NPDES
NPDES stands for National Pollutant Discharge Elimination System, the permit system under the federal Clean Water Act. For construction, it is the stormwater permit required once a project disturbs enough ground.
What it means
Pennsylvania’s Chapter 102 defines NPDES as the national permitting system under section 402 of the Clean Water Act, including EPA-approved state programs and the Chapter 92 regulations. In practice a construction NPDES permit covers stormwater discharges from earth disturbance.
The 1-acre line
PA DEP says construction projects that disturb one acre or more of earth and need NPDES coverage require a Chapter 102 permit. Operators may apply for coverage under the PAG-02 general permit if eligible. DEP also lists PAG-01, a general permit for small construction activities. If an applicant does not qualify for either, an individual NPDES permit applies. Agricultural plowing or tilling, animal heavy use areas, timber harvesting and road maintenance are excluded from this requirement. DEP’s fact sheet adds that a disturbance under one acre can still need a permit when it is part of a larger common plan of development, such as a house on a half-acre lot in a subdivision.
In the field
An NPDES permit sits on top of the E&S plan, and larger sites also need a post-construction plan (PCSM). Your county conservation district is where local review and fees are posted. Fees and steps differ by district.
Permit types in Pennsylvania
DEP’s Chapter 102 page sorts permits by activity and size. Construction that needs NPDES coverage at one acre or more of earth disturbance uses PAG-01, PAG-02 or an individual NPDES permit. Timber harvesting and road maintenance need an E&S permit at 25 or more acres, oil and gas activities at 5 or more acres, and other activities not listed at 5 or more acres. The individual NPDES application applies when a project is not eligible for either general permit. DEP’s page does not spell out the eligibility criteria for PAG-01 or PAG-02, so ask DEP or your conservation district before choosing one.
Common plan of development
EPA’s construction stormwater page makes the same point as DEP’s fact sheet: a site under one acre is still covered when it is part of a common plan of development or sale that will ultimately disturb one or more acres. DEP’s example is a half-acre lot in a development where other homes are being built, and it adds that most individual lot sites can avoid a permit when they are not part of a larger common plan. The fact sheet says to confirm with the county conservation district. It also says a licensed professional such as an engineer, geologist, surveyor or landscape architect is best suited to prepare an NPDES application.
Federal minimums to know
EPA’s page lists minimum limits that every construction stormwater permit must include under the federal rule at 40 CFR 450.21. They include designing, installing and maintaining erosion and sediment controls, stabilizing disturbed areas right after construction stops if work will not resume within 14 days, and prohibiting discharges of concrete washout wastewater, paint, stucco, form release oil, fuels, oils, soaps and solvents unless controlled. EPA’s own Construction General Permit applies only where EPA is the permitting authority, so Pennsylvania projects follow DEP’s permits. Pennsylvania’s FAQ uses its own stabilization trigger of more than 4 days, so follow the stricter state and local terms.
Common mistakes
Judging a job by the size of the patio instead of the total disturbed ground, forgetting that stockpiles and clearing count, assuming a subdivision lot is exempt because it is small, and treating an E&S plan and an NPDES permit as the same thing. DEP’s FAQ says E&S practices are required for any earth disturbance regardless of size. Related entries: impervious surface and silt fence. This page is planning information only. Confirm permit requirements with DEP or your county conservation district.
Frequently asked questions
When do I need an NPDES permit in Pennsylvania?
At one acre or more of earth disturbance, per PA DEP, and sometimes below that when the work is part of a larger common plan of development.
What is PAG-02?
A general permit for construction stormwater that eligible operators disturbing one or more acres can apply for, instead of an individual permit.
Is a patio job big enough to need one?
A single residential patio is usually far below one acre, but the whole project’s disturbance counts. Ask your conservation district if you are unsure.
Sources
- 25 Pa. Code 102.1 (definitions)
- PA DEP: Construction Stormwater
- PA DEP fact sheet 3150-FS-DEP4096 (Rev. 6/2015), as posted by Brighton Township