Change order #[01] · Date: [Date]
Project: [Project name] · [Property address]
[Company]
[Street address]
[Phone]
License/Reg. #[#]
1. Contract reference
Owner: [Owner name]
Original contract dated [date], contract #[000].
Previous change orders: [none / #1 (+$0), #2 (-$0)]
2. Description of the change
This change order modifies the work in the contract above as follows. All other terms of the contract stay the same.
- Added, removed or changed: [e.g. add 12 LF of 4 in. drain pipe from downspout to daylight]
- Location: [e.g. north side of patio, plan sheet L-1]
- Materials and specs: [product, size, quantity]
- Plan or drawing revision: [sheet and date, or none]
Write the change in quantities and dimensions, the same way the original scope is written. “Extra drainage” starts an argument; “12 LF of 4 in. solid pipe, 2% fall, pop-up outlet” ends one.
3. Reason for the change
☐ Owner request ☐ Unforeseen site condition ☐ Code or inspector requirement ☐ Other: [explain]
Details: [e.g. ledge rock found 14 in. below grade; owner asked to widen the patio by 2 ft]
4. Price effect
| Item | Qty / unit | Add (+) | Deduct (-) |
|---|---|---|---|
| [Labor] | [hrs] | [$] | [$] |
| [Materials] | [qty] | [$] | [$] |
| [Equipment / disposal] | [hrs / loads] | [$] | [$] |
| Net change to contract price | [+/- $0,000] | ||
Payment for this change: [e.g. due with the next progress payment / due at completion of the change].
5. Schedule effect
Working days added or removed: [+0 / -0]. Previous completion date: [date]. Revised completion date: [date]. Work on the change will start about [date].
6. Revised contract total
| Original contract price | [$] |
| Net of previous change orders | [+/- $] |
| This change order | [+/- $] |
| Revised contract total | [$] |
|---|
Pennsylvania contractors: read the notes under the form about the 3-business-day cancellation notice and the deposit cap before you put a dollar amount due at signing on a change order.
7. Approval
By signing, the owner and the contractor agree to this change, its price and its schedule effect. The work will not start until both have signed. [Insert any notice your state requires.]
How to use this change order form
Sign before you dig
The form works only if both signatures are on it before the extra work is done. Walk the owner through the description and the dollar figure on site, hand over a copy, and keep the original with the contract.
Price it like the original
Use the same labor and equipment rates as the base contract, add materials and disposal, and show the add and the deduct separately so the owner can see what changed. Our guide on how to estimate a paver patio shows a takeoff you can reuse for extras, and the paver calculator and retaining wall cost calculator help with quantities. If the owner is adding area or walls, ask for a revised plan; we draw plans for contractors under your logo.
Say what it does to the schedule
A price with no schedule line leaves a gap that turns into an argument at the end of the job. Even “no change to completion date” is worth writing down.
Tie it back to the contract
The change order should name the original contract and every earlier change order, so the revised total can be checked line by line. The landscape and hardscape proposal template says changes are made only by a signed change order, which is what this form is for.
Pennsylvania: what the Home Improvement Consumer Protection Act says about change orders
This section covers Pennsylvania’s Home Improvement Consumer Protection Act (HICPA), 73 P.S. § 517.1 et seq., which applies to home improvement work on a private residence when the total cash price of all work agreed upon is more than $500 (§ 517.2). Here is what the text confirms, and what it does not.
Confirmed in the Act
- Written and signed. Section 517.7(a)(7) requires the contract to include a description of the work, the materials and a set of specifications that “cannot be changed without a written change order signed by the owner and the contractor.”
- Dated, with the price change. Section 517.9(6) lists, among prohibited practices, deviating from or disregarding plans or specifications in any material respect without a written change order dated and signed by both the contractor and the owner that contains the price changes for each deviation. That is why this form has a date line, a price table and two signature lines.
- Time and materials jobs. Section 517.7(a)(8) allows a time and materials contract only with a written initial estimate, and the cost may not go over that estimate plus 10% without a written change order signed by the owner and the contractor.
- Three business days to cancel the contract. Section 517.7(b) lets a person who signs a home improvement contract rescind it without penalty within three business days of the date of signing, subject to the emergency exception in the Unfair Trade Practices and Consumer Protection Law.
- One-third deposit cap. Section 517.9(10)(i) says that on a home improvement contract with a total price of more than $5,000, a contractor may not receive a deposit of more than one-third of the home improvement contract price, or one-third plus the cost of special order materials designated in the written contract. Subparagraph (10)(ii) carves out certain home improvement retailers.
- No payment before signing. Section 517.9(9) prohibits demanding or receiving any payment for a home improvement before the home improvement contract is signed.
Not confirmed: ask your attorney
- Does a price-adding change order get its own 3-business-day cancellation notice? The Act’s rescission right is written for the “home improvement contract.” We could not confirm from the statute text whether a change order that adds money is treated as a new contract with its own cancellation window, or only as an amendment to the original. Ask your attorney before you decide.
- How does the one-third deposit cap work when a change order raises the price? The cap is measured against the “home improvement contract price” and applies to contracts over $5,000. The text does not say whether the revised total after change orders is the number that counts, or whether you may collect a deposit on the added amount. Ask your attorney.
The consequences of a miss can be serious: under Section 517.7(a), a contract that lacks the required terms is not valid or enforceable against the owner. For the deposit rules by state, see our Pennsylvania deposit limits and 3-day right to cancel guide and the deposit limits by state comparison. Payment disputes over extras also affect your lien rights: see Pennsylvania mechanics lien deadlines.
Disclaimer. This template and page are a starting point, not legal advice. Laws change and the Act has been the subject of bills. Have a Pennsylvania attorney review your final change order and contract forms before you use them.
Sources: Home Improvement Consumer Protection Act, Act 132 of 2008 as amended, 73 P.S. §§ 517.2, 517.7, 517.9: text of Act 132 at attorneygeneral.gov, and § 517.7 at FindLaw. Confirm the current text on palegis.us.
More free templates
This form is part of our free contractor templates. Also see the daily field log template for documenting the conditions behind a change, and the punch list template for closing out the job.
Questions
Does a change order have to be in writing?
In Pennsylvania, for home improvement work covered by the Home Improvement Consumer Protection Act, yes: the contract’s specifications cannot be changed without a written change order signed by the owner and the contractor (73 P.S. § 517.7(a)(7)). It is also good practice everywhere else.
What should a change order include?
The contract it changes, a description of the change in quantities, the reason, the price added or deducted, the schedule effect, the revised contract total, a date, and both signatures.
Can I start the extra work before the owner signs?
You can, but it is a bad idea. In Pennsylvania, deviating materially from the plans or specifications without a dated change order signed by both parties is listed as a prohibited practice (73 P.S. § 517.9(6)). Get the signature first.
Does a change order need its own 3-day cancellation notice in Pennsylvania?
We could not confirm this from the statute text. The Act gives the owner three business days to rescind the home improvement contract. Ask your attorney whether a price-adding change order should carry its own notice.
Does the one-third deposit cap apply to change orders?
The cap is one-third of the home improvement contract price on contracts over $5,000 (73 P.S. § 517.9(10)(i)). The text does not say how it applies to money added by a change order, so ask your attorney.