Selinsgrove Borough, PA: Zoning Permit, CKCOG Building Permit and Floodplain Rules
Selinsgrove is a borough in Snyder County. Its website has a Codes section with a full forms list, a Zoning Permit Application that includes step-by-step instructions, and a page for people opening a business. This guide paraphrases those official documents and marks anything the site does not state. The borough’s forms page was last modified September 9, 2026, and everything here was checked November 23, 2026. County context is on our Snyder County guide.
Quick answer
- Zoning permits: apply to the Borough Office, One North High Street, Selinsgrove, PA 17870, phone 570-374-2311, email borough@selinsgrove.org, Monday to Friday 8:30 am to 4:30 pm
- Building permits under the UCC: submitted to Central Keystone COG (CKCOG), 1610 Industrial Boulevard, Suite 400A, Lewisburg, PA 17837, with a copy of the approved zoning application
- Zoning review time: up to 30 days after all materials and the fee are received
- Fence: listed as a proposed use on the zoning permit application
- Zoning fee amount: not stated on the municipality’s site
What does Selinsgrove’s zoning permit application cover?
The Zoning Permit Application (the posted version was revised July 12, 2024; the forms page now lists a May 20, 2026 version) is built to verify zoning compliance. It applies when someone erects, establishes, alters, changes or replaces a structure or use, whether principal or accessory, residential or non-residential. It also names non-conforming structures or uses and temporary uses of 30 days or less. A fence appears as one of the listed proposed uses. The form cites sections 27-1601 and 27-1603 of the borough code, which deal with zoning and occupancy permits.
The applicant fills in the parcel number, the zoning district and the dimensions of the lot and structure. Required measurements include the setback from the right-of-way, both side yards and the rear yard, along with height and number of stories. The form also asks for existing and proposed driveway length and width and for parking spaces, using nine-by-seventeen-foot spaces as the unit. The borough’s checklist reviews setbacks, building coverage, impervious coverage and floodplain compliance, but the form does not print the limits, so the actual numbers are not stated on the form. Look them up in the zoning ordinance on eCode360 or ask the Zoning Officer.
What do you submit and how long does it take?
- A completed application and a scaled plan drawing showing existing structures, the proposed construction, adjacent roads, all setbacks and existing boundary lines.
- A signed owner certification made under penalty of the Pennsylvania Crimes Code.
- The application fee. The form leaves the fee field blank and the forms page lists no amount; call 570-374-2311 or check the borough’s fee schedule on eCode360.
- For projects in or next to a FEMA floodplain, a contractor’s cost estimate and a check of the floodway, Zone AE, Zone A or Zone X category.
The form says the borough may take up to 30 days after it has everything, and that clock restarts if the zoning officer asks for more documents. Permits are reviewed in the order received. A copy of the application and a placard must be displayed at the site for the whole project. Work must start within six months of the permit date and finish within one year, and the borough may hold, disapprove or revoke a permit over outstanding compliance issues. Notify the zoning office when the work is finished and before anyone occupies the space.
How does the UCC building permit work in Selinsgrove?
The zoning form says that if a project is covered by the Pennsylvania Uniform Construction Code, you submit a copy of the approved zoning application along with your building permit application to Central Keystone COG at 1610 Industrial Boulevard, Suite 400A, Lewisburg, PA 17837. CKCOG lists 570-522-1326 and toll-free 877-457-9401, and its building permit page says applications can be emailed to permits@ckcog.com. After CKCOG issues the occupancy certificate, a copy goes to the borough. The borough’s business page calls CKCOG the borough’s third-party inspection agency, says CKCOG sets inspection intervals and says the owner is responsible for scheduling inspections. Our UCC third-party agencies and UCC permit application pages explain the state process.
The business page also says cosmetic work such as painting or wallpaper in a turnkey space does not need a building permit, while alterations, demolition, new construction and changes to door or window openings do. That statement is written for tenant fit-outs, not for yard projects, so do not apply it to a deck or wall.
Which other forms does the borough post?
The Applications and Forms page lists these items relevant to site work. The page says the forms are not fillable; print them or bring them to the office.
- Floodplain Development Permit Application and a separate zoning permit for repairing, demolishing or elevating a flood-damaged structure (dated September 2017).
- Sign Permit Application (May 16, 2025) and a Shade Tree Commission Permit (rev. May 24, 2023).
- Application for Connection Permit, Application for Hearing, and Application to Appeal the Decision of the Zoning Officer.
- Subdivision and Land Development plan application and Application for Change of Zoning.
A zoning map PDF and the zoning ordinance link on eCode360 are also posted. The page does not state stormwater, retaining wall or driveway permit requirements.
What should a homeowner or contractor do first?
Confirm the use and district, pull the zoning permit, then ask whether CKCOG needs a building permit for your scope. For statewide context see our building code guide, fence law, shed permit and retaining wall permit pages. We are not stating that any project is exempt; the borough site does not say so.
Sources
All checked November 23, 2026. Applications and Forms; Zoning Permit Application (revised 7-12-24); Opening a New Business; Central Keystone COG building permits. Rules and fees change, so confirm with the borough.
FAQ
Who issues zoning permits in Selinsgrove Borough?
The Borough Office accepts the zoning permit application at One North High Street, and the borough’s zoning officer reviews it. Call 570-374-2311.
Who handles UCC building permits in Selinsgrove?
The borough’s zoning form and business page direct building permit applications to Central Keystone COG, which the borough describes as its third-party inspection agency.
How much is a Selinsgrove zoning permit?
The fee amount is not stated on the municipality’s site. The application has a fee field but no amount, so call the borough.
This is a plain-English summary, not legal advice. Call the borough and CKCOG to confirm requirements and fees before you price or start work.
Related: Pennsylvania guide · Snyder County · PA permit fees · PA building code · PA fence law.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “Selinsgrove Borough, PA: Zoning Permit, CKCOG Building Permit and Floodplain Rules,” https://muthlerlandscaping.com/state-guides/pennsylvania/selinsgrove-borough-permits/ (page updated November 23, 2026).