Rock Construction Entrance

A rock construction entrance, sometimes called a stabilized construction entrance, is a pad of stone where vehicles enter and leave a site. It removes mud from tires before trucks reach the road.

What PA DEP says

PA DEP’s fact sheet for single-family lots (3150-FS-DEP4096) describes the entrance as installed along the roadway to remove mud from construction vehicle tires before they leave the site. DEP’s E&S FAQ says matting is not a substitute for a rock construction entrance, and that using matting as one would itself count as earth disturbance. The same FAQ notes that a low-rated control can be improved by adding a wash rack and a rock construction entrance.

Where it comes up

It is a standard BMP on an E&S plan, usually paired with a silt fence around the disturbed area. It is built from crushed stone, and keeping it working means topping it up or replacing it when it clogs. The two DEP documents above do not give a stone size, thickness or length. The standard construction detail described below does, but the specification in your own plan or from your conservation district controls.

What the standard detail shows

Pennsylvania plan sets reproduce DEP’s Standard Construction Detail 3-1 for the rock construction entrance. It appears on an applicant’s E&S detail sheet hosted by a DEP regional office, not in the E&S manual itself, so treat the numbers as a guide to what plans typically show. That sheet calls for AASHTO #1 aggregate at a minimum thickness of 8 inches. It also shows an option of 4 inches of rolled and compacted PennDOT 2RC aggregate over 4 inches of AASHTO #1. The drawing labels a 50 foot minimum length and a note says to extend the rock over the full width of the entrance. A geotextile fabric layer is shown under the stone, though the sheet gives no fabric specification.

Keeping the entrance working

The notes on that detail say to remove topsoil before installing the rock, and to keep the thickness at the specified dimensions by adding rock, with a stockpile maintained on site for that purpose. Sediment deposited on paved roadways must be removed and returned to the construction site immediately. DEP’s single-family fact sheet says the same thing as an end-of-workday task. If excessive sediment still reaches the road, the detail says to extend the entrance in 50 foot increments or install a wash rack. It also says that washing the roadway or sweeping the deposits into roadway ditches is not acceptable, because that just moves the sediment into the drainage system.

Matting is a narrow exception

DEP’s E&S FAQ (item 38) says matting is not a substitute for a rock construction entrance unless equipment stays on the matting the entire time it is on the site. Otherwise, using matting as the entrance counts as earth disturbance. The FAQ also explains when plans are required: a written E&S plan is needed when total earth disturbance reaches 5,000 square feet, and an NPDES permit is needed before work begins on projects that will disturb at least one acre. DEP’s single-family fact sheet adds that E&S practices are required for all earth disturbance, even under 5,000 square feet. A small driveway or patio job may therefore still need controls even without a written plan.

Frequently asked questions

What is a rock construction entrance for?

To remove mud from vehicle tires so sediment is not tracked onto public roads.

Can I use matting instead?

DEP says matting is not a substitute for a rock construction entrance.

How big does it have to be?

Follow the dimensions on your approved plan or your conservation district’s standard detail. The standard detail we reviewed shows AASHTO #1 stone at least 8 inches thick and a 50 foot minimum length, but the two DEP documents do not list dimensions.