Production rates · Nov 2026 · central PA crew data
Landscape production rates: pavers and walls per crew-day
A three-man crew lays about 140 sq ft of paver patio a day, from excavation through poly sand, and sets about 44 sq ft of block wall face a day. Those are our planning rates: 0.17 man-hours per sq ft of patio and 0.55 per sq ft of wall face, checked against one fully clocked wall job.
What are the production rates?
| Work | Planning rate | Per man, per day | 3-man crew, per day | Basis |
|---|---|---|---|---|
| Paver patio, excavation through poly sand | 0.17 MH/sq ft | 47 sq ft | 141 sq ft | Planning rate from our bid model. Not a stopwatch number. |
| Retaining wall, Belgard Diamond Pro, per sq ft of counted block face | 0.55 MH/sq ft | 15 sq ft | 44 sq ft | Planning rate, checked against one clocked wall at 0.58 MH/sq ft (n = 1). |
MH = man-hours of on-site work. A crew-day is the number of men times 8 paid hours on site. Drive time, shop time, permits, 811 marking and weather days are not in these rates; add them to your schedule separately. Counted block face includes the buried first course, because the crew sets it.
How many square feet of pavers can a crew lay in a day?
About 47 sq ft per man per day, start to finish, which is 94 sq ft for two men, 141 for three and 188 for four. That covers the whole patio, not just laying: layout, excavation, hauling spoils, base, bedding sand, pavers, cuts, edge restraint and polymeric sand.
| Crew | Man-hours per day | Patio sq ft per day |
|---|---|---|
| 2 men | 16 | 94 |
| 3 men | 24 | 141 |
| 4 men | 32 | 188 |
- Layout and excavation to subgrade
- Hauling spoils off site
- 8 inches of compacted 2A stone, fabric and 1 inch of bedding sand
- Setting pavers, cutting, edge restraint and polymeric sand
- Steps, seat walls and retaining walls
- Drainage, lighting and planting
- Removing an old patio
- Bad access, heavy grade changes or soft subgrade
This is a planning rate: the labor a typical backyard patio price can carry after materials and overhead. Our paver jobs this season were mixed with steps, walls or repairs, so our clocks cannot isolate a clean patio rate yet. Front-yard and walkway work varies more, so we do not publish one number for it.
How long does a paver patio take to install?
A 300 sq ft backyard patio is about 51 man-hours, which is roughly two days for a three-man crew. These are our arithmetic from the 0.17 man-hours per sq ft planning rate, with 8-hour crew-days and no weather delays.
| Patio size | Man-hours | 2 men (days) | 3 men (days) | 4 men (days) |
|---|---|---|---|---|
| 200 sq ft | 34 | 2.1 | 1.4 | 1.1 |
| 300 sq ft | 51 | 3.2 | 2.1 | 1.6 |
| 400 sq ft | 68 | 4.3 | 2.8 | 2.1 |
| 500 sq ft | 85 | 5.3 | 3.5 | 2.7 |
For the homeowner view of the same job, see how long a paver patio takes and how to estimate a paver patio.
How many square feet of retaining wall can a crew build in a day?
About 15 sq ft of block face per man per day, all in. At our 0.55 man-hour planning rate that is 29 sq ft for two men, 44 for three and 58 for four. Our one fully clocked wall came in at 0.58, so a 4-man crew ran about 55 sq ft a day.
| Crew | Man-hours per day | Planning, 0.55 (sq ft per day) | Clocked, 0.58 (sq ft per day) |
|---|---|---|---|
| 2 men | 16 | 29 | 28 |
| 3 men | 24 | 44 | 41 |
| 4 men | 32 | 58 | 55 |
What did the clocked wall actually include?
| Item | Measured on the job |
|---|---|
| Wall | Belgard Diamond Pro, 8 x 18 x 12 in block, about 4 ft exposed, about 37.5 ft long, central PA, Nov 2026 |
| Quantity | 160 block units (about 160 sq ft of counted face) plus 27 caps |
| Reinforcement and drainage | 3 layers of geogrid, 6 ft deep each; crushed stone base; 12 in of drain stone behind the wall |
| Clocked work hours | 93.4 over 5 crew-days (crew of 1, 2, 4, 4 and 2 men) |
| Result | 0.58 MH per sq ft of counted face, about 14 units set per man per day, dig through caps |
| Sample size | One wall. Treat it as a data point, not an average. |
Hours come from our GPS time clock in Muthler OS and count on-site work only; drive and shop time are excluded. That wall was built along a driveway, and most walls that size run a little under it, so we plan at 0.55 instead of 0.58.
How long does a retaining wall take to build?
A 100 sq ft wall face is about 55 man-hours, which is roughly two and a half days for a three-man crew. The table below is our arithmetic from the 0.55 planning rate, in 8-hour crew-days.
| Counted face | Man-hours | 2 men (days) | 3 men (days) | 4 men (days) |
|---|---|---|---|---|
| 60 sq ft | 33 | 2.1 | 1.4 | 1.0 |
| 100 sq ft | 55 | 3.4 | 2.3 | 1.7 |
| 150 sq ft | 83 | 5.2 | 3.4 | 2.6 |
| 200 sq ft | 110 | 6.9 | 4.6 | 3.4 |
| 300 sq ft | 165 | 10.3 | 6.9 | 5.2 |
The published timelines for the same job, side by side, are in our retaining wall timeline guide. For cost, see retaining wall cost.
