Pennsylvania Prevailing Wage Act: When a $25,000 Public Project Triggers Wage Rates
A contractor who bids on a township, school district, county or state job in Pennsylvania may have to pay workers a minimum wage rate set by the state, not the rate the company normally pays. That is the Pennsylvania Prevailing Wage Act (Act 442 of 1961, 43 P.S. 165-1 et seq.). This page draws on the act as published by the General Assembly and the Department of Labor and Industry’s prevailing wage FAQ, checked November 23, 2026. Verify every threshold and section number against the current statute text and the department’s own pages. This page is for contractors deciding whether to bid public work; it is not advice on any specific project.
Quick answer
- Covered work: construction, reconstruction, demolition, alteration, custom fabrication and repair other than maintenance, under contract and paid at least partly with public body funds, estimated total cost over $25,000 (Section 2)
- No splitting: the department says a project cannot be divided to get under the threshold
- Rates: set by the Department of Labor and Industry by craft and locality, and written into bid documents
- Contractor duties: keep wage records, post rates at the job site, and file sworn statements before final payment
- Intentional violations: can mean three years of debarment from public work
Which projects does the act cover?
Section 2 defines public work as construction, reconstruction, demolition, alteration, custom fabrication and repair work, other than maintenance work, done under contract and paid for in whole or in part from public body funds, where the estimated total project cost is more than $25,000. A public body is the Commonwealth, its political subdivisions, authorities created by the General Assembly and their agencies and instrumentalities. The department’s FAQ adds that the public body need not be a party to the contract, and that the total project cost, not the size of the public contribution, decides coverage.
The FAQ also describes a separate $100,000 line for locally funded highway and bridge projects contracted after January 1, 2014. That figure comes from the FAQ only, so check it with the department before bidding road work.
| Topic | What the sources report |
|---|---|
| Threshold | Estimated total cost over $25,000 (statute Section 2; department FAQ) |
| Maintenance | Repair of existing facilities that does not change size, type or extent is outside the act (Section 2) |
| Not maintenance, per FAQ | In-kind sidewalk replacement, roof replacement, road milling and replacement, manhole repair, painting beyond minor imperfections |
| Residential rehabilitation | Excluded from public work; residential property means fewer than eight units (Section 2) |
| Federal projects | Section 15 says the act does not apply to work covered by the Davis-Bacon or Walsh-Healey Acts |
| Workmen | Laborers, mechanics, skilled and semi-skilled workers and apprentices employed by a contractor or subcontractor on the project |
How do the wage rates work?
Under Section 7, the Secretary of Labor and Industry determines general prevailing minimum wage rates by craft or classification for the locality, after consulting an advisory board. Employer and employee benefit contributions under a bona fide collective bargaining agreement count as part of the wage. Section 4 puts the public body in charge of obtaining the rates, publishing them in the bid notice and building them into the contract, where they cannot be changed during the term. Section 5 says workers on public work must be paid at least those rates.
If you think a rate is wrong, Section 8 sets a short window: a verified petition to review must be filed within ten days after the specifications are published, and the FAQ says the challenger carries the burden of proving a different rate. Missing that window is a common way to lock in a rate you cannot meet, so read bid documents the day you get them.
What must a contractor do on the job?
- Keep records (Section 6): each worker’s name, craft and actual hourly rate, kept for two years from payment and open to the public body and the Secretary.
- Post the rates (Section 9): by craft and classification, with effective dates of changes, at the job site or the pay location.
- Certified payroll: the department’s FAQ says contractors and subcontractors submit weekly certified payrolls to the public body, and that falsifying them can be prosecuted as a misdemeanor.
- Sworn statements (Section 10): before final payment, contractors and subcontractors file sworn statements listing amounts owed to workers. A knowingly false statement is a misdemeanor; read the statute itself for the penalty figures.
What happens if workers are underpaid?
Section 11 separates unintentional and intentional failures. For a non-intentional failure, the Secretary gives a reasonable chance to correct it by paying what is owed or posting adequate security. For an intentional failure, public bodies are told, and no contract may be awarded to the firm, or to a firm in which it has an interest, for three years from the notice. The firm also owes liquidated damages to the Commonwealth equal to the underpayment, on top of damages for other breaches, and the Secretary may direct termination of the contractor’s right to proceed (Section 12). The department’s FAQ lists examples of intentional violations: willful or knowing underpayment, false certifications, falsified records, misclassification, and failing to correct an earlier unintentional finding. It adds that a contractor’s inability to pay is not an excuse.
Workers can act too. A worker may file a protest within three months, and Section 13 lets an underpaid worker sue for the difference between wages paid and the contract rate within six months of the event. Because those windows are short, check them in the statute before you rely on them. The department’s Bureau of Labor Law Compliance enforces the act, investigates complaints and may hold hearings; appeals go to the Prevailing Wage Appeals Board and then Commonwealth Court, per the FAQ.
How this ties to workers you use
Misclassifying laborers as contractors is on the department’s list of intentional violations. If you use subs, read our misclassification guide first. Private homeowner work under the Home Improvement Consumer Protection Act is a different regime; see our home improvement definition page for how the two differ.
Before you bid public work
- Find the wage determination in the bid package and price every craft you will use at that rate, including benefits.
- Decide within ten days of publication whether to challenge a rate.
- Set up weekly certified payroll before the first day on site, for you and every sub.
- Do not treat recurring work as maintenance unless the department confirms it; the FAQ does not give landscaping-specific guidance.
- Have a Pennsylvania attorney or your CPA review the payroll setup if this is your first covered job.
Sources
Pennsylvania Prevailing Wage Act, Act of Aug. 15, 1961, P.L. 987, No. 442, text published by the Pennsylvania General Assembly (PDF), and Pennsylvania Department of Labor and Industry, Prevailing Wage FAQs. Checked Nov. 23, 2026. Verify against the current statute text.
FAQ
What is the dollar threshold for the Pennsylvania Prevailing Wage Act?
Public work is covered when the estimated total project cost exceeds $25,000, and the department says a project cannot be split to fall below that amount.
Does the act apply to private homeowner jobs?
No. It covers work paid at least partly with public body funds. Homeowner work falls under other laws, such as the Home Improvement Consumer Protection Act.
Who sets the prevailing wage rates?
The Department of Labor and Industry sets rates by craft and locality, and the public body places them in the bid notice and contract.
What is the penalty for intentionally underpaying workers?
A three-year bar from public contracts, liquidated damages equal to the underpayment, possible termination of the contract, and payment of wages owed, according to the statute and the department’s FAQ.
Questions about a project in central Pennsylvania? Muthler Landscaping & Construction LLC, 913 Bellefonte Avenue, Lock Haven, PA 17745, PA HIC #PA212584, (570) 397-9800.
This is a plain-English summary of what the official sources state, not legal advice. Statutes get amended and courts interpret them, so talk to a Pennsylvania attorney or CPA about your own situation before you rely on any of it.
Related: Pennsylvania guide · Misclassification Act · Workers’ comp for contractors · Sales tax on landscaping.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “Pennsylvania Prevailing Wage Act: When a $25,000 Public Project Triggers Wage Rates,” https://muthlerlandscaping.com/state-guides/pennsylvania/pa-prevailing-wage-act-basics-public-works/ (page updated November 23, 2026).
Get an email when your state’s rules change
We re-check every entry against official sources. Tell us your state and we’ll email you when something changes.