E&S plan contents under 25 Pa. Code 102.4(b): planning principles and the 15 required items
Our Chapter 102 thresholds page explains when a written erosion and sediment (E&S) plan is required. This page covers what 25 Pa. Code 102.4(b) says the plan must contain. Paragraph (b)(4) lists four planning principles, paragraph (b)(5) lists 15 contents items, and other paragraphs cover the preparer, high quality and exceptional value waters, alternatives and recordkeeping.
General information only, not legal advice. This page paraphrases the regulation text. Verify against the current source before relying on any detail. Anything the source did not state is marked “not stated.” The agricultural plowing and animal heavy use provisions in 102.4(a) are not covered here.
When a written plan is required: (b)(2)
Best management practices (BMPs) are required for all earth disturbance activities, even under 5,000 square feet. A written plan is required under (b)(2) in three cases: disturbance of 5,000 square feet or more; the person must already have a plan under this chapter or other Department of Environmental Protection (DEP) rules; or the site is near drainage features that could discharge to High Quality (HQ) or Exceptional Value (EV) waters under Chapter 93. The third case gives no distance: not stated.
Who prepares the plan: (b)(3)
The plan is prepared by a person trained and experienced in E&S methods suited to the project’s size and scope. A specific license is not named in that paragraph. See the glossary entry on the erosion and sediment control plan for the plain definition.
Four planning principles: (b)(4)
Unless DEP, or the conservation district after consulting DEP, authorizes otherwise, the plan must be planned to the extent practicable to do the following:
- Minimize the extent and duration of earth disturbance.
- Maximize protection of existing drainage features and vegetation.
- Minimize soil compaction.
- Use measures that prevent or reduce increased runoff.
Compare these with the eight goals for the post construction side on our PCSM plan contents page. Practices that address the third principle are described on our minimize soil compaction and minimize total disturbed area pages.
The 15 contents items: (b)(5)
| Item | Required content |
|---|---|
| (i) | Existing topography of the site and surroundings |
| (ii) | Soil types, depths, slopes, locations and limitations |
| (iii) | Past, present and proposed land uses and planned alterations |
| (iv) | Volume and rate of runoff from the site and its upstream watershed |
| (v) | Receiving surface waters and their Chapter 93 classifications |
| (vi) | A narrative of perimeter and on-site BMPs before, during and after disturbance |
| (vii) | The sequence of BMP installation and removal relative to earth disturbance, so the BMPs function properly |
| (viii) | Supporting calculations and measurements |
| (ix) | Plan drawings |
| (x) | A maintenance program with BMP inspections weekly and after each stormwater event, repair or replacement as needed, and a written report for each inspection and maintenance action |
| (xi) | Procedures for recycling or disposing of project materials under Title 25 |
| (xii) | Geologic formations or soil conditions that could cause pollution, with BMPs to avoid or minimize it |
| (xiii) | Potential thermal impacts to surface waters, with BMPs to avoid, minimize or mitigate them |
| (xiv) | Consistency with the PCSM plan under 102.8 |
| (xv) | Existing and proposed riparian forest buffers |
Two of these deserve a closer look. Item (vii) is the closest the text comes to phasing. Item (x) sets the weekly and after-each-event inspection rhythm with a written report each time. For plain-language entries on common E&S measures, see silt fence, rock construction entrance, inlet protection and sediment trap. The section does not require any specific one of them: not stated.
Separate from the PCSM plan: (b)(5)(xiv)
Item (xiv) adds that the E&S plan must be separate from the PCSM plan, labeled “E&S” or “Erosion and Sediment Control Plan,” and serve as the final construction plan unless DEP approves otherwise.
HQ and EV waters: (b)(6)
In the permit application, the applicant must evaluate nondischarge alternatives for the E&S plan. If the applicant shows none exist, the plan must include ABACT (Antidegradation Best Available Combination of Technologies), subject to an exception in 25 Pa. Code 93.4c(b)(1)(iii). The alternatives and design standards are listed in DEP’s Erosion and Sediment Pollution Control Program Manual (No. 363-2134-008, April 2000, as amended). See our 102.11 page for how that manual is referenced.
Alternatives, availability and requests: (b)(7) to (b)(9), (c), (d)
- (b)(7): DEP may approve alternative BMPs that maintain and protect existing water quality and designated uses.
- (b)(8): the plan, inspection reports and monitoring records must be kept at the project site for DEP or conservation district inspection at all stages.
- (b)(9): after a complaint or site inspection, DEP or the district may require the plan to be submitted for review and approval.
- (c): DEP, or the district after consulting DEP, may require more information or alternative BMPs on a case-by-case basis to protect water quality and uses.
- (d): before starting, the person must obtain any other permits or authorizations related to the activity from DEP or the district.
- (e): where 102.5 requires permit coverage, it must be in place before earth disturbance begins.
What this page does not say
- Stabilization timelines, stockpile rules and phasing details: not stated in 102.4. Stabilization is covered separately on our 102.22 page.
- Fees: not stated in 102.4; see the 102.6 page.
Sources
- 25 Pa. Code 102.4, Erosion and sediment control requirements (Cornell Legal Information Institute, checked Nov 23, 2026)
Related
All Pennsylvania site work regulations · NPDES overview · NPDES glossary
FAQ
How often must E&S BMPs be inspected under 102.4(b)(5)(x)?
The plan’s maintenance program must provide for inspection weekly and after each stormwater event, with a written report for each inspection and maintenance action.
Who prepares an E&S plan?
A person trained and experienced in E&S control methods suited to the project’s size and scope, under paragraph (b)(3).
Where must the plan be kept?
At the project site, available with inspection reports and monitoring records for DEP or conservation district inspection at all stages, under paragraph (b)(8).
What extra step applies near HQ or EV waters?
The applicant evaluates nondischarge alternatives, and if none exist the plan must include ABACT, under paragraph (b)(6).
General information only. This page does not state or imply that any company complies with these rules, and it is not legal advice. The regulation text and DEP control. Source checked Nov 23, 2026; verify against the current source.