How many blocks make up 100 square feet of wall face?
It depends on the block. A Belgard Diamond Pro unit covers 1 sq ft, so 100 sq ft is about 100 units. A Versa-Lok Standard unit covers 0.667 sq ft, so the same face is about 150 units. Convert units to face before you apply any rate.
| Block | Size (in) | Face per unit | Units per 100 sq ft | Weight per unit | Our rate |
|---|---|---|---|---|---|
| Belgard Diamond Pro | 8 x 18 x 12 | 1.0 sq ft | 100 | About 77 lb | 0.55 planning, 0.58 clocked (n = 1) |
| Belgard Diamond Pro Air | 8 x 18 x 12 (Smooth Face 11.5 deep) | 1.0 sq ft | 100 | 54 lb | Not published yet |
| Versa-Lok Standard | 6 H x 14/16 W x 12 D | 0.667 sq ft | 150 | 82 lb | Not published yet |
Sources: Belgard Diamond Pro Smooth Face cut sheet, Northfield, revised 01/2025 (36 units and 2,773 lb per pallet, which gives the roughly 77 lb per unit, our arithmetic); Belgard Diamond Pro Air cut sheets, 2024 and 2025 (1 sq ft block, 54 lb); Rochester Concrete Products, Versa-Lok Standard cut sheet (0.667 sq ft face, 82 lb, no date shown). One regional dealer’s product page lists the Diamond Pro unit at 1.5 sq ft, which conflicts with Belgard’s own cut sheets, so confirm the unit coverage before you quote from a dealer’s page. We publish a rate for a block only after a finished job gives us clocked hours and a counted quantity.
What slows a crew down?
- Long hauls from truck to work area
- Wet, soft or rocky subgrade
- Slopes that need benching or step-downs
- Tight staging beside a driveway or house
- Walls taller than about 4 feet need more geogrid and, per the sources in our timeline guide, an engineer
- Curves, corners, steps and many cuts
- Drain pipe and extra drain stone
- Thicker base on poor soil
- 811 marking before any dig
- Permit or inspection holds
- Rain and frozen ground
- New crew members and mixed crews
We have not clocked enough jobs to publish a percentage for any of these, so we do not. Treat the planning rates as a clean-site, hand-set starting point and walk the actual site before you price.
How should you use these rates on a bid?
Patio: square feet of finished surface. Wall: counted face, including the buried course, from your block count times face per unit.
Square feet times man-hours per sq ft gives on-site man-hours. Divide by the crew’s daily man-hours for crew-days.
These are on-site work hours. Add round-trip drive time for every man, truck fuel and wear, and daily startup and shutdown for each crew-day separately.
For commercial work, see how to bid commercial landscaping jobs. Machine-set large block is a different job: Redi-Rock publishes 300 to 600 sq ft of wall face per day for its machine-set system, depending on block type, access, equipment, complexity and crew experience (Redi-Rock construction efficiency FAQ, no date shown). The rates above are for hand-set segmental block of the size used on residential walls.
Questions
How many square feet of pavers can a crew lay in a day?
At our planning rate of 0.17 man-hours per sq ft, a two-man crew finishes about 94 sq ft of typical backyard patio a day, a three-man crew about 141 and a four-man crew about 188. That includes excavation, base, bedding sand, pavers, edge restraint and polymeric sand.
How many man-hours per square foot is a paver patio?
About 0.17 man-hours per sq ft on a typical backyard patio, start to finish. It is a planning rate from our bid model, not a clocked average, and it excludes steps, walls, drainage and difficult access.
How many square feet of retaining wall can a crew build in a day?
At our planning rate of 0.55 man-hours per sq ft of counted block face, a three-man crew builds about 44 sq ft a day. Our one fully clocked wall ran 0.58 man-hours per sq ft, about 55 sq ft a day for a four-man crew.
How many blocks are in 100 square feet of retaining wall?
About 100 Belgard Diamond Pro units (1 sq ft each) or about 150 Versa-Lok Standard units (0.667 sq ft each). Check the manufacturer’s cut sheet for the block you are using.
Do these rates include drive time?
No. They are on-site work hours only. Add drive time, daily startup and shutdown, permits, 811 marking and weather separately.
Are these rates for machine-set walls?
No. They are for hand-set segmental block of the size used on residential walls. Redi-Rock publishes 300 to 600 sq ft of wall face per day for its machine-set system.
Need the design before the crew shows up?
Muthler Landscaping and Construction builds the designs behind these jobs. Start at online landscape design, or call (570) 397-9800. More guides: pavers and patios, retaining walls and how long home projects take.
Planning rates for estimating only, not a Muthler schedule, quote or promise. Actual time depends on your site, materials, crew, weather and permits. Wall hours are from one Muthler job tracked on our GPS time clock in November 2026; the patio rate is a bid-model planning rate. Sources: Belgard Diamond Pro cut sheets; Rochester Concrete Products Versa-Lok Standard cut sheet; Redi-Rock construction efficiency FAQ. Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.