Benner Township is in Centre County, with its office on Buffalo Run Road. Its Zoning and Permits page lays out a clear order of steps: zoning permit first, then a building permit through one of two authorized inspection agencies, with sewage and driveway permits added where they apply. This page paraphrases that page, the township’s application forms page and the Keystone Inspection Agency application, all checked on November 23, 2026. County offices are on our Centre County guide.
Quick answer
- Step 1: zoning permit before altering, adding to or erecting a building, or changing its use
- Step 2: building permit, with a zoning permit in hand, through Penns Valley Code Enforcement Agency or Keystone Inspection Agency
- Also possible: sewage permit, Highway Occupancy Permit for a driveway
- Township office: 814-355-1419, 1224 Buffalo Run Road
- Fee amounts: not stated on the zoning or forms pages
How does permitting work in Benner Township?
The township says its Zoning Officer, Michael Lesniak, serves through the Penns Valley Code Enforcement Agency. The officer reviews applications for compliance with the Zoning Ordinance and may issue permits for by-right uses. For conditional uses the officer advises the Board of Supervisors, and for special exceptions the officer advises the Zoning Hearing Board. The officer also investigates complaints about possible violations, and the page says most are resolved without a fine.
The township office is at 1224 Buffalo Run Road (the page spells the town Bellfonte), main line 814-355-1419, with business hours of Monday through Friday, 8 AM to 4 PM. The zoning page says the zoning officer is in the township office on Wednesdays from 8 AM to noon, while the forms page says 9 a.m. to noon, so confirm the hour by phone. The page also lists Millheim office hours of Tuesday through Thursday, 1 PM to 5 PM. The forms page says permits are dropped off at the township office for processing.
When is a zoning permit required?
The page says a zoning permit is required before altering, adding to or erecting any building or part of one, before changing the use of a building or land, and before changing or extending a nonconforming use. It says work may not begin until a permit is issued. It also says ground-mounted solar requires conditional approval.
The page does not name decks, sheds, fences or retaining walls individually, so it does not tell you how a ground-level patio or a low wall is treated. The first trigger, altering or erecting any building or part of one, is broad, but whether a given hardscape item counts as a building or structure is a question for the zoning officer. For statewide context, see our shed permit guide and retaining wall permit guide.
Building permit: agencies, plans and add-ons
To get a building permit you must first obtain a zoning permit, and the township page says to submit three sets of plans. It adds that other items may be required: a sewage permit for new construction or renovations that add bedrooms, a Highway Occupancy Permit from the Roadmaster when a driveway is added or when Centre County requires it, and a site plan or plot plan showing distances from property lines.
The page says the Penns Valley Code Enforcement Agency and Keystone Inspection Agency are authorized by the township to issue township building permits. Penns Valley is listed at (814) 349-8177, info@pvcode.org. Keystone Inspection Agency’s own application lists 248 N. Main Street, Suite 1, Pleasant Gap, PA 16823, office phone 814-359-3333. Note that the township page asks for three sets of plans, while the Keystone application asks for two sets of construction documents, so ask which count the agency you choose wants. See our UCC third-party agencies guide for how these agencies work statewide.
What the Keystone application asks for
The Keystone application covers new construction, addition, alteration, repair, relocation, change of use, plumbing, mechanical, electrical, sprinkler system, demolition and swimming pool. For residential work it asks for approved zoning, water, sewer and driveway permits, a detailed site plan, engineer design specifications and a certificate of insurance. The form states a minimum footer depth of 36 inches below grade, including for pole buildings and decks, and says the owner and applicant must locate easements, rights-of-way and flood hazard areas. It also says a permit does not authorize violating any local code, and that a certificate of appropriateness may be required in a historical district. The applicant signs to follow the Uniform Construction Code (Act 45 of 1999). Our frost line depth guide explains why footer depth matters for decks and piers.
Signs, driveways and other permits
The township page says signs are not allowed in the right-of-way and that signs on Pennsylvania state roads require PennDOT approval. A peddler’s permit is required, with details in the ordinance. The forms page also links a Driveway Application Form (a Highway Occupancy Permit application), a conditional use application and a variance hearing application. For state-road driveways, see our PennDOT driveway permit guide.
Forms and fees
The township posts a Zoning Permit Application, a Penns Valley Building Permit Application, a Keystone Building Permit Application, a swimming pool and a solar building permit application (both link to the same file on the page), a sign permit application, a peddler permit application and a variance hearing application. It also posts the Zoning Map, Zoning Ordinance (amended 9/30/24), Floodplain Ordinance, Street Standards and the Spring Creek Canyon Overlay. A Zoning Fee Schedule dated 02-2021 is linked, but no fee amounts appear on the zoning or forms pages, and we do not quote any.
What the township does not state
- Whether decks, sheds, fences or retaining walls specifically need zoning or building permits.
- Fee amounts and review times.
- Setbacks and lot coverage (found in the Zoning Ordinance PDF).
- The Millheim office address.
- Stormwater permit steps (not on the zoning page; see the conservation district resources).
See our conservation district guide and stormwater plan rules for earth-disturbance background.
Sources
Benner Township official pages, checked November 23, 2026: Zoning and Permits, Application Forms, and the Keystone Inspection Agency building permit application hosted on the township site. Rules and phone numbers change, so confirm before you start.
FAQ
Do I need a zoning permit before a building permit in Benner Township?
Yes. The township page says you must first obtain a zoning permit before applying for a building permit.
Who issues building permits in Benner Township?
The township page says Penns Valley Code Enforcement Agency and Keystone Inspection Agency are authorized to issue township building permits.
Who is the zoning officer in Benner Township?
The township page lists Michael Lesniak, serving through the Penns Valley Code Enforcement Agency.
Are Benner Township permit fees posted?
A Zoning Fee Schedule dated 02-2021 is linked, but the township’s pages state no amounts.
This is a plain-English summary of what the municipality’s own pages state, not legal advice. Call the municipality to confirm, and check the PA UCC permit rules for any structure that needs a building permit.
Related: Pennsylvania guide · Centre County · Bellefonte Borough · UCC opt-in and opt-out · PA building code · PA fence law.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “Benner Township, PA: Zoning Permit, Building Permit Agencies and Driveway Rules,” https://muthlerlandscaping.com/state-guides/pennsylvania/benner-township-permits/ (page updated November 23, 2026).
Get an email when your state’s rules change
We re-check every entry against official sources. Tell us your state and we’ll email you when something changes.