Home / Guides / How to hire a contractor in Pennsylvania

Guide · 2026 · Pennsylvania · Home Improvement Consumer Protection Act

How to hire a contractor in Pennsylvania

Check the contractor’s registration with the Attorney General before you sign, get a written contract that includes the items state law requires, and pay nothing before it is signed. Pennsylvania’s Home Improvement Consumer Protection Act (HICPA) sets those rules for work on a private home. The legal rules below come from the statute or the Attorney General, with the section cited.

Deposit cap on contracts over $5,000One-third of the price
Check a contractor (AG)Call (570) 397-9800

Check these seven things before you sign

StepCheckWhat the law or the Attorney General says
1RegistrationA contractor who does $5,000 or more of home improvement work a year must be registered with the Attorney General. Look the number up before you sign, in the AG’s search portal (hicsearch.attorneygeneral.gov) or on the helpline, 1-888-520-6680. The Attorney General says registration is not an endorsement of a contractor’s competency or skill.
2The number in writingThe registration number has to appear on every contract, estimate, proposal and advertisement (§ 517.6). If a quote or ad has none, ask for it before going further.
3InsuranceThe contract must state the contractor’s liability coverage and promise to keep at least $50,000 for personal injury and $50,000 for property damage (§§ 517.4, 517.7(a)(11)). The Attorney General says to ask for current proof, because the proof on file was given when the contractor registered.
4Written contractNo home improvement contract is valid or enforceable against you unless it meets every requirement in § 517.7(a), listed below. HICPA covers work with a total agreed price of more than $500. The contractor must give you a complete copy at signing, free of charge (§ 517.7(c)).
5Payment before signingNone. A contractor may not demand or receive any payment for a home improvement before the contract is signed (§ 517.9(9)).
6DepositOn contracts over $5,000, no more than one-third of the price, plus the cost of special-order materials designated in the written contract. The contract must list the down payment and any special-order advance separately (§§ 517.9(10), 517.7(a)(9)).
7CancellationYou can cancel without penalty within three business days of signing, wherever you signed, except for emergency work covered by the state consumer protection law. The contract must include notice of this right (§ 517.7(b)).

Section numbers are from 73 P.S. §§ 517.1 to 517.19 (Act 132 of 2008). Plain-English checklist, not legal advice.

What the contract has to say

Who and when
  • Written and legible, with the contractor’s registration number.
  • Signed by you and by the contractor or its salesperson.
  • The date of the transaction.
  • The contractor’s name, address (a P.O. box alone does not count) and phone number.
  • Approximate start and completion dates.
What and how much
  • A description of the work, the materials and the specifications. Changes need a written change order signed by both sides.
  • The total price, or a time-and-materials clause with a written initial estimate and costs capped at 10% over it.
  • The down payment and any special-order advance, listed separately.
  • The entire agreement, with copies of the required notices attached.
Your protections
  • Names, addresses and phone numbers of the subcontractors known when you sign.
  • The contractor’s agreement to keep liability insurance, and the current coverage amount.
  • The Attorney General’s toll-free number.
  • Notice of your right to cancel.

Those are the 13 items in § 517.7(a). A contract that leaves any out cannot be enforced against you. Our page on the 13 required terms goes item by item. You can also void a contract that contains certain clauses, including a hold-harmless clause, a jury-trial waiver, a confession of judgment or an award of attorney fees to the contractor (§ 517.7(e)); see voidable clauses and arbitration.

Paying for the job

HICPA caps the deposit. It does not set a schedule for later payments, and the Act has no specific final-payment rule. That makes the contract the place to protect yourself. Our advice: make each payment a stated amount tied to stated finished work, and keep a record of every payment. Any change to the work should be a written change order signed by both sides, which the Act requires for changes to the specifications (§ 517.7(a)(7)). On a time-and-materials job, the contractor must give you a written initial estimate before work starts, and the contract must say costs cannot run more than 10% over it without a signed change order (§ 517.7(a)(8)).

