Preconstruction meeting, PPC plan and co-permittees under 25 Pa. Code 102.5(e) to (l)
The thresholds in 25 Pa. Code 102.5(a) through (d) get most of the attention. The rest of the section, paragraphs (e) through (l), covers the preconstruction meeting with a 7-day notice, who is responsible for the PCSM plan, when other permits make a separate Chapter 102 permit unnecessary, when a co-permittee is required, and when a pollution prevention contingency (PPC) plan is needed.
General information only, not legal advice. This page paraphrases the regulation text. Verify against the current source before relying on any detail. Anything the source did not state is marked “not stated.” The thresholds themselves are on our Chapter 102 thresholds page and the NPDES overview.
Preconstruction meeting: 102.5(e)
Permitted projects must hold a preconstruction meeting unless the Department of Environmental Protection (DEP) or the conservation district says otherwise in writing. The permittee must invite DEP or the district and give all invitees at least 7 days’ notice. Attendance is required of the following:
- Permittees and co-permittees.
- Operators.
- The responsible licensed professionals or their designees, including those overseeing implementation of the erosion and sediment (E&S) and post construction stormwater management (PCSM) plans and the critical implementation stages.
The role of the licensed professional at critical stages is covered on our record drawings and notice of termination page. What the meeting agenda must include is not stated in 102.5. Permit coverage itself must be in place before earth disturbance begins, a point also made in 102.4 and covered on the E&S plan contents page.
Responsibility for the PCSM plan: 102.5(f)
The person proposing a permitted activity is responsible for making sure the PCSM plan is implemented. The contents of that plan are on our PCSM plan contents page.
Other Department permits: 102.5(g)
If a Department permit issued under a different chapter, not Chapter 92 or 102, already requires compliance with Chapters 92 and 102, no additional E&S or NPDES permit is needed. Which specific permits meet that description is not stated in this paragraph. Our Chapter 105 waterways and wetlands page covers a separate set of DEP approvals, and this page does not say whether Chapter 105 permits fall within paragraph (g).
Co-permittees: 102.5(h)
Any operator who is not the permittee must be a co-permittee. The glossary has a short definition of NPDES for the permit type that most often involves these roles.
Section 404 overlap: 102.5(i)
Activities that discharge dredged or fill material to U.S. waters and need a Clean Water Act section 404 permit do not need a separate E&S or NPDES permit for the area that the 404 permit covers. The section 404 program is federal, and this page does not describe how it works beyond this overlap.
Agricultural exemptions: 102.5(j)
Agricultural plowing or tilling and animal heavy use areas do not need an E&S or NPDES permit under Chapter 102.
Unpermitted activities: 102.5(k)
Activities that do not need a permit under Chapter 102 must still comply with the chapter’s other provisions.
Pollution prevention contingency plan: 102.5(l)
A PPC plan is required when certain materials are stored, used or transported on, onto or from a site during earth disturbance. The materials named are:
- Fuels, chemicals, solvents and petrochemicals.
- Pesticides, fertilizers and lime.
- Wastewater and cement.
- Sanitary or solid waste.
- Hazardous materials.
The PPC plan must be available to DEP or the conservation district on request. The design reference for these plans is named in 102.11(a)(4), covered on our 102.11 page. Whether a minimum quantity triggers the requirement is not stated in 102.5. For the glossary meaning of a related site practice involving cement, see concrete washout.
General permits for non-NPDES activities: 102.5(m)
The Department may issue general permits for non-NPDES activities. The steps are:
| Paragraph | What it says |
|---|---|
| (m)(1) | A general permit may cover a region, the whole state, specific watersheds, stream categories or geographic areas, if DEP finds the projects similar, adequately regulated through standard specifications, better suited to a general permit, and without significant adverse impact individually or cumulatively. |
| (m)(2) | Contents: the covered activity and exceptions, geographic areas, standard specifications or another agency’s criteria, operating, maintenance, inspection and monitoring conditions, and how to obtain coverage. |
| (m)(3) | At least 30 days before issuance, DEP publishes notice and the proposed text in the Pennsylvania Bulletin and accepts written comments. It may hold a public hearing. |
| (m)(4) and (m)(5) | Persons under a general permit must follow its terms. General permits may be issued, amended, suspended, revoked, reissued or terminated, and issuing one does not exempt anyone from Title 25. |
| (m)(6) | DEP may deny, revoke, suspend or terminate coverage for noncompliance and may require an individual permit instead. |
What this page does not say
- Meeting agendas, minutes or sign-in rules: not stated in 102.5.
- Fees for permit coverage: not stated in 102.5; see our 102.6 page.
- Whether any particular project needs a co-permittee or a PPC plan: this page does not decide that.
Sources
- 25 Pa. Code 102.5, Permit requirements (Cornell Legal Information Institute, checked Nov 23, 2026)
Related
All Pennsylvania site work regulations · PCSM glossary · Site stabilization
FAQ
How much notice is required for the preconstruction meeting?
Section 102.5(e) says the permittee must invite DEP or the district and give all invitees at least 7 days’ notice, unless DEP or the district says in writing that no meeting is needed.
Who must attend?
Permittees, co-permittees, operators, and the responsible licensed professionals or designees, including those overseeing E&S and PCSM plan implementation and critical stages.
When is a PPC plan required?
When materials such as fuels, chemicals, solvents, pesticides, fertilizers, lime, cement, waste or hazardous materials are stored, used or transported on, onto or from the site during earth disturbance.
Who must be a co-permittee?
Under 102.5(h), any operator who is not the permittee.