Minimize Soil Compaction: PA Stormwater BMP Manual 5.6.2
Minimize soil compaction: how the PA BMP Manual describes it
Quick answer: BMP 5.6.2 in the Pennsylvania Stormwater Best Management Practices Manual treats soil as stormwater infrastructure. It asks designers to keep construction traffic and stockpiles off the soil that will later be lawn or planting beds, and to use quality topsoil with at least 5% organic content, a depth of at least 4 inches for turf and compaction no higher than 1,400 kPa.
What it is
BMP 5.6.2 is a non-structural practice in Chapter 5, titled “Minimize Soil Compaction in Disturbed Areas.” Its purpose is to protect soil quality during land development so that areas meant to stay pervious keep their stormwater functions. The manual says healthy, uncompacted soil supports nutrient cycling, reduces runoff and erosion, holds water, dampens storm surges, filters pollutants and supports roots, and that it reduces turf and landscape care. It adds that vegetated areas with compacted soil respond to storms much like impervious areas, especially in large events. The manual separates this from erosion and sediment control, which protects soil from washing away rather than from being squeezed.
Ratings in the manual
The manual credits 30% for total suspended solids and 0% for phosphorus and nitrate. Volume reduction, recharge and water quality are rated very high and peak rate control is rated high. Residential, commercial, ultra-urban, industrial, retrofit and highway uses are all marked as applicable. It applies to any development that has relatively healthy existing soil and proposed pervious areas. If soils are already compacted, the manual sends the reader to the soil restoration practice in Chapter 6.
Key design elements
- Protect disturbed soils from excessive compaction during construction.
- Minimize large cleared areas and topsoil stockpiling.
- Use quality topsoil and maintain soil quality after construction.
- Reduce the disturbed area through design and construction practices.
- Restore soils that were already degraded.
The soil management plan
Early in design the manual calls for a soil management plan, based on soil types, existing disturbance, runoff routing, trees and vegetation to keep, and tests of soil depth and quality. The plan sorts the site into zones:
| Zone | What the manual says |
|---|---|
| Protected areas | No soil or vegetation disturbance; protected soil organisms can later recolonize disturbed ground |
| Minimal disturbance areas | Limited disturbance; amendments may be needed before the area is fully pervious |
| Construction traffic areas | Need soil restoration if they are to count as pervious afterward; keep as small as practicable |
| Topsoil stockpile areas | Protect and maintain, then restore with compost and other amendments |
| Topsoil quality and placement | Test soils; meet Appendix C parameters |
Protected and minimal disturbance areas should be as large as possible, signed and fenced off from construction traffic.
Topsoil numbers
The manual says topsoil should meet the Appendix C parameters, with a minimum depth of 4 inches for turf and more for other vegetation. Organic content should be at least 5%, and compaction should not exceed 1,400 kPa. Topsoil must be bonded to the subsoil so water can pass between the layers. To bond them, spread a thin layer of 2 to 3 inches, till it into the subsoil, then apply the remaining topsoil. For a field check of compaction, see our guide to testing soil compaction with a penetrometer.
Construction steps in brief
- At the start, mark protected and minimal disturbance areas with signs and fencing on the construction drawings.
- Enforce those areas strictly.
- Shield them from excess sediment and runoff while upslope areas are disturbed.
- Protect topsoil stockpiles at all times, then bond and place topsoil as described above.
Maintenance
The manual says a properly protected site needs considerably less maintenance, with healthier landscaping, higher survival rates and less irrigation and fertilizer. Frequent lawn mowing can compact soil after construction and should be avoided where possible, and native, low-maintenance plantings are described as the best way to avoid maintenance damage. Protected areas on private property could be secured with an easement, deed restriction or other legal measure. For lawns that are already compacted, see how to fix compacted lawn soil in Pennsylvania and effects of soil compaction.
Costs
The manual gives no dollar figures. It says the practice generally results in significant construction cost savings through less disturbance, clearing, earthwork and soil restoration, and through smaller engineered stormwater systems. Better topsoil can lower landscaping cost through higher survival and less replanting, while design costs may rise slightly because of more site-specific planning.
Where the manual contradicts itself
- Restoration: the description says lost soil functions can never be completely restored, yet the practice itself, and the related 5.6.1 grading practice, rely on soil restoration to recover permeability.
- Stockpiles: a key element says to minimize topsoil stockpiling, while the plan includes designated stockpile areas to protect and later restore.
- Water quality rating: water quality is rated very high, but phosphorus and nitrate credits are 0% and only 30% is credited for solids.
Pennsylvania approvals and who designs it
A soil management plan, topsoil specification and any stormwater credit claimed for protected soil need a qualified professional, and may be reviewed by your municipality, the county conservation district or DEP. Check whether an erosion and sediment plan or NPDES permit applies (see Chapter 102 and PA stormwater plan rules). See also the glossary entries for compaction and topsoil stripping.
Sources
- Pennsylvania Department of Environmental Protection, Pennsylvania Stormwater Best Management Practices Manual (363-0300-002, December 30, 2006), BMP 5.6.2 Minimize Soil Compaction in Disturbed Areas, via the PA DEP eLibrary. Checked Nov 23, 2026.
Related
All drainage guides · Soil structure · Soil organic matter · Infiltration trench
FAQ
How much topsoil does the manual call for?
At least 4 inches for turf and more for other vegetation, with organic content of at least 5%.
What compaction limit does the manual give?
Topsoil compaction should not exceed 1,400 kPa.
How should topsoil be tied to the subsoil?
Spread a thin 2 to 3 inch layer, till it into the subsoil, then add the rest of the topsoil.
Can compacted soil be fully restored?
The manual says lost functions can never be completely restored, yet it also calls for soil restoration where soil is already compacted.
Planning information only. Design must be done by a qualified professional and approved by your municipality and, where required, DEP. Source checked Nov 23, 2026.