34 Pa. Code 403.81 to 403.84: Stop Work Orders, Violation Notices, Orders to Show Cause and Unsafe Buildings
When a Pennsylvania building code official finds a problem, the Uniform Construction Code (UCC) regulations set a ladder of responses in 34 Pa. Code Sections 403.81 to 403.84. The ladder runs from a written stop work order, through a notice of violations and an order to show cause, to a vacate order for an unsafe building. Each step has rules on how the order must be served, how long the owner has to answer, and what a pending appeal does. This page walks through the four sections, as they appear on Cornell’s Legal Information Institute, checked November 23, 2026. Verify every number, service method and deadline against the current regulation. Section 403.85 on records and Section 403.86 on entry are separate; entry is covered on our inspections regulation page.
Quick answer
- 403.81: a written stop work order stating the reasons and the conditions for resuming, served by certified mail or in person
- 403.82: after an inspection finds a violation, the official discusses it and may issue a written notice ordering correction within a reasonable period
- 403.83: an order to show cause gives the owner 30 days to file a written answer; a pending appeal, variance or extension request stays the enforcement action
- 403.84: an unsafe building must be ordered vacated, with a posted notice at each entrance, and the order stays until the condition is corrected
- Penalties: continuing work after service of a stop work order may bring penalties under section 903 of the act
What does a stop work order under 403.81 involve?
Subsection (a) says a building code official may issue a written stop work order if the official determines that construction violates the UCC or is being performed in a dangerous or unsafe manner. The order must state the reasons and list the conditions required before construction can resume. Under (b) it is served on the permit owner or the owner’s agent by certified mail or personal service. Under (c), a person who keeps building after service may be subject to penalties under section 903 of the act (35 P.S. 7210.903), except for work necessary to remove a violation or unsafe condition. The official may also seek enforcement of the order in a court of competent jurisdiction. Our Sections 901 to 903 page covers the penalty provision, and our violations and fines page covers the practical side.
How does the violation notice in 403.82 work?
Section 403.82 has three steps. First, the official discusses the inspection results with the permit holder when the inspection is complete. Second, the official may issue a written notice of violations to the permit holder, describing the violations and ordering correction within a reasonable period the official sets. If a violation involves an unsafe building, structure or equipment, the official must follow 403.84. Third, after the compliance date the official inspects to see whether the violation was corrected. If it was, the order is closed. If not, the official may issue an order to show cause under 403.83 to the owner. This means a notice of violations is a chance to fix the problem before the process escalates, which is why a call back to the official is worth making.
What is an order to show cause under 403.83?
Subsection (a) lets the official start proceedings to close or vacate a building, structure or equipment that violates the UCC by issuing an order to show cause to the owner or the owner’s agent. Under (b) the order must state the grounds and list the alleged violations, warn that the property may be closed or vacated, and give 30 days to submit a written answer, served by certified mail or in person. Under (c), within 30 days of service the owner may file a written answer that admits or denies each allegation, states the facts, legal points or code interpretations relied on, and may request a variance or more time. The official must forward variance, extension or interpretation appeals to the board of appeals within 5 business days; requests involving accessibility go to the Department within the same period. Under (d) and (e), the board or Department takes jurisdiction and combines the answer with any pending request, and a pending request stays the enforcement action.
| Step | Section | Key number or rule |
|---|---|---|
| Stop work order | 403.81 | Written; certified mail or personal service |
| Notice of violations | 403.82 | Correction within a reasonable period the official sets |
| Order to show cause | 403.83 | 30 days to answer; forwarding of appeals within 5 business days |
| After the answer | 403.83(f) | If no earlier appeal, the official may issue a stop work order, vacate or close, abate or modify, or order other protective action |
| Unsafe building | 403.84 | Vacate order; notice at each entrance |
After an extension or other compliance period ends, 403.83(g) requires an inspection. If the work still violates the code, the official may issue an order vacating or closing the building or taking equipment out of operation, served by certified mail or in person.
What makes a building unsafe under 403.84?
Subsection (a) says an official may find a building, structure or equipment unsafe because of inadequate egress, inadequate light or ventilation, fire hazard, other dangers to life or public welfare, illegal or improper occupancy, or inadequate maintenance. A vacant building that is not secured against entry is automatically unsafe. If an unsafe condition exists the official must order the building vacated. The notice goes to the owner, owner’s agent or person in control, includes the vacate order and describes the conditions and required repairs, and is served by certified mail or personal delivery to the last known address; if that fails, the notice is posted at the entrance or on the equipment. When a building is ordered vacated, a notice is posted at each entrance saying the structure is unsafe and occupancy is prohibited, and the official may not rescind the order until the owner corrects the condition. Under (f), the Department may seal an elevator under section 105(c)(1) of the act, and only the Department may remove the seal; see our Section 105 page.
What owners and contractors can do with these sections
- Read a stop work order for its stated conditions, and do only the work needed to remove the violation until the official releases it.
- Answer a notice of violations in writing, and keep proof of the correction.
- Calendar the 30-day answer period from the day an order to show cause is served, not the day you read it.
- If you plan to appeal, remember a pending request stays enforcement of a correction order under 403.122, but actions under 403.84 cannot be stayed.
- For an unsafe-building order or any penalty, talk to a Pennsylvania attorney right away.
Sources
34 Pa. Code 403.81 (Cornell LII), 403.82 (Cornell LII), 403.83 (Cornell LII) and 403.84 (Cornell LII). Checked Nov. 23, 2026. Verify against the current regulation, which has been amended.
FAQ
Who can issue a stop work order under the UCC?
Section 403.81(a) says a building code official may issue a written stop work order if construction violates the UCC or is performed in a dangerous or unsafe manner, stating the reasons and the conditions for resuming.
How long do I have to answer an order to show cause?
Section 403.83(b) and (c) give the owner or agent 30 days from service to file a written answer. A pending variance, extension or appeal request stays the enforcement action.
Can I keep working after a stop work order?
Continuing after service may bring penalties under section 903 of the act, except for work necessary to remove a violation or unsafe condition. Ask a Pennsylvania attorney about your situation.
What makes a vacant building unsafe?
Under 403.84(a), a vacant building that is not secured against entry is automatically unsafe, and an unsafe building must be ordered vacated.
This is a plain-English summary of what the official sources state, not legal advice. Regulations get amended and agencies and courts interpret them, so talk to a Pennsylvania attorney about your own situation before you rely on any of it.
Related: Pennsylvania guide · Board of appeals · Pennsylvania building code · UCC opt-in vs opt-out.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “34 Pa. Code 403.81 to 403.84: Stop Work Orders, Violation Notices, Orders to Show Cause and Unsafe Buildings,” https://muthlerlandscaping.com/state-guides/pennsylvania/ucc-34-pa-code-403-81-403-84-stop-work-violations-unsafe-buildings/ (page updated November 23, 2026).
Get an email when your state’s rules change
We re-check every entry against official sources. Tell us your state and we’ll email you when something changes.