34 Pa. Code 403.45 and 403.86: UCC Inspections, the Final Inspection Report and the Official’s Right of Entry
Section 403.45 of the Pennsylvania regulations says how inspections work on commercial construction under the Uniform Construction Code (UCC), and Section 403.86 says when a code official may enter a property to inspect. Together they answer three common questions on a job: who has to ask for the inspection, what the final inspection must cover, and what the official may do if the owner is not on site. This page walks through both sections, as they appear on Cornell’s Legal Information Institute, checked November 23, 2026. Verify every detail against the current regulation. The residential inspection section, 403.65, is not part of this page, and the residential rules may differ.
Quick answer
- 403.45(c): the permit holder or agent notifies the official when work is ready and keeps the work accessible and exposed
- 403.45(d): the official tells the permit holder whether the construction complies or fails to comply
- 403.45(e): a final inspection and a final inspection report covering seven areas of the UCC
- 403.86: entry during normal business hours or at an agreed time, with credentials and permission, and not into an unoccupied building after hours without the owner’s permission
- No fixed days: the text gives no day-based deadline for scheduling inspections
What does 403.45 require of the official and the permit holder?
Subsection (a) says a construction code official must inspect to confirm the construction matches the approved permit and the UCC. Under (b), before issuing a permit a building code official may examine the buildings, structures, facilities or sites tied to the application; the word is “may,” so it is discretionary. Subsection (c) puts a duty on you: the permit holder or authorized agent must notify the official when work is ready for inspection and provide access, and the work must stay accessible and exposed for inspection. Inspections generally occur during normal hours at the site, unless the permit holder or agent requests or agrees to another time, and may proceed under 403.86. This is why a code official can fail an inspection simply because a footing was backfilled or a wall was closed in before the visit. Our required inspections page lists the typical inspection stages.
What is the final inspection report under 403.45(e)?
Under (d) the official must notify the permit holder whether the construction complies with the UCC or fails to comply. Under (e) the official must conduct a final inspection of the completed work and file a final inspection report. The report must indicate that each of seven areas met UCC requirements:
| Item | Area on the report | Cross-reference |
|---|---|---|
| (e)(1) | General building | 401.7(6) |
| (e)(2) | Electrical | 401.7(7) |
| (e)(3) | Plumbing | 401.7(9) |
| (e)(4) | Accessibility | 401.7(11) |
| (e)(5) | Fire protection | 401.7(6) |
| (e)(6) | Mechanical | 401.7(8) |
| (e)(7) | Energy conservation | 401.7(10) |
The table cites 401.7(6) for both general building and fire protection, so check the current text. The final report matters because it is the document that supports the certificate of occupancy, which we cover on our certificate of occupancy regulation page. Subsection (f) adds a narrow point: a code administrator may act in place of a lumber grading or inspection agency to satisfy section 2303.1.1 of the 2021 International Building Code, or its successor. The text gave no deadline for when the final report must be filed.
When may an official enter a property under 403.86?
Subsection (a) says an official may enter a building, structure or premises during normal business hours, or at a time the owner or owner’s agent agrees to. The purposes are UCC inspections, enforcing the UCC, or a reasonable-cause belief that a condition violates the UCC or is unsafe. Under (b) the official may enter after presenting credentials to the occupant and receiving permission. Under (c) the official may not enter an unoccupied building, structure or premises, or enter after normal business hours, without permission from the owner or owner’s agent. Under (d) the official may seek help from a law enforcement agency to gain entry to enforce the UCC when there is reasonable cause to believe the premises is unsafe. Under (e) the section is to be used together with the Fire and Panic Act.
How do inspections connect to the rest of the enforcement process?
An inspection that finds a problem leads to the steps in 403.82 and 403.83, where the official discusses results with the permit holder and may issue a written notice of violations. Those steps are on our enforcement regulation page. If a municipality has chosen not to enforce the UCC, inspections run differently; see our opt-in and opt-out guide and third-party agencies page.
What owners and contractors can do with these sections
- Call for each inspection before covering the work, and keep the work exposed until the official has seen it.
- Keep a log of each call and each result, because 403.45(d) says the official must tell you whether the work complies.
- Ask the code office how it wants inspection requests made and how much notice it needs, since the text sets no days.
- Be present, or name an agent, so the official has someone to give credentials to under 403.86(b).
- Before the final inspection, check that every area on the seven-item report is ready, including accessibility and energy.
Sources
34 Pa. Code 403.45 (Cornell LII) and 403.86 (Cornell LII); final regulation amending 403.45, IRRC Regulation #12-125 (IRRC), published as final Nov. 8, 2025, effective Jan. 1, 2026. The Cornell LII copy had not yet reflected the 2025 amendment when checked Nov. 23, 2026. Verify against the current regulation, which has been amended.
FAQ
Who has to schedule a UCC inspection?
Section 403.45(c) says the permit holder or authorized agent must notify the official when work is ready for inspection, provide access and keep the work accessible and exposed.
What does the final inspection report cover?
Section 403.45(e) lists general building, electrical, plumbing, accessibility, fire protection, mechanical and energy conservation. Verify the current text.
Can a code official walk onto my property without permission?
Section 403.86 allows entry during normal business hours or at an agreed time with credentials and permission, but not into an unoccupied building or after hours without the owner’s or agent’s permission. A different rule lets the official seek law enforcement help when there is reasonable cause to believe premises are unsafe. Ask an attorney about a specific entry.
How many days does the code office have to inspect?
Section 403.45 gives no day-based deadline for scheduling inspections or filing the final report. Ask your code office about its timing.
This is a plain-English summary of what the official sources state, not legal advice. Regulations get amended and agencies and courts interpret them, so talk to a Pennsylvania attorney about your own situation before you rely on any of it.
Related: Pennsylvania guide · Required inspections · Pennsylvania building code · UCC opt-in vs opt-out.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “34 Pa. Code 403.45 and 403.86: UCC Inspections, the Final Inspection Report and the Official’s Right of Entry,” https://muthlerlandscaping.com/state-guides/pennsylvania/ucc-34-pa-code-403-45-403-86-inspections-final-report-right-of-entry/ (page updated November 23, 2026).