NPDES construction stormwater permit in Pennsylvania: an overview
In Pennsylvania, a construction project that disturbs one acre or more of ground generally needs a National Pollutant Discharge Elimination System (NPDES) permit for stormwater, either an individual permit or coverage under a general permit such as PAG-02. The permit sits on top of the erosion and sediment control plan and, for permitted sites, a post construction stormwater plan.
General information only, not legal advice. The regulation text and DEP control. Whether a specific project needs a permit, and which one, should be confirmed with your county conservation district or DEP before ground is disturbed.
The trigger: one acre, including common plans
Under 25 Pa. Code 102.5(a), a person proposing an earth disturbance activity of 1 acre (0.4 hectare) or more, including as part of a larger common plan of development or sale, must obtain an individual NPDES permit or coverage under a general NPDES permit. The “common plan” language matters: a small lot that is one piece of a larger development can be counted with the rest.
DEP’s construction stormwater page says the same thing in plain terms. Construction activities with earth disturbances greater than or equal to one acre need NPDES coverage. Agricultural plowing or tilling, animal heavy use areas, timber harvesting and road maintenance are listed separately. Applicants may use the PAG-02 general permit for construction stormwater discharges, or PAG-01 if eligible. If an applicant is not eligible for either, an individual NPDES permit applies.
Permit types at a glance
| Option | What DEP says |
|---|---|
| PAG-02 | NPDES general permit for discharges of stormwater associated with construction activities, available to persons disturbing one or more acres who are eligible. |
| PAG-01 | General permit DEP lists alongside PAG-02 for eligible persons. |
| Individual NPDES permit | For applicants not eligible for a general permit. |
DEP’s page does not spell out eligibility for each general permit. Ask DEP or the conservation district which one fits before you pick.
How the application is filed
Section 102.6(a) provides that a person proposing or conducting an earth disturbance activity that requires a permit must submit to the Department or a conservation district a complete application or notice of intent (NOI). Under 102.6(c), it is not complete until the necessary information is provided. Conservation districts often handle the review locally; see our county conservation district pages.
What goes with the permit
- E&S plan: 25 Pa. Code 102.4(b) requires E&S BMPs and a written plan with drawings and a narrative, with weekly and post-storm inspections. See Chapter 102 erosion and sediment control.
- PCSM plan: 102.8(a) calls for a post construction stormwater management plan for a new earth disturbance activity that requires permit coverage under Chapter 102. Under 102.5(f), the permittee is responsible for ensuring implementation of the PCSM plan. See PCSM.
- Preconstruction meeting: 102.5(e) refers to attendance at a preconstruction meeting, including for critical stages of implementation of the approved PCSM plan.
Federal minimum controls
The federal rule for construction site stormwater, 40 CFR 450.21, sets requirements that apply to permits issued under it. Among them:
- Erosion and sediment controls (a): design, install and maintain effective erosion controls and sediment controls to minimize the discharge of pollutants.
- Soil stabilization (b): stabilization must start immediately when activities have permanently ceased, or when they have temporarily ceased on any portion of the site and will not resume for a period exceeding 14 calendar days.
- Dewatering (c): discharges from dewatering, including of trenches and excavations, are prohibited unless managed by appropriate controls.
- Prohibited discharges (e): wastewater from washout of concrete, unless managed by an appropriate control; wastewater from washout and cleanout of stucco, paint and form release oils; fuels, oils or other pollutants used in vehicle and equipment operation and maintenance; and soaps or solvents used in vehicle and equipment washing.
Pennsylvania’s permits and rules may add to these. Follow the stricter requirement where they differ, and read the terms of your actual permit.
Common mix-ups
- A written E&S plan can be required well below one acre (5,000 square feet under 102.4(b)(2)(i)). The NPDES permit is a separate, larger threshold.
- The acre is counted for the earth disturbance, not for the finished patio or wall footprint.
- A permit is not a substitute for waterway approvals under Chapter 105.
Sources
- 25 Pa. Code 102.5, Permit requirements (checked Nov 23, 2026)
- 25 Pa. Code 102.6, Permit applications and fees
- 25 Pa. Code 102.8, PCSM requirements
- PA DEP, Construction Stormwater
- 40 CFR 450.21, Effluent limitations (construction and development)
Related
All Pennsylvania site work regulations · NPDES glossary entry · Silt fence · Rock construction entrance
FAQ
At what size does a construction project need an NPDES permit in Pennsylvania?
Under 25 Pa. Code 102.5(a), at 1 acre (0.4 hectare) or more of earth disturbance, including as part of a larger common plan of development or sale.
What is PAG-02?
DEP describes PAG-02 as the NPDES general permit for discharges of stormwater associated with construction activities that persons disturbing one or more acres may apply for if eligible.
Is concrete washout water allowed to run off a site?
The federal rule at 40 CFR 450.21(e) lists wastewater from washout of concrete as a prohibited discharge unless managed by an appropriate control.
Do I file the application with DEP or the conservation district?
Section 102.6(a) provides for submitting a complete application or NOI to the Department or a conservation district. Ask your county conservation district which applies.