Pennsylvania Payment Act: Withholding, Retainage, Penalty and Attorney Fees

When an owner or contractor disputes part of an invoice, Pennsylvania’s Contractor and Subcontractor Payment Act (Act of Feb. 17, 1994, P.L. 73, No. 7, as amended in 2018) says how much can be held back, what written notice must be given and what it costs to get this wrong. This page paraphrases Sections 6 through 12 and 16 of the act as published on the Pennsylvania General Assembly site and checked on November 23, 2026. The payment deadlines and interest rate are on our payment deadlines guide. Section numbers below are the act’s own.

Quick answer

  • Owner withholding notice: written notice of the deficiency and the good-faith reason within 14 calendar days after the invoice is received (Section 6(b))
  • Invoice errors: the recipient must give written notice within ten working days of receipt (Section 8(a))
  • Retainage: due within 30 days after final acceptance of the work (Section 9(a))
  • Sub gets retainage: within 14 days after the contractor receives it (Section 9(c))
  • Penalty: 1% per month on the amount wrongfully withheld, plus reasonable attorney fees for the substantially prevailing party (Section 12)

How can an owner withhold part of an invoice?

Section 6(a) lets an owner withhold payment for deficiency items under the construction contract, but the owner must still pay for any invoiced item that has been satisfactorily completed. The act defines a deficiency item as work performed that the owner, the contractor or the inspector will not certify as complete according to the construction contract’s specifications. An inspector is the contractor or a person authorized or engaged by the owner to inspect the work.

The withholding has conditions. Except for retainage, which Section 9 handles separately, the amount withheld must be reasonable, and the owner must give the contractor written notice of the deficiency and the owner’s good-faith reason within 14 calendar days of the date the invoice is received (Section 6(b)(1)). If the owner does not give that notice, Section 6(b)(2) says the owner loses the basis to withhold and must pay the contractor in full for the invoice. Even where the owner does withhold, each other satisfactorily completed item must still be paid (Section 6(b)(3)).

The practical lesson for owners is to calendar the 14 days from the day the invoice arrives, not from the day work finished. For contractors, the lesson is the mirror image: record when each invoice was delivered, because a late or missing notice can defeat a withholding.

What if an invoice is wrong or incomplete?

Section 8(a) covers defective paperwork. If an invoice is incorrectly or incompletely filled out, or has another defect, the recipient must give written notice to the sender within ten working days of receiving it. Once the notice is received, the invoice recipient must pay the correct amount on the due date under the act (Section 8(c)). The text shows Section 8(b) as deleted by amendment.

This rule keeps a paperwork error from becoming an open-ended reason to delay payment. A contractor that gets a notice should fix the invoice quickly, and an owner that spots an error should say so in writing inside the ten working days rather than waiting.

How can a contractor withhold from a subcontractor?

Section 11 mirrors Section 6 one level down. A contractor or subcontractor may withhold payment from a subcontractor responsible for a deficiency item, but must still pay under the act for any satisfactorily completed item on the invoice (Section 11(a) and (c)). Except for retainage, the withholding party must notify both the subcontractor and the owner in writing of its good-faith reason. The notice is due within the time set in the construction contract, or within 14 calendar days after receipt of notice of the deficiency item (Section 11(b)(1)).

If that notice is not given, the basis to withhold is waived and the subcontractor must be paid in full for the invoice (Section 11(b)(2)). Notice to the owner as well as the subcontractor is easy to miss, and the act treats it as part of the requirement.

How does retainage work?

Retainage is money held back until the job is finished. Section 9(a) says retainage due on final completion must be paid within 30 days after final acceptance of the work. If the owner is not withholding retainage, a contractor may withhold retainage from a subcontractor under their agreement, and that retainage must also be paid within 30 days after final acceptance (Section 9(b)). Once a contractor receives retainage, it must pay each subcontractor the full amount due within 14 days, and each subcontractor must do the same for its own subcontractors (Section 9(c)).

The act also includes an early-release option. According to Section 9(a.1), after substantial completion of its own scope, a contractor or subcontractor may obtain earlier release of retainage by posting a maintenance bond with an approved surety for 120% of the retainage held. Read the subsection itself before relying on it, because the details of who must accept the bond and when matter.

