34 Pa. Code 403.43 and 403.63: Permit Decision Deadlines, Deemed Approval, Revocation and the 180-Day Rule
Once a Pennsylvania building permit application is filed, two regulations govern what happens next. Section 403.43 covers commercial buildings and Section 403.63 covers residential buildings. Both set a decision deadline, say what a denial must contain, explain when a permit can be revoked, and limit how long a permit stays valid. They differ in important ways, most notably the length of the review clock and whether a missed deadline means deemed approval. This page compares the two, as they appear on Cornell’s Legal Information Institute, checked November 23, 2026. Verify every number against the current regulation.
Quick answer
- Commercial (403.43(a)): grant or deny within 30 business days of filing
- Residential (403.63(a)): 15 business days, or 5 business days if a Pennsylvania-licensed or registered design professional certifies the plans meet the UCC
- Deemed approval: the residential text says an application is deemed approved if the official misses the deadline; the commercial section does not say that
- Expiration: a permit is invalid if work does not begin within 180 days, or is suspended or abandoned for 180 days, and no permit lasts more than 5 years
- Fees: a permit is not valid until required fees are collected
How long does the building code official have to decide?
For commercial work, 403.43(a) requires the official to grant or deny an application, in whole or in part, within 30 business days of the filing date. A written denial must identify the noncompliant parts, cite the UCC and ordinance provisions, and go to the applicant. The official and applicant may agree in writing to extend the deadline by a specific number of days, and a different deadline may be set for an application in a historic district. For residential work, 403.63(a) sets 15 business days, or 5 business days if a design professional licensed or registered in Pennsylvania certifies that the plans meet the UCC and applicable ordinances. If the official misses the deadline the application is “deemed approved.” The same written-denial and written-extension rules apply. Our permit review deadlines page gives the plain-language version, and our Sections 502 and 503 page covers the statute behind it.
| Topic | Commercial, 403.43 | Residential, 403.63 |
|---|---|---|
| Decision deadline | 30 business days | 15 business days; 5 with a design professional’s certification |
| Missed deadline | Not stated in the section | Application deemed approved |
| Validity | Invalid if work does not begin within 180 days or is suspended or abandoned for 180 days; max 5 years | Same 180-day rule and 5-year maximum |
| Appeals to board | Under 403.122 | Under 403.122, in municipalities with an enforcement ordinance or joint administration |
| Fees | Collected under 401.2 and 401.2a | Collected under 401.2a |
What must the official do with the plans?
Both sections require the official to examine the construction documents to see whether the proposed work complies with the UCC and other applicable laws and ordinances. Before issuing the permit, each page of the reviewed set must be stamped or marked as reviewed and approved for UCC compliance. Required nondesign changes must be clearly marked and the marked set returned to the applicant, who must keep a copy at the work site for inspection. Under both, a permit for property needing access to a PennDOT-controlled highway cannot be issued unless it states that a highway occupancy permit under section 420 of the State Highway Law is required before driveway access is allowed. See our PennDOT driveway permit page.
Can a partial permit or deferred submittal be used?
Both sections let the official issue a permit for foundations or other parts of a building before the full set of documents is submitted, if the applicant previously filed adequate information and detailed statements. That approval does not guarantee a permit for the entire structure. Only the commercial section, 403.43(k), also allows deferred submittals: the official must approve the deferral in advance, a licensed architect or professional engineer in responsible charge must list the deferred items on the construction documents, a licensed architect or engineer must review the deferred documents and note that they generally conform to the building design, and deferred items may not be installed until the official approves them.
When can a permit be suspended or revoked?
Issuing a permit does not bar prosecution or other legal action for violations. The official may suspend or revoke a permit if the holder fails to make changes required when the documents were marked, if the permit was issued in error, if it was based on inaccurate or incomplete information, or if it violates any law, regulation, ordinance or the UCC. The 180-day rule works in two directions: a permit is invalid unless work begins within 180 days of issuance, or if work is suspended or abandoned for 180 days after it has started. The holder may request a written extension for just cause, and the official may grant it in writing. No permit is valid for more than 5 years from its issue date. Our permit expiration page covers the practical side.
What about changes, appeals and accessibility?
Work must follow the approved documents, and the holder must submit a revised set for any change that does not conform. An applicant may request extensions or variances, or appeal the official’s action, to a board of appeals under 403.122. The commercial section, 403.43(j), adds that a board of appeals cannot rule on extensions, variances or appeals involving accessibility, which fall to the Secretary under 403.142. The residential section ties board appeals to municipalities that have adopted an enforcement ordinance or jointly administer the act by agreement. See our board of appeals page.
What owners and contractors can do with these sections
- Write down the filing date and count business days from it, then ask for a written denial if the deadline passes.
- On residential jobs, ask your designer whether a certification could shorten the clock to 5 business days.
- Start work, or request an extension in writing, before day 180.
- Keep the stamped set at the site and submit a revised set before you change the work.
- If you think a deemed approval applies, talk to a Pennsylvania attorney before relying on it.
Sources
34 Pa. Code 403.43 (Cornell LII) and 403.63 (Cornell LII). Checked Nov. 23, 2026. Verify against the current regulation, which has been amended.
FAQ
How many days does a PA code office have to approve a residential permit?
Section 403.63(a) says 15 business days, or 5 business days if a Pennsylvania-licensed or registered design professional certifies the plans meet the UCC. A missed deadline means the application is deemed approved.
How long is the review period for a commercial permit?
Section 403.43(a) says 30 business days from the filing date, unless extended in writing by agreement or set differently for a historic district.
When does a Pennsylvania building permit expire?
Under 403.43(g) and 403.63(g), a permit is invalid if work does not begin within 180 days or is suspended or abandoned for 180 days, and no permit is valid for more than 5 years from issuance.
Can a permit be revoked after it is issued?
Yes. The official may suspend or revoke a permit issued in error, based on inaccurate or incomplete information, or in violation of a law, regulation, ordinance or the UCC. Consult an attorney about a specific revocation.
This is a plain-English summary of what the official sources state, not legal advice. Regulations get amended and agencies and courts interpret them, so talk to a Pennsylvania attorney about your own situation before you rely on any of it.
Related: Pennsylvania guide · Permit application · Pennsylvania building code · UCC opt-in vs opt-out.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “34 Pa. Code 403.43 and 403.63: Permit Decision Deadlines, Deemed Approval, Revocation and the 180-Day Rule,” https://muthlerlandscaping.com/state-guides/pennsylvania/ucc-34-pa-code-403-43-403-63-permit-decisions-deemed-approval-expiration/ (page updated November 23, 2026).
Get an email when your state’s rules change
We re-check every entry against official sources. Tell us your state and we’ll email you when something changes.