Red flags

Fraud signs the AG lists
  • False or misleading statements to win the job or justify a price increase.
  • Taking an advance and not doing the work or refunding it.
  • Damaging your property to get the work.
  • Posing as a government or utility worker.
  • Calling an item special order when it is not, or misstating its cost.
  • Changing your documents without your consent.
  • False or deceptive advertising.
Also prohibited (§ 517.9)
  • Demanding or taking payment before the contract is signed.
  • Doing home improvement work without registering.
  • Abandoning the job or failing to perform without justification.
  • Departing from the plans without a signed change order.
Penalties

Permits, digging and liens

Permits

Ask who pulls the permit and what your municipality requires before work starts. Code enforcement differs by municipality: see opt-in and opt-out municipalities and the Pennsylvania building code page. Confirm with your township or borough code office.

Digging

If the job involves digging, ask who is calling 811. Pennsylvania requires a call at least three business days before digging, per the PA Public Utility Commission. See our 811 guide.

Subs, suppliers and liens

The contract must list the subcontractors known when you sign. Ask about suppliers and about lien waivers, and ask for a workers’ compensation certificate. See lien deadlines, lien waivers and who must carry workers’ comp.

If something goes wrong

  • Nothing started: if no substantial part of the work is done and more than 45 days have passed since the start date in the contract, send a refund request by certified mail. The contractor must refund within 10 days (§ 517.9(2)).
  • Complain: file with the Attorney General using the online consumer complaint form, or call the HICPA helpline at 1-888-520-6680.
  • Defective contract: a contract that leaves out required items cannot be enforced against you, but courts have still let contractors sue for the reasonable value of work in some cases, so it is not a free job. See our page on contracts that do not follow HICPA.
  • A dispute over money or work: talk to a Pennsylvania attorney. This guide is a summary, not legal advice.

Check us the same way

Muthler Landscaping & Construction LLC is registered with the Pennsylvania Attorney General as PA HIC #PA212584. Look it up in the AG’s search portal before you sign with us or anyone else. We build patios, retaining walls, walkways and drainage across central Pennsylvania. Call (570) 397-9800 or request a free estimate.

More guides for homeowners

Questions

How do I check if a contractor is registered in Pennsylvania?

Search the Attorney General’s registration portal at hicsearch.attorneygeneral.gov, where the registration number field gives an exact result, or call the helpline at 1-888-520-6680. The portal’s results list active registrations. Registration is not an endorsement of a contractor’s skill.

Does Pennsylvania require a contractor license?

The statewide program the Attorney General runs is registration, not a license. A contractor who does $5,000 or more of home improvement work a year must register. The Attorney General’s current application instructions list a non-refundable $100 fee, and a registration lasts two years. Your township or borough may have its own rules, so ask its code office.

How much deposit can a contractor ask for in Pennsylvania?

On a home improvement contract over $5,000, no more than one-third of the price, plus the cost of special-order materials designated in the written contract. No payment of any kind is allowed before the contract is signed.

Can I cancel a home improvement contract in Pennsylvania?

Yes. You can cancel without penalty within three business days of signing, wherever you signed. In Commonwealth v. Gillece Services, decided April 30, 2026, the Pennsylvania Supreme Court held that the contractor must honor a cancellation by phone, in writing or in person as long as it has actual notice. Putting it in writing as well gives you proof of the date.

Does a small job need a written contract?

HICPA covers home improvement work when the total agreed price is more than $500, and every contract it covers must be in writing and signed. Below $500 its contract rules do not apply, but a written agreement is still a good idea.

What if a contractor took a deposit and never started?

If no substantial part of the work is done and more than 45 days have passed since the start date in the contract, send a refund request by certified mail; the contractor must refund within 10 days. Keeping an advance without doing the work or refunding it can also be home improvement fraud. You can file a complaint with the Attorney General.

Sources, checked Nov 24, 2026: Home Improvement Consumer Protection Act, Act 132 of 2008, 73 P.S. §§ 517.1 to 517.19 (Attorney General copy of the Act; FindLaw, §§ 517.7 and 517.9); PA Attorney General, Helpful Home Improvement Information; PA Attorney General, Contractor Frequently Asked Questions; PA Attorney General, Home Improvement Contractor Registration Application Instructions (revised Feb. 18, 2026); PA Attorney General HICPA registration page and search portal (hicsearch.attorneygeneral.gov); PA Attorney General news release of May 1, 2026; Commonwealth v. Gillece Services, L.P., No. 32 WAP 2024 (Pa. Apr. 30, 2026); PA Public Utility Commission, PA One Call. Plain-English summary, not legal advice; statutes get amended, so confirm against the current text and talk to a Pennsylvania attorney about your own situation. Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.