Bedford County Conservation District: E&S fees and review steps

Bedford County’s district publishes a fee schedule marked Rev. 3/2026 and a procedures document that spells out review timing, resubmission charges, plan validity and withdrawals. A small project under an acre is one of the cheaper reviews in the state.

Quick answer

Small project under 1 acre: $150. Waste/borrow area under 1 acre: $500. Industrial, commercial or utility under 1 acre: $750. Fees are due when you submit. The district says it reviews plans within 22 business days of a complete application and fees. Under 5,000 sq ft of disturbance needs no review. Checked Nov. 22, 2026.

E&S service fees

Project typeFee
Small project, under 1 acre$150
Waste/borrow area, under 1 acre$500
Industrial, commercial, utility, under 1 acre$750
Industrial, commercial, utility, 1 to 5 acres$1,000 + $200 per disturbed acre
Industrial, commercial, utility, 6 to 25 acres$2,000 + $150 per disturbed acre
Industrial, commercial, utility, 25+ acres$3,000 + $100 per disturbed acre
Residential, 1 to 10 units$200 per unit
Residential, 11 to 20 units$2,000 + $100 per unit
Residential, 21 to 100 units$3,000 + $75 per unit
Residential, 101+ units$4,000 + $50 per unit
Timber sale, under 10 acres / 10+ acres$150 / $300
Chapter 105 review$150

Disturbed acres are rounded to the nearest whole acre. The schedule’s tiers overlap at 25 acres, so ask the district which one applies at exactly 25.

NPDES fees

ItemFee
General permit (no disturbance in HQ or EV waters)$500
Individual permit (any disturbance in HQ or EV waters)$1,500
State Clean Water Fund fee$100 per disturbed acre
Timber or road maintenance erosion control permit, 25+ acres$500

Don’t combine checks. A 1-acre-plus NPDES project needs three: the service fee, the NPDES fee and the state fee.

How review works

What to send

Folded site drawings, the plan narrative, the application, a location map and the fees, submitted straight to the district and not the township.

22 business days

Plans are reviewed in order of receipt, within 22 business days of a complete application and fees. The procedures document also says to allow up to 50 days, and doesn’t reconcile the two.

2-year validity

Approvals are valid for 2 years. If earth disturbance hasn’t started by then, the review no longer holds.

Resubmissions and withdrawals

Service fees cover the first technical review and one resubmission. A third and each later technical resubmission costs 75% of the original fee. Comments not answered within 60 calendar days also cost 75%. An administratively incomplete package is returned, and resubmitting it takes a new fee of 100%. Minor revisions within 2 years of approval are free; major ones take a new fee. Refunds on withdrawals are decided case by case, with a $100 minimum processing fee, and none after the adequacy determination.

State rules that apply here

Any size

E&S controls are required on any earth disturbance (25 Pa. Code § 102.4).

5,000 sq ft

A written E&S plan is required at 5,000 sq ft or more.

1 acre

NPDES permit coverage applies at 1 acre (§ 102.5(a)).

Contact: Bedford County Conservation District, 702 West Pitt Street, Suite 3, Bedford, PA 15522. Phone 814-623-8099. Email bccd@bedfordcountyconservation.com. See our Bedford County guide, the PA conservation district list and stormwater plan rules.

Planning estimate, not legal advice. The fee schedule is marked Rev. 3/2026 with no separate effective date, and the procedures document was revised in 2026. Call the district for current fees before you submit.

Questions

How much is an E&S review in Bedford County for a small project?

$150 for a small project under 1 acre, per the district’s fee schedule marked Rev. 3/2026. A waste/borrow area under 1 acre is $500.

How long does Bedford County take to review an E&S plan?

The district says within 22 business days of a complete application and fees, in order of receipt. Its procedures also say to allow up to 50 days.

What does a third review cost in Bedford County?

75% of the original service fee for a third and each later technical resubmission.

Do I need a plan reviewed for under 5,000 square feet?

The district’s procedures say earth disturbance under 5,000 sq ft needs no review. State law still requires controls on any earth disturbance.

Sources: Bedford County Conservation District, E&S fee schedule; Bedford County Conservation District, E&S plan review procedures (revised 2026); 25 Pa. Code § 102.4; 25 Pa. Code § 102.5. Checked Nov. 22, 2026.

Muthler Landscaping & Construction · Lock Haven, PA

Building in central PA?

Our crews work central Pennsylvania from Lock Haven. If your job is in our area, we handle the grading, drainage and erosion control that go with a patio, wall or driveway.

Get a quoteAll PA districts

Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.

Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.

Cite as: Muthler Landscaping & Construction, “Bedford County Conservation District: E&S fees and review steps,” https://muthlerlandscaping.com/state-guides/pennsylvania/conservation-districts/bedford-county-conservation-district/ (page updated November 23, 2026).