State guides · Pennsylvania · Building code
How long a town has to decide your building permit
Pennsylvania sets the clock. Once you file a complete application for a home project, the municipality has a fixed number of business days to grant or deny it, and a missed deadline has a consequence.
One- and two-family homes and accessory structures: 15 business days, or 5 if a licensed design professional certifies the plans comply. Other buildings: 30 business days. For homes, missing the deadline means the application is deemed approved. Checked Nov. 22, 2026.
The deadlines
| Application | Deadline to grant or deny |
|---|---|
| One- or two-family dwelling, or utility and miscellaneous structure | 15 business days after filing |
| Same, with plans certified by a licensed or registered design professional | 5 business days |
| All other construction permits | 30 business days |
| Certificate of occupancy, one- and two-family | 5 business days after a final inspection report shows compliance (10 in first-class cities) |
Source: section 502(a)(1) of the Construction Code Act and 34 Pa. Code § 403.63(a). The parties can agree in writing to extend a deadline.
If the town misses the deadline
For one- and two-family and utility permits, failing to act in time means the application is deemed approved (section 502(a)(3); § 403.63(a)).
The regulation says a permit doesn’t protect anyone from prosecution or legal action for violations, and the official can suspend or revoke a permit issued in error or on incomplete information.
If the town does nothing, don’t just start digging. Ask the code office to confirm the filing date and status in writing first.
If your permit is denied
A denial must be in writing, identify the parts that don’t comply and cite the code provisions (§ 403.63(a); section 502(a)(2)). You can fix the plans and refile, or appeal; see our board of appeals guide.
What can still hold you up
- The permit isn’t valid until the required fees are paid (§ 403.63(k)).
- If the property needs access to a state highway, the permit must note that a separate highway occupancy permit is required before driveway access is allowed (§ 403.63(d)). Section 502(b) gives PennDOT 60 days on those permits, and failure to act means deemed issuance. See our PennDOT driveway permit guide.
- Zoning and floodplain approvals are separate and aren’t on the building code clock.
The clock runs on a complete application. For what goes in it, see the UCC permit application. For fees, see central PA permit fees.
Questions
How long does a Pennsylvania town have to approve a building permit?
15 business days for one- and two-family homes and accessory structures, or 5 business days if a licensed design professional certifies the plans. Other permits get 30 business days.
What happens if the town doesn’t respond in time?
For one- and two-family and utility permits, the application is deemed approved.
Does the town have to explain a denial?
Yes. The denial must be in writing, identify what doesn’t comply and cite the code provisions.
Can the deadline be extended?
Yes, by written agreement between the parties.
Sources: Construction Code Act, section 502; 34 Pa. Code § 403.63, Permit review. Checked Nov. 22, 2026. The Justia page carries a note that it may not reflect the current regulation.
Muthler Landscaping & Construction · Lock Haven, PA
Planning a project in central PA?
We build patios, walls, drainage and site work across Clinton, Centre, Lycoming and Union counties, and we handle the permits that go with them.
Get a free estimatePennsylvania guideMuthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “Pennsylvania Building Permit Review Deadlines,” https://muthlerlandscaping.com/state-guides/pennsylvania/ucc-permit-review-deadlines/ (page updated November 23, 2026).