Retainage held more than 30 days after final acceptance is subject to the withholding obligations in Section 6(b) or 11(b). If an owner, contractor or subcontractor unreasonably withholds acceptance or fails to pay retainage, it owes interest at the Section 5(d) rate, which is 1% per month or fraction of a month on the balance due, and the interest runs from the date acceptance was unreasonably withheld or the date the retainage was due, whichever applies (Section 9(d)). Section 12 also applies.

Are advance payments allowed?

Yes. Section 10 says the act does not prohibit advance, progress or prepayments where an agreement or the circumstances make them appropriate. All payments are due when due and owing, late payments bear interest at the Section 5(d) rate from the date payment was due, and a party that fails to pay on time is also subject to Section 11. This section matters mainly because it confirms the act is not a ban on deposits. Home improvement deposits on private residences have their own limits under a different statute; see our contractor deposit limits guide.

What are the penalty and attorney fee rules?

Section 12(a)(1) applies when arbitration or litigation is brought to recover payment under the act and the party is found to have failed to comply with the act’s payment terms. In that case the arbitrator or court must award, in addition to other damages, a penalty equal to 1% per month of the amount wrongfully withheld.

An amount is not treated as wrongfully withheld if two things are true: the amount reasonably relates to the value of a claim held in good faith against the party seeking payment, and the claim holder complies with Section 6 or 11 (Section 12(a)(2)). That is why the written notice rules above carry so much weight. A good-faith dispute only protects the party that gave timely notice.

Section 12(b) adds that, despite any contrary agreement, the substantially prevailing party in a proceeding to recover payment under the act receives a reasonable attorney fee, set by the court or arbitrator, plus expenses. A contract clause that tries to say each side bears its own fees does not override that rule, according to the text.

Other provisions to know

  • Section 13: if the act conflicts with a federal statute or regulation, or with conditions attached to federal aid, the act does not prevent receipt of that aid.
  • Section 14: a contract governed by another state’s law is unenforceable, and so is a contract that requires litigation, arbitration or other dispute resolution in another state.
  • Section 16: after a contractor pays a subcontractor under the contract or the act, later payment claims against that contractor by the parties the subcontractor owed are barred.
  • Section 3(a): the act does not apply to improvements to real property of six or fewer residential units under construction at the same time, so check coverage first.

Sources

Contractor and Subcontractor Payment Act, Act of Feb. 17, 1994, P.L. 73, No. 7, as amended, text published by the Pennsylvania General Assembly at legis.state.pa.us, checked November 23, 2026. Read the full act, or ask a Pennsylvania attorney, before relying on a deadline or the retainage bond provision.

FAQ

How long does an owner have to explain why it is withholding payment?

Within 14 calendar days of the date the invoice is received, the owner must give written notice of the deficiency and its good-faith reason, or it loses the basis to withhold (Section 6(b)).

When must retainage be paid in Pennsylvania?

Retainage due on final completion must be paid within 30 days after final acceptance of the work (Section 9(a)), and a contractor must pass it to subcontractors within 14 days of receiving it (Section 9(c)).

What is the penalty for wrongfully withholding payment?

In arbitration or litigation under the act, the arbitrator or court must award a penalty of 1% per month of the amount wrongfully withheld, plus reasonable attorney fees to the substantially prevailing party (Section 12).

Can a contract waive the act’s attorney fee rule?

Section 12(b) says the substantially prevailing party receives reasonable attorney fees despite any contrary agreement, and Section 3(c) generally bars waiving provisions of the act.

This is a plain-English summary of what the official sources state, not legal advice. Statutes get amended and courts interpret them, so talk to a Pennsylvania attorney about your own situation before you rely on any of it.

Related: Pennsylvania guide · CASPA payment deadlines and interest · Pennsylvania mechanics lien deadlines · Contractor deposit limits.

Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.

Cite as: Muthler Landscaping & Construction, “Pennsylvania Payment Act: Withholding, Retainage, Penalty and Attorney Fees,” https://muthlerlandscaping.com/state-guides/pennsylvania/caspa-withholding-retainage-penalty/ (page updated November 23, 2026).