Dewatering: Removing Water From Excavations and Sediment Basins

Dewatering is the removal or control of water in an excavation, trench or basin so that work can go on safely and the water leaving the site does not carry sediment into a stream. The word has two common uses in site work. In an excavation it means pumping or diverting water out of the hole. In Pennsylvania erosion control it also describes how a sediment basin drains down after a storm.

Dewatering and the terms around it

  • Dewatering: removing water from a work area. OSHA’s excavation standard calls it water removal, and the PA DEP erosion manual uses the word for draining a sediment basin.
  • Accumulated water: OSHA’s term in 29 CFR 1926.651(h) for water standing or collecting in an excavation where employees would work.
  • Diversion: keeping surface water out of an excavation with ditches, dikes or other suitable means. See also drain outlet for where drainage water ends up.
  • Pumped water filter bag: a geotextile bag used to filter pumped water before it is discharged. See pumped water filter bag.
  • Competent person: the person OSHA requires to monitor water removal equipment. See competent person.

Why it matters on a job

Water causes two separate problems, and they are governed by two separate bodies of rules. The first is worker safety. A wet trench is a hazard to the people standing in it, and OSHA says so in plain terms. The second is water quality. Water pumped out of a muddy hole is not clean, and Pennsylvania’s erosion and sediment control program expects it to be treated before it reaches a stream or a storm sewer. A job can satisfy one set of rules and still fail the other, so a plan for water has to cover both.

It also connects to how a site is planned. A trench or excavation that is open for several days is exposed to more rain than one opened and closed in a day, and a written erosion and sediment control plan is where pumping and discharge points are normally laid out.

What OSHA says about water in excavations

According to OSHA’s text of 29 CFR 1926.651(h), water accumulation is handled in three steps:

  • (h)(1): employees may not work in excavations that contain accumulated water, or in excavations where water is accumulating, unless adequate precautions have been taken to protect them. The examples given are special support or shield systems, water removal, and a safety harness and lifeline. The rule sets no water-depth threshold.
  • (h)(2): if water removal equipment is used to control water, a competent person must monitor the equipment and operations to ensure proper operation.
  • (h)(3): if excavation work interrupts natural surface drainage, diversion ditches, dikes or other suitable means must be used to prevent surface water from entering the excavation and to provide adequate drainage of the area adjacent to the excavation. Excavations subject to runoff from heavy rains require an inspection by a competent person and compliance with (h)(1) and (h)(2).

Separately, 1926.651(k)(1) requires inspection after every rainstorm or other hazard-increasing occurrence, so a storm triggers both a water check and a general check of the hole.

What PA DEP says about pumped water

The Pennsylvania DEP Erosion and Sediment Pollution Control Program Manual (document 363-2134-008, effective April 15, 2000) notes on page 1 that sediment removal treatment for water pumped from excavations may be needed. Its Pumped Water Filter Bag practice, on pages 100 and 101, lists these limits:

  • Purpose: filter water pumped from disturbed areas, or from the sediment storage areas of sediment basins, before discharge to waters of the Commonwealth.
  • Pumping rate: no greater than 750 gallons per minute or one half of the manufacturer’s maximum rating, whichever is less. Pump intakes should be floating and screened.
  • Placement: in a well-vegetated area, discharging onto stable, erosion-resistant ground, and not on slopes greater than 5 percent.
  • Maintenance: replace bags when they become one half full, and inspect daily. If a problem is found, stop pumping and do not resume until it is corrected.

The manual also uses the word in a second sense. It says sediment basins must dewater in a period ranging from 2 to 7 days (page 40), and that a dewatering zone of 5,000 cubic feet is to be provided for each acre tributary to the basin (page 42). In that sense dewatering is a design feature of the basin, not a pumping job. The manual’s other related pages include a standard construction detail for a basin’s sediment storage dewatering facility. Our silt fence and NPDES entries cover other parts of the same program.

Reading a dewatering line in a proposal

If a proposal for excavation, a foundation or a drainage run says dewatering is included, a few clear questions follow from the sources above. Who monitors the pump, since OSHA assigns that to a competent person? Where will the water be discharged, and will it pass through a filter bag or another treatment? What is the plan if rain fills the hole overnight? None of these answers come from the glossary. They come from the contractor, the site plan and the permit conditions. If a project disturbs enough ground to need a permit, the conditions of that permit control.

This page does not set any numbers for groundwater pumping, well points or discharge permits. Those fall outside the sources cited, and a project that needs them calls for an engineer and the local DEP or conservation district office.

Dewatering FAQ

Can workers stay in an excavation that has water in it?

Under 29 CFR 1926.651(h)(1), not unless adequate precautions have been taken, such as special support or shield systems, water removal, or a safety harness and lifeline. The rule gives no water-depth threshold.

Who monitors the pump?

OSHA 1926.651(h)(2) says water removal equipment and operations must be monitored by a competent person to ensure proper operation.

Can pumped water go straight to a stream?

The PA DEP manual says sediment removal treatment for water pumped from excavations may be needed, and its pumped water filter bag practice is meant to filter such water before discharge to waters of the Commonwealth. Check the permit and plan for the site.

How long should a sediment basin take to dewater?

The PA DEP manual says sediment basins must dewater in a period ranging from 2 to 7 days. Verify against the current manual and the approved plan.

Sources

Descriptions here are summaries of the regulations and manual. Verify against the