34 Pa. Code 403.46 and 403.65: Certificate of Occupancy Contents, the 5-Day Issuance Rule and Temporary Certificates

A building in Pennsylvania cannot be used or occupied under the Uniform Construction Code (UCC) without a certificate of occupancy. Section 403.46 sets the rules for commercial buildings and Section 403.65 sets them for residential buildings. They are close cousins, with a few differences in what the certificate must list and in how fast it must be issued in the largest cities. This page compares the two as they appear on Cornell’s Legal Information Institute, checked November 23, 2026. Verify every number against the current regulation.

Quick answer

  • Requirement: no use or occupancy without a certificate issued by a building code official
  • Commercial deadline (403.46(b)): within 5 business days after the official receives a final inspection report showing compliance
  • Residential deadline (403.65(b)): 5 business days, or 10 business days in cities of the first class
  • Partial and temporary certificates: the official may issue a certificate for a part that independently meets the UCC, and a temporary certificate for parts that can be occupied safely, for a set time period
  • Revocation: allowed if issued in error, on incorrect information or in violation of the UCC, with a hearing before the board of appeals available beforehand

When is the certificate issued?

Both sections start with the same rule in subsection (a): a building, structure or facility cannot be used or occupied without a certificate of occupancy issued by a building code official. Subsection (b) sets the clock. For commercial buildings the official must issue the certificate within 5 business days after receiving a final inspection report showing compliance with the UCC. For residential buildings the official issues it after receiving a final inspection report showing compliance with the UCC and local ordinance, within 5 business days, or 10 business days in cities of the first class. The final inspection report itself comes from the process described on our inspections regulation page. Our certificate of occupancy overview gives the plain-language version.

What must the certificate list?

ContentCommercial, 403.46(b)Residential, 403.65(b)
Permit number and property addressYesYes
Name and addressPermit holderOwner
Part of property coveredDescription of the part coveredDescription of the part of the building the permit covers
Inspection statementDate of the final inspectionStatement that the part was inspected for UCC compliance
Issuing officialName of the building code officialName of the building code official who issued the permit
Code editionApplicable construction code editionApplicable edition of the construction code
Use and construction typeUse and occupancy classification under Chapter 3 and construction type under Chapter 6 of the 2021 IBC, when designatedNot listed
Sprinkler systemNot listedWhether an automatic sprinkler system is provided
Special conditionsSpecial stipulations and conditions, including board of appeals decisions and accessibility variances granted by the SecretaryAny special stipulations or conditions tied to the building permit

Keep your copy. A lender, insurer or buyer may ask for the certificate, and the listed conditions, including any variance, travel with it. Ask your lender or insurer what they require; that is a practical caution only.

Can a part of a building be certified or occupied early?

Yes, in two ways. Subsection (c) lets the official issue a certificate for a portion of a building, structure or facility if that portion independently meets the UCC. In commercial 403.46(e) and residential 403.65(f), the official may issue a temporary certificate for part or parts of a building or structure before all permitted work is complete, if those parts can be occupied safely. The official must set a time period during which the temporary certificate is valid. Ask the code office how long that period may be. A tenant fit-out in one wing of a building and a finished first floor of a house with work continuing upstairs are the kind of situations these provisions address, though the text itself does not give examples.

Can a certificate be suspended or revoked?

Under 403.46(d) and 403.65(d), the official may suspend or revoke a certificate if it was issued in error, based on incorrect information from the applicant, or in violation of the UCC. Before revocation, the building owner may request a hearing before the board of appeals under 403.122. That appeal route is covered on our appeals regulation page and our board of appeals overview.

Who sends the certificate to the municipality?

Only the residential section has this rule. Under 403.65(e), a third-party agency under contract with the permit holder must send a copy of the certificate to the municipality. If your project uses a private agency, see our third-party agencies page, and confirm that the agency has sent the copy before you tell the owner the job is closed out.

What owners and contractors can do with these sections

  • Do not let an owner move in, or a tenant open, until the certificate is in hand, or a temporary certificate covers the part in use.
  • Note the date the final inspection report is filed and count 5 business days from it, or 10 in a city of the first class on a residential job.
  • Ask for a partial or temporary certificate in writing if the owner needs part of the building early.
  • Check the certificate for the permit number, address, code edition and any listed conditions before you hand it over.
  • If a certificate is revoked or you disagree with a stipulation, talk to a Pennsylvania attorney and ask about a board of appeals hearing.

Sources

34 Pa. Code 403.46 (Cornell LII) and 403.65 (Cornell LII); final regulation amending 403.46, IRRC Regulation #12-125 (IRRC), published as final Nov. 8, 2025, effective Jan. 1, 2026. The Cornell LII copy had not yet reflected the 2025 amendment when checked Nov. 23, 2026. Verify against the current regulation, which has been amended.

FAQ

How fast must a Pennsylvania certificate of occupancy be issued?

Under 403.46(b) and 403.65(b), within 5 business days after the official receives a final inspection report showing compliance, or 10 business days in cities of the first class for residential buildings.

Can someone move in before the work is finished?

The official may issue a temporary certificate for parts that can be occupied safely before all permitted work is complete, and must set a time period during which it is valid.

Can a certificate of occupancy be revoked?

Yes, if it was issued in error, based on incorrect applicant information, or in violation of the UCC. The owner may request a hearing before the board of appeals under 403.122 before revocation.

Does the certificate show the code edition used?

Yes. Both sections list the applicable construction code edition among the required contents. Verify the current text for the full list.

This is a plain-English summary of what the official sources state, not legal advice. Regulations get amended and agencies and courts interpret them, so talk to a Pennsylvania attorney about your own situation before you rely on any of it.

Related: Pennsylvania guide · Required inspections · Pennsylvania building code · UCC opt-in vs opt-out.

Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.

Cite as: Muthler Landscaping & Construction, “34 Pa. Code 403.46 and 403.65: Certificate of Occupancy Contents, the 5-Day Issuance Rule and Temporary Certificates,” https://muthlerlandscaping.com/state-guides/pennsylvania/ucc-34-pa-code-403-46-403-65-certificate-of-occupancy/ (page updated November 23, 2026).