What Is a Sediment Basin? Storage, Spillway and PA DEP Dewatering Rules
A sediment basin is a pool built in an excavated or natural depression, or behind an embankment, so sediment can settle out of construction runoff before it leaves the site. EPA gives a typical drainage area of 5 to 100 acres and points smaller areas to sediment traps. Basins can be temporary or permanent, and a permanent design is a job for a qualified professional engineer.
Sediment basin and the terms around it
- Sediment basin: per EPA, a pool made by excavating, or by building an embankment across a low area or drainage swale. The embankment is compacted soil or rock.
- Sediment trap: the smaller version for areas under 5 acres. See sediment trap.
- Riser and barrel: EPA’s earthen principal spillway, a riser at the deepest point that discharges to a barrel through the embankment.
- Dewatering device: per EPA, a perforated pipe or floating skimmer on an earthen basin. See dewatering.
- PCSM: post-construction stormwater management. PA DEP’s FAQ discusses basins that convert to it. See PCSM.
Why it matters on a job
EPA says the purpose of a basin is to capture sediment before stormwater leaves a construction site, slowing runoff and reducing the sediment it carries. It reports sediment removal of 60 to 80 percent for properly designed basins, and says performance depends mainly on particle size and the ratio of basin surface area to inflow. Baffles, sediment-trap pretreatment and flocculants can improve results, according to the fact sheet.
EPA also attaches serious cautions. Earthen embankments are suitable only where dam failure would not cause substantial property damage or loss of life. A basin should not go in a permanent or intermittent stream. Piping, which is seepage that erodes the embankment, is named as a common failure cause.
Sizing and design figures from EPA
The EPA fact sheet on sediment basins and rock dams (EPA-832-F-21-028W, December 2021) gives these points:
- Storage guideline: 3,600 cubic feet per acre draining to the basin, with local jurisdictions setting the actual hydrologic requirements.
- Storage zones: dry storage below the riser height and wet storage above it.
- Side slopes: no steeper than 2H:1V inside and 3H:1V on the outlet side.
- Location: the lowest point of the site, reachable by maintenance crews.
- Riser: typically 1 foot below the dam crest, with a watertight riser-barrel connection.
- Outlet: for regulated sites of 1 acre or more, EPA says NPDES rules call for surface-withdrawing outlets unless that is infeasible.
- Rock dam: well-graded, erosion-resistant stone of at least 12 inches, fine gravel at least 1 foot thick on the basin side, a downstream rock apron at least as long as the dam is high, and filter fabric under the structure and apron.
Drainage area limits are 100 acres for an earthen basin and 50 acres for a rock dam. EPA states no detention time, no length-to-width ratio and no basin depth, other than the riser position. It gives no emergency spillway design, though it notes a rock dam may use its top as an overflow outlet.
Pennsylvania DEP points
The PA DEP erosion and sediment control FAQ is the Pennsylvania source used here. These items come from it:
- Spillway capacity (item 24): discharge at least 2 cfs per acre from the whole contributing watershed, or pass the 25-year, 24-hour peak flow. The principal spillway must carry at least the 10-year, 24-hour peak unless the 2 cfs per acre option is used. For a basin that converts to post-construction use, the emergency spillway should pass the 100-year, 24-hour peak for the final design drainage area.
- Dewatering time (item 22): 2 to 7 days, or 4 to 7 days in special protection watersheds.
- Forebay (item 20): should be 10 to 15 percent of total required storage volume, and its volume is subtracted from the basin’s required volume.
- Forebay or turbidity barrier (item 21): can replace the required surface area or length-to-width ratio without additional design.
- Bottom elevation (item 27): the bottom must sit above the seasonal high water table, shown by test pit logs. Soil borings and NRCS soil survey data are not acceptable substitutes.
- Reduced dewatering volume (item 26): no reductions in non-special protection areas discharging to waters impaired for siltation, suspended solids, turbidity or similar causes.
The FAQ states no drainage-area trigger for when a basin is required, and it states no cleanout rule. It does say an E&S plan is required when earth disturbance reaches 5,000 square feet, and that one acre or more generally needs an NPDES permit. See NPDES. Verify against the current source.
Inspection, cleanout and repair
- EPA says to clean out sediment when it exceeds 50 percent of storage volume.
- Inspect after each storm event for proper drainage and structural repair needs, including the dewatering device.
- Repair eroded earthen embankments immediately and replace displaced rock.
- Remove trash and debris from dewatering devices.
Common mistakes
- Building in a stream. EPA says not to install a basin in a permanent or intermittent stream.
- Ignoring failure consequences. EPA limits earthen embankments to places where failure would not cause substantial damage or loss of life.
- Loose riser-barrel connections. EPA names seepage piping as a common failure cause and lists tight connections, anchoring and compaction among the fixes.
- Bottom in the water table. PA DEP requires the bottom above the seasonal high water table.
- Letting sediment pass half the storage. EPA’s cleanout trigger is 50 percent.
What the sources do not say
EPA does not address basin removal or closeout. It gives no detention time, no basin depth and no length-to-width ratio. The PA DEP FAQ items cited here give no storage volume per acre, no cleanout rule, no baffle requirement and no numeric freeboard for basins. This page leaves those blank on purpose.
Sediment basin FAQ
How much area can a sediment basin serve?
EPA gives a typical range of 5 to 100 acres, with a maximum of 100 acres for earthen basins and 50 acres for rock dams. Under 5 acres, EPA points to sediment traps.
How much storage does a sediment basin need?
EPA’s typical guideline is 3,600 cubic feet per acre draining to the basin, and local rules set the actual requirement. The PA DEP FAQ items cited here do not give a per-acre volume.
How long should a basin take to drain in Pennsylvania?
PA DEP’s FAQ gives 2 to 7 days, and 4 to 7 days in special protection watersheds.
When is a sediment basin cleaned out?
EPA says to clean out sediment when it exceeds 50 percent of storage volume, and to inspect after each storm event.
Sources
- U.S. EPA, NPDES BMP Fact Sheet: Sediment Basins and Rock Dams (EPA-832-F-21-028W, December 2021). Federal source, not specific to Pennsylvania.
- Pennsylvania DEP, Erosion and Sediment Control FAQ
Verify thresholds and dimensions against the current source before you rely on them.
Keep reading
- Hardscape and Site Work Glossary
- Related terms: sediment trap, dewatering, PCSM, erosion and sediment control plan and NPDES