Deck post-to-beam connections: IRC R507.5 and the AWC guide

The post-to-beam joint carries the deck’s weight down to the footing. The model code and the AWC deck guide are specific about how that joint is made, and about the common shortcut they do not allow.

Quick answer

The AWC DCA 6 guide shows two connections: a notched post (Fig. 8A) or a post cap (Fig. 8B). Three-ply beams need a post cap, and fastening a beam to the side of an un-notched post is prohibited (Fig. 9) (p. 10). The model IRC says the connection must transfer vertical load and resist horizontal displacement, with bolts and washers (R507.5.2).

Connection rules by section

PointWhat the source statesSection
Beam spansBeam spans come from the beam span table.IRC R507.5, Table R507.5
BearingA multi-ply beam has full bearing on the post.IRC R507.5.1
ConnectionMust transfer vertical load and resist horizontal displacement; bolts with washers.IRC R507.5.2
Two optionsNotched post (Fig. 8A) or post cap (Fig. 8B).AWC DCA 6, p. 10
Three-ply beamsNeed a post cap.AWC DCA 6, p. 10
Not allowedAttaching the beam to the side of the post without notching (Fig. 9).AWC DCA 6, p. 10
Corner bracingCorner posts over 2′-0″ high need diagonal bracing with 1/2 inch lag screws.AWC DCA 6, p. 10
Lateral hold-downsTwo hold-downs of at least 1,500 lb within 24 inches of each end, or four of at least 750 lb.IRC R507.9.2, Figs. R507.9.2(1) and (2)

Our sources disagree on the nailing pattern for built-up beams (one gives two rows at 19 inches on center, another 16 inches), so we leave the number out. Check your code edition. Glossary: beam and post base. Related: joist spans and bearing and footing requirements.

Planning information, not engineering or legal advice. Section numbers follow the 2018 IRC numbering in Penn State’s deck materials and the 2015 AWC DCA 6. Pennsylvania began enforcing the 2021 International Residential Code on Jan. 1, 2026, so section numbers and some values may differ; confirm with your local code office. Pennsylvania L&I says the 2015 International Codes were adopted as of October 1, 2018, and numbering differs between editions. The PA-adopted edition and local amendments may differ, so confirm with your municipal code office before you build.

Questions

Can I bolt a deck beam to the side of a post?

The AWC guide prohibits attaching the beam to the side of a post without notching it (Fig. 9, p. 10). Use a notched post or a post cap.

Does a three-ply beam need a post cap?

Yes, per the AWC guide (p. 10).

Does a deck need lateral hold-downs?

The model IRC calls for two 1,500 lb hold-downs near each end, or four 750 lb hold-downs (R507.9.2).

Sources: American Wood Council, DCA 6 (2015); Penn State Housing Research Center, deck design handout; 2018 IRC deck construction summary; PA L&I, UCC regulations and statutes. Checked Nov. 22, 2026.

Muthler Landscaping & Construction · Lock Haven, PA

Planning a deck?

We build decks across central Pennsylvania. Tell us what you have in mind.

Get a quoteAll guides

Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.