What Is a Sediment Trap? Size, 5-Acre Limit and PA DEP Dewatering Rules
A sediment trap is a small, temporary ponding basin that lets sediment settle out of stormwater on a construction site. EPA describes it for drainage areas of generally 5 acres or less, and says its short detention time is too brief to remove fine silts and clays. Larger drainage areas call for a sediment basin instead.
Sediment trap and the terms around it
- Sediment trap: per EPA, a small temporary basin made by excavating an area or placing an earthen embankment across a low area or swale.
- Sediment basin: the larger version. EPA points drainage areas over 5 acres to basins. See sediment basin.
- Dewatering: draining the stored water. See dewatering for pumped-water practices on a site.
- Compost filter sock trap: a trap built with a compost sock. PA DEP gives it its own freeboard and spillway rules, covered below. See compost filter sock.
- E&S plan: the written plan where a trap is shown. See erosion and sediment control plan.
Why it matters on a job
EPA’s fact sheet places a trap at the outlet of a diversion structure, channel, slope drain, wash rack or other conveyance that releases sediment-laden water. It says to put traps where they address the highest erosion areas, keep access easy for maintenance, and divert flow from undisturbed areas.
EPA’s reported typical sediment removal for a trap is 50 to 70 percent. It also says the effective life of a trap is usually 24 months or less. Those figures come from the fact sheet, and the fact sheet is a federal summary, so a Pennsylvania plan may differ.
Size and shape figures from EPA
EPA’s sediment trap fact sheet (EPA-832-F-21-028FF, December 2021) gives these points:
- Drainage area: generally 5 acres or less. EPA says some states and localities set smaller limits.
- Volume: many municipalities require at least 1,800 cubic feet per acre of drainage area.
- Embankment height: capped at 5 feet above original ground.
- Side slopes: no steeper than 2:1.
- Outlet width: at least 4 feet for a 1-acre drainage area, which EPA gives as a Tennessee example.
- Outlet lining: well-graded stone. EPA does not state a stone size.
- Length to width: no numeric ratio. EPA says pools with large length-to-width ratios are more effective.
- Depth: not stated.
Pennsylvania DEP points
The PA DEP erosion and sediment control FAQ has several items on traps. FAQ item 23 says the dewatering time for a trap is 2 to 7 days, and that draining in under 2 days is acceptable if the minimum skimmer orifice is used. It also says dewatering calculations are not required for traps. The skimmer orifice is sized using Figure 7.2 of the E&S Manual, and the minimum diameter is three-quarters of an inch.
FAQ item 28 covers compost sock traps. It says calculations are required for every trap, a compost sock trap included. A sock trap does not need the length-to-width ratio other traps use, and it needs no emergency spillway, but it needs at least 1 foot of freeboard above the maximum design water elevation. FAQ item 27 says a basin or trap bottom must sit above the seasonal high water table, with test pit logs submitted in Module 1. Soil borings and NRCS soil survey data are not accepted in place of test pits.
The FAQ states no drainage-area trigger for when a trap is required, and it states no cleanout rule. It does say a written E&S plan is required when earth disturbance reaches 5,000 square feet, and that projects of one acre or more generally need an NPDES permit. See NPDES. Verify against the current source before relying on any figure.
Inspection, cleanout and removal
- EPA says to inspect after each rainfall event, checking for erosion damage and proper drainage.
- EPA says to remove accumulated sediment when the trap reaches 50 percent of its capacity.
- EPA does not state how sediment should be removed or how the trap is closed out.
Limits
EPA lists three limits. A trap is unsuitable for large drainage areas, generally those over 5 acres. Its effective life is usually 24 months or less. And its detention time is too short to remove fine silts and clays. The fact sheet does not offer a fix for the fine-particle problem in this entry beyond pointing to a basin for larger areas.
Common mistakes
- Using a trap on a drainage area over 5 acres. EPA says that size calls for a basin.
- Letting sediment fill past half. EPA’s cleanout trigger is 50 percent of capacity.
- Setting the bottom in the water table. PA DEP says the bottom must be above the seasonal high water table.
- Skipping freeboard on a sock trap. PA DEP requires at least 1 foot above the maximum design water elevation.
- Skipping the after-rain check. EPA says to inspect after each rainfall event.
What the sources do not say
The EPA fact sheet states no trap depth, no stone size and no numeric length-to-width ratio. The PA DEP FAQ items cited here state no required volume per acre for traps and no cleanout trigger. We have not stated any of these here. The approved plan for your site sets them.
Sediment trap FAQ
What is the difference between a sediment trap and a sediment basin?
Size of drainage area is the line EPA draws. A trap is generally for 5 acres or less, and a basin is for larger areas, with EPA giving 5 to 100 acres as the typical basin range.
How big does a sediment trap have to be?
EPA says many municipalities require at least 1,800 cubic feet of storage per acre of drainage area. Pennsylvania figures come from the approved plan and the PA DEP manual, so confirm with the conservation district.
How long should a trap take to drain in Pennsylvania?
The PA DEP FAQ gives 2 to 7 days for traps. Draining in under 2 days is acceptable if the minimum skimmer orifice, three-quarters of an inch, is used.
When do you clean out a sediment trap?
EPA says to remove sediment when the trap reaches 50 percent capacity and to inspect after each rainfall event.
Sources
- U.S. EPA, NPDES BMP Fact Sheet: Sediment Traps (EPA-832-F-21-028FF, December 2021). Federal source, not specific to Pennsylvania. Its outlet-width example is from Tennessee.
- Pennsylvania DEP, Erosion and Sediment Control FAQ
Verify thresholds and dimensions against the current source before you rely on them.
Keep reading
- Hardscape and Site Work Glossary
- Related terms: sediment basin, compost filter sock, dewatering, erosion and sediment control plan and NPDES
Planning earthwork in central PA? Contact Muthler Landscaping & Construction for a straight answer. Planning information, not engineering advice.