34 Pa. Code 403.64: Residential Building Inspections, the Four Required Inspection Areas and the Final Report
When a homeowner or contractor in Pennsylvania pulls a building permit for a house, addition or deck, the permit is only the start. Section 403.64 of Title 34 of the Pennsylvania Code is the residential inspection rule in the Uniform Construction Code (UCC). It says who inspects, what the permit holder must do to make an inspection happen, which inspection areas are mandatory, and who gets a copy of the final report. This page walks through the section subsection by subsection, as shown on Cornell’s Legal Information Institute and checked November 23, 2026. Please verify against the current regulation. For the commercial side of the same topic, see our page on sections 403.45 and 403.86.
Quick answer
- 403.64(a): a construction code official inspects all construction for which a permit was issued, and the permit holder must make the work accessible
- 403.64(b): the permit holder or an authorized agent notifies the official when work is ready and provides access
- 403.64(d): required inspection and report areas are foundation; plumbing, mechanical and electrical; frame and masonry; and wallboard
- 403.64(f): a final inspection of the completed work, with a final report on UCC compliance
- 403.64(g): a third-party agency under contract with the permit holder sends the final report to the owner, the builder and the builder’s designated lender
What does 403.64(a) require of the official and the permit holder?
Subsection (a) is short but sets the tone. A construction code official shall inspect all construction for which a permit was issued, and the permit holder must make the construction accessible for inspection. The subsection also says an inspection does not bar prosecution or other legal action for violations of the UCC. In plain English, passing an inspection is not a pardon. If a violation shows up later, an earlier sign-off does not stop enforcement. For a contractor, that means you cannot treat an inspector’s approval as a legal shield for work that was built wrong. The section reports no deadlines or numbers; those, where they exist, come from other sections and from the municipality or agency doing the inspecting.
The word “accessible” matters on a real job. If drywall is hung over wiring before the rough-in inspection, or backfill covers a foundation drain before the foundation inspection, the work is no longer accessible and the official can ask you to open it up. The regulation puts that burden on the permit holder, not the inspector.
Who calls for the inspection, and what does the official owe in return?
Subsection (b) says the permit holder, or an authorized agent, must notify the construction code official when the work is ready for inspection and must provide access. Subsection (c) completes the loop: the official must notify the permit holder whether the construction complies with the UCC or fails to comply. So the process runs in two directions. You request, the official inspects, and the official tells you the result. The section does not say how the notice must be given (phone, portal or in writing) or how fast the official must respond. Those mechanics vary by municipality and by third-party agency, so ask for the inspection request procedure when you pick up the permit. Our general page on required UCC inspections covers the practical sequence.
Which inspections are required under 403.64(d)?
Subsection (d) says the official must make inspections and file reports on UCC compliance in four areas:
| Area under (d) | What it generally means on a residential job |
|---|---|
| 1. Foundation | Footings, foundation walls and related work, before they are covered |
| 2. Plumbing, mechanical and electrical systems | The trade systems, typically at rough-in stage while they are still visible |
| 3. Frame and masonry | Structural framing and masonry work |
| 4. Wallboard | The stage involving wallboard installation |
The middle column is our plain-language gloss, not regulation text. The regulation lists only the four area names. For the exact stage of each inspection, follow the inspection list the official gives you with the permit and the adopted code requirements. Subsection (e) adds that the official may conduct other inspections to check compliance with the UCC or municipal ordinances. That one is discretionary: the official can add an inspection, for example a footing check or an insulation check, even though it is not one of the four in (d). Do not assume that the four areas are the only visits you will get.
What happens at final inspection under 403.64(f) and (g)?
Under (f), the official must conduct a final inspection of the completed work and file a final inspection report indicating UCC compliance. That report matters because it feeds the certificate of occupancy process, which we cover on our certificate of occupancy page. Subsection (g) adds a distribution rule: a third-party agency under contract with the permit holder must send a copy of the final inspection report to the property owner, the builder, and the lender the builder designates. This rule is aimed at the third-party agency situation, which occurs in opt-in and opt-out municipalities where a certified agency does the inspecting. Our page on UCC third-party agencies explains who they are.
For a homeowner, the practical point is to ask whoever is inspecting your project that the final report be sent to you, and to keep the copy. Lenders, insurers and future buyers often ask for it. For a builder, it is a reminder to name your lender with the agency so the lender receives the report.
How does 403.64 connect to the rest of the UCC?
Cornell’s page lists the sections that cite 403.64: 403.61 (residential buildings), 403.102 (municipalities electing to enforce the UCC) and 403.103 (municipalities electing not to enforce the UCC). That tells you the inspection rule is part of the residential chapter and is carried into both the opt-in and opt-out frameworks. Whether a given municipality enforces the UCC itself, or leaves residential work to private agencies, is covered on our opt-in versus opt-out page. In every case the permit holder still has to ask for inspections and keep the work open until they are done.
Practical steps for owners and contractors
- Get the list of required inspections when you pick up the permit, and keep it on site.
- Schedule each inspection before covering foundation, trade rough-in, framing or wallboard stages.
- Do not conceal work early to save time; the burden to keep it accessible is on the permit holder under (a).
- Ask the inspector for the result in writing after each visit, since (c) requires the official to notify you of compliance or failure.
- Request the final report and confirm that the owner, the builder and the designated lender each get a copy where a third-party agency is used.
- If you disagree with an official’s decision, see our page on the UCC board of appeals rather than skipping a correction.
Limits of this summary
This page does not cover the amendment history of 403.64. Section 403.64 sits alongside the Construction Code Act and other chapters, so a municipality’s own ordinance, a third-party agency contract or a lender may impose extra inspections or paperwork. Where a dispute over whether work passed or failed could cost real money, talk to a Pennsylvania attorney.
Sources
34 Pa. Code 403.64 (Cornell LII). Checked Nov. 23, 2026. Verify against the current regulation text.
FAQ
Which inspections does 403.64 require for residential construction?
Under 403.64(d), the official must inspect and file reports on foundation; plumbing, mechanical and electrical systems; frame and masonry; and wallboard, plus a final inspection under (f). Verify the current text.
Who has to ask for an inspection?
Subsection (b) says the permit holder or an authorized agent must notify the construction code official when the work is ready and provide access to it.
Does passing an inspection protect me from later enforcement?
No. Under subsection (a), an inspection does not bar prosecution or other legal action for violations of the UCC.
Who receives the final inspection report?
Under (g), a third-party agency under contract with the permit holder must send a copy to the property owner, the builder and the lender the builder designates.
This is a plain-English summary of what the official sources state, not legal advice. Regulations get amended and agencies and courts interpret them, so talk to a Pennsylvania attorney about your own situation before you rely on any of it.
Related: Pennsylvania guide · Work that doesn’t need a UCC permit · Pennsylvania building code · Residential permit exemptions.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “34 Pa. Code 403.64: Residential Building Inspections, the Four Required Inspection Areas and the Final Report,” https://muthlerlandscaping.com/state-guides/pennsylvania/ucc-34-pa-code-403-64-residential-inspections-final-report/ (page updated November 23, 2026).