PA Chapter 102 erosion and sediment control: when a plan or permit is needed
Chapter 102 of Title 25 of the Pennsylvania Code is the state’s erosion and sediment control rule. It sets three different thresholds that people often blur together: a written plan at 5,000 square feet of earth disturbance, an NPDES stormwater permit at 1 acre, and a separate E&S permit at 5 or 25 acres for certain activities.
General information only, not legal advice. The regulation text controls. Confirm what applies to your project with your county conservation district or the Department of Environmental Protection (DEP) before you disturb ground.
Best management practices apply to any earth disturbance
Under 25 Pa. Code 102.4(b)(1), the implementation and maintenance of erosion and sediment (E&S) best management practices (BMPs) are required to minimize the potential for accelerated erosion and sedimentation. For agricultural plowing or tilling and animal heavy use areas, 102.4(a)(1) says BMPs are required including for activities that disturb less than 5,000 square feet. In other words, small size does not turn the BMP duty off.
The 5,000 square foot written plan
Section 102.4(b)(2) says a person proposing earth disturbance activities shall develop and implement a written E&S Plan if one or more listed criteria apply. The first, in (b)(2)(i), is that the activity will result in a total earth disturbance of 5,000 square feet (464.5 square meters) or more. Other requirements in the section fix what the plan must contain:
- The plan is prepared by a person trained and experienced in E&S control methods, under (b)(3).
- It must contain drawings and a narrative, under (b)(5).
- Its maintenance program must provide for inspection of BMPs on a weekly basis and after each stormwater event, with a written report documenting each inspection, under (b)(5)(x).
- The plan, inspection reports and monitoring records must be available for review and inspection, under (b)(8).
For the plain definition of the plan, see our glossary entry on the erosion and sediment control plan.
The 1 acre NPDES line, and the larger E&S permit lines
Section 102.5 sets the permit thresholds. Paragraph (a) covers a person proposing an earth disturbance activity of 1 acre (0.4 hectare) or more, including as part of a larger common plan of development or sale. That person must obtain an individual NPDES permit or coverage under a general NPDES permit. The other paragraphs cover E&S permits:
| Section | Activity | Threshold |
|---|---|---|
| 102.5(a) | Earth disturbance, including as part of a larger common plan of development or sale | 1 acre or more: NPDES permit |
| 102.5(b) | Timber harvesting or road maintenance | 25 acres (10 hectares) or more: E&S permit |
| 102.5(c) | Oil and gas activities | 5 acres (2 hectares) or more over the life of the project |
| 102.5(d) | Other activities not covered above | 5 acres (2 hectares) or more over the life of the project |
DEP’s construction stormwater page describes the same structure: construction activities with earth disturbances greater than or equal to one acre need NPDES coverage, using the PAG-02 general permit if eligible. An individual NPDES permit is for applicants who do not qualify for a general permit. See our NPDES construction stormwater permit overview.
How to apply
Section 102.6(a) says a person proposing or conducting an earth disturbance activity that requires a permit shall submit a complete application or notice of intent (NOI) to the Department or a conservation district. Under 102.6(c), an application or NOI is not complete until the necessary information is provided. Review and fees differ by district, so start with your county conservation district.
After construction: PCSM
Section 102.8(a) requires a post construction stormwater management (PCSM) plan for a person proposing a new earth disturbance activity that requires permit coverage under Chapter 102. See PCSM.
Sources
- 25 Pa. Code 102.4, Erosion and sediment control requirements (checked Nov 23, 2026)
- 25 Pa. Code 102.5, Permit requirements
- 25 Pa. Code 102.6, Permit applications and fees
- 25 Pa. Code 102.8, PCSM requirements
- PA DEP, Construction Stormwater
Related
All Pennsylvania site work regulations · Silt fence · NPDES · Chapter 105 waterways and wetlands
FAQ
When is a written E&S plan required in Pennsylvania?
Under 25 Pa. Code 102.4(b)(2), a written plan is required if one or more listed criteria apply. One is a total earth disturbance of 5,000 square feet (464.5 square meters) or more.
When is an NPDES permit required?
Section 102.5(a) applies to an earth disturbance activity of 1 acre (0.4 hectare) or more, including as part of a larger common plan of development or sale, and calls for an individual NPDES permit or coverage under a general NPDES permit.
Do E&S controls apply under 5,000 square feet?
Section 102.4(b)(1) requires implementation and maintenance of E&S BMPs to minimize accelerated erosion and sedimentation. The written plan trigger is separate. Check with your conservation district, because your municipality may add its own requirements.
Who reviews E&S plans?
Section 102.6(a) provides for submission of an application or NOI to the Department or a conservation district. Ask your county conservation district which process applies to your project.
General information only. This page does not state or imply that any company complies with these rules, and it is not legal advice. The regulation text and DEP control. Sources checked Nov 23, 2026.