Home / Pennsylvania / Conservation districts / Columbia County

Columbia County, PA · checked Nov 22, 2026

Columbia County Conservation District

The Columbia County Conservation District in Bloomsburg reviews and approves erosion and sediment plans, inspects active earthmoving sites and responds to complaints in Columbia County. Its Chapter 102 page lists a named specialist but no thresholds or fees, so call before you plan.

Call (570) 317-9469All PA districts

What the district does

Reviews plans

Reviews and approves erosion and sediment control plans.

Inspects sites

Inspects active earthmoving sites for erosion controls.

Takes complaints

Responds to erosion and sediment complaints from the public.

Contact

SpecialistSteven Wanner, Erosion Control and Compliance Specialist, 570-317-9469
Main office702 Sawmill Road, Suite 103, Bloomsburg, PA 17815; 570-317-9456
HoursMon to Fri, 8:00 AM to 4:00 PM

The Chapter 102 page itself does not state thresholds, NPDES details or fees; the district’s FAQ page, summarized below, does. Call the district to confirm.

Thresholds on the district’s FAQ page

The district’s FAQ says earthmoving must use adequate best management practices to keep sediment from leaving the project. A written E&S plan is required for disturbance of 5,000 square feet or more, for any disturbance in a High Quality or Exceptional Value watershed, or when another DEP permit requires one. NPDES permit coverage applies to most construction with earth disturbance of 1 acre or more over the life of the project, which includes later work such as houses built in a subdivision whose roads were built first. Timber harvesting or road maintenance involving 25 acres or more of earth disturbance needs a separate Erosion and Sedimentation Control Permit. A post-construction stormwater management plan is required for NPDES projects.

Plans, approvals and timelines

The district says the plan must be prepared by someone experienced in erosion and sediment control, kept on site and followed. District approval is required when a municipality asks for an adequacy letter or another permit calls for it, including NPDES and Chapter 105 permits for stream work. The district or DEP may also require a plan after problems at an active site. For NPDES applications, the district says administrative review is done within 10 working days of receipt, and technical review begins after acceptance, with a policy target of 30 days from acceptance. Reviews run in the order complete applications arrive, and a pre-submission meeting is not required but is recommended for major projects.

What the district’s application asks for

The district’s E&S plan review application, revised 11/2024, asks for one copy each of the application form, the plan narrative, the plan drawings and a location map, plus the service fee. It lists fees such as a $200 base plus $150 per unit for residential projects and a $500 base plus $200 per disturbed acre for commercial and industrial ones. The applicant signs to comply with Chapter 102 and to obtain other needed permits, and authorizes district site inspections. Confirm current fees by phone, because the form carries a revision date rather than an effective date.

Related guides

See the Columbia County guide, PA stormwater plan rules and the conservation district hub.

Questions

Who handles erosion control in Columbia County?

The conservation district’s Erosion Control and Compliance Specialist, Steven Wanner, at 570-317-9469.

Can I report an erosion problem?

Yes. The district says it responds to complaints.

Where is the district office?

702 Sawmill Road, Suite 103, Bloomsburg.

When does Columbia County need a written erosion plan?

The district’s FAQ says at 5,000 square feet or more of disturbance, for any disturbance in a High Quality or Exceptional Value watershed, or when another DEP permit requires one.

How long does NPDES review take?

The district says administrative review is within 10 working days of receipt, and its policy is to finish technical review within 30 days of acceptance.

Planning information from the district’s published page, not legal advice or a permit determination. Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.

Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.

Cite as: Muthler Landscaping & Construction, “Columbia County Conservation District: erosion control contact,” https://muthlerlandscaping.com/state-guides/pennsylvania/conservation-districts/columbia-county-conservation-district/ (page updated November 23, 2026).