Pennsylvania’s regulation says who applies, what has to go with the application and what the code official can waive. A complete filing is also what starts the review clock.
The owner or an authorized agent applies to the building code official before work starts. The application includes construction documents (plans and specifications), a site plan, any other required permits or approvals and, in a flood hazard area, flood elevation data. Checked Nov. 22, 2026.
Who applies, and when
Under 34 Pa. Code § 403.62(a), the owner or an authorized agent must apply to the building code official and get a permit before constructing, enlarging, altering, repairing, moving, demolishing or changing the occupancy of a residential building. The same goes for installing, altering, repairing, removing, converting or replacing regulated electrical, gas, mechanical or plumbing systems. An “authorized agent” is how a contractor can pull the permit for you.
What goes in the application (§ 403.62a)
| Item | Detail |
|---|---|
| Application | Filed with the building code official |
| Construction documents | Plans and specifications. The official may waive them if the work doesn’t need review to confirm UCC compliance. |
| Other approvals | Any other permits or approvals for the construction that § 403.102(n) requires |
| Site plan | Size and location of new construction and existing structures, and their distances from lot lines. For demolition, what’s coming down and what stays. The official can waive or modify it for alterations and repairs. |
| Flood hazard area data | If the building is in an NFIP flood hazard area: flood hazard area and floodway boundaries, flood zones and the design flood elevation; for Zone AO, the lowest floor elevation and its height above the highest adjacent grade |
Design flood elevations come from the municipality’s FEMA flood map; if the map lacks them, the applicant and the official obtain and reasonably use data from other sources. Check yours with our flood zone lookup.
Review, markup and on-site copies
The official checks the plans against the UCC and other applicable laws. The review clock is in our permit review deadlines guide.
Reviewed plans are stamped or noted as approved, required changes are marked, and the marked set goes back to you. You keep a copy on site for inspection (§ 403.63(c)).
Emergency repair or equipment replacement can start before a permit is issued if you submit an application to the code official within 3 business days (§ 403.62(b)).
Practical notes
- Zoning and other municipal approvals often come first. Ask what the code office needs to see before it will accept the application.
- Fees must be paid for the permit to be valid; see central PA permit fees.
- Once issued, see permit expiration and required inspections.
- Which jobs need one at all: work that doesn’t need a UCC permit.
Questions
Can my contractor pull the permit?
The regulation lets the owner or an authorized agent apply. A contractor acting for the owner is an authorized agent.
Do I need a site plan?
Usually. The application must include a site plan showing new and existing structures and their distances from lot lines, though the official can waive or modify it for alterations and repairs.
What if it’s an emergency repair?
Work can start first. Submit a permit application to the code official within 3 business days.
What extra do I need in a flood zone?
Flood hazard area and floodway boundaries, flood zones and the design flood elevation with the construction documents.
Sources: 34 Pa. Code § 403.62; § 403.62a, Permit application; § 403.63. Checked Nov. 22, 2026. The Justia pages carry a note that they may not reflect the current regulation.
Muthler Landscaping & Construction · Lock Haven, PA
Planning a project in central PA?
We build patios, walls, drainage and site work across Clinton, Centre, Lycoming and Union counties, and we handle the permits that go with them.
Get a free estimatePennsylvania guideMuthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.
Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.
Cite as: Muthler Landscaping & Construction, “Pennsylvania Building Permit Application: What to File,” https://muthlerlandscaping.com/state-guides/pennsylvania/ucc-permit-application/ (page updated November 23, 2026).
Get an email when your state’s rules change
We re-check every entry against official sources. Tell us your state and we’ll email you when something changes.