gives the email code@pburg.comcastbiz.net. The page lists no phone number, office hours or mailing address for the officer, and it points to the Contact page. The borough office is at 4 North Centre Street, Philipsburg, PA 16866, phone (814) 342-3440. The page does not name an enforcing agency for the UCC, so the chapter’s own language, covered below, is the best available source.
The two borough pages disagree on office hours. The home page says office hours are 7 AM to 3 PM, while the Contact page shows 07:30 am to 03:30 pm. Neither page says which is current, so call before you drive over.
The Land Use and Zoning Permit in Chapter 5, Part 2
Chapter 5 of the borough code, linked from the Code Enforcement page as a PDF, is where the local permit rules sit. Part 2, covering sections 5-201 to 5-207, says land use and zoning permits are required for certain buildings that do not need a UCC permit, so that all taxable improvements are assessed uniformly. It applies to construction of buildings and structures, and to renovations that would trigger reassessment, that do not require a UCC permit. The definitions section includes agricultural buildings, recreational cabins, utility and miscellaneous use structures, and it defines “structure” to cover fences and retaining walls.
Section 5-204 makes it unlawful to start or renovate a covered building without first getting a land use and zoning permit from the borough. Read that with care: Part 2 applies to work that does not need a UCC permit and is tied to reassessment, so whether a particular wall or fence is covered depends on the definitions and on the borough’s own reading. Our Pennsylvania retaining wall permit guide and fence law guide give the statewide background.
What an application must include and how long a permit lasts
Section 5-205 says applications must be written, on borough forms, and include:
- The names and addresses of the applicant, the owner and the contractor.
- The site location and map number.
- A description of the work with an estimated cost.
- A site plan showing existing and proposed structures with setbacks.
After a permit is issued, no changes to the work, the site plan or the submitted information may be made without borough approval. Section 5-207 says work must start within six months of permit issuance and be completed within 12 months. Construction counts as started with first concrete work, such as pouring slabs or footings, or any work past excavation. For structures without a basement or poured footings, the start includes first permanent framing or assembly, or affixing a prefabricated structure to its foundation.
Section 5-206 says every application must include a fee set by Borough Council from time to time, and a footnote says the current fee schedule is on file with the Borough Secretary. No fee amount is posted on the borough pages.
UCC building permits in Chapter 5, Part 1
Section 5-101 says the borough follows the Pennsylvania Construction Code Act and adopts the Uniform Construction Code (34 Pa. Code, Chapters 401 to 403) as its municipal building code. It says Borough Council decides by resolution, from time to time, whether to use a borough employee as code official, hire code officials or third-party agencies, join an intermunicipal agreement, contract with another municipality, or agree with the Pennsylvania Department of Labor and Industry for certain structures. An editor’s note says the borough currently uses the Centre County Council of Governments UCC Board of Appeals. UCC enforcement fees are set by Council resolution. The chapter does not name the agency that currently reviews and inspects building permits. Our UCC third-party agencies guide and UCC permit application guide explain the general arrangement.
Other permits listed by chapter title
The Code Enforcement page also lists, by chapter and part title only, curb cuts and driveway construction (Chapter 21, Part 3), sidewalk construction (Chapter 21, Part 2), opening and excavations in streets (Chapter 21, Part 1), swimming pool regulations (Chapter 23, Part 1), floodplain special permits (Chapter 8, Part 5), special exceptions and conditional uses, temporary uses, signs and variances in the zoning chapter, and a mobile home removal permit. Call the borough to confirm what they require, whom they apply to and what they cost. The borough’s Forms page lists a Zoning Certificate, an appeal request, a Safety Inspection Report and a parking permit for an individual under Code Enforcement, with no fees.
Where the documents disagree or are silent
- Office hours differ between the home page (7 AM to 3 PM) and the Contact page (7:30 am to 3:30 pm).
- Chapter 5, Part 2 cites Act 44 of 1999 in its findings, while Part 1 cites Act 45 of 1999 for the UCC; the chapter does not explain the difference.
- The Code Enforcement page does not name a UCC agency or list which projects need permits; the chapter text carries that detail.
- No fee amounts are posted; the fee schedule is on file with the Borough Secretary.
- The chapter sets no deadline for the borough to act on an application and does not name the official who issues land use and zoning permits.
- For the zoning chapter (Chapter 27), setbacks and the zoning map, call the borough.
Sources
Philipsburg Borough official pages, checked November 23, 2026: Code Enforcement, Forms, home page and Contact. Chapter 5, Code Enforcement, PDF linked from the Code Enforcement page, checked November 23, 2026. Rules, hours and phone numbers change, so confirm before you start.
FAQ
Does Philipsburg Borough treat fences and retaining walls as structures?
Chapter 5 of the borough code, linked from the borough’s Code Enforcement page, defines “structure” to cover fences and retaining walls for purposes of its land use and zoning permit rules. Whether a particular job is covered depends on the chapter’s scope, so confirm with the Code Enforcement Officer.
Who is the Philipsburg Code Enforcement Officer?
The borough’s Code Enforcement page names Rhonda Swartz and lists the email code@pburg.comcastbiz.net. The borough office phone is (814) 342-3440.
How long does a Philipsburg land use and zoning permit last?
Chapter 5, section 5-207 says work must start within six months of issuance and be completed within 12 months.
What does a permit cost in Philipsburg?
The chapter says fees are set by Borough Council and the current schedule is on file with the Borough Secretary. No amounts are posted on the borough pages.
This is a plain-English summary of what the municipality’s own pages state, not legal advice. Call the municipality to confirm, and check the PA UCC permit rules for any structure that needs a building permit.
Related: Pennsylvania guide · Centre County · Central PA permit fees · PA fence law · PA retaining wall permit · PA building code · UCC permit exemptions
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “Philipsburg Borough, PA: Land Use and Zoning Permit, UCC Building Permit and Code Enforcement,” https://muthlerlandscaping.com/state-guides/pennsylvania/philipsburg-borough-permits/ (page updated November 23, 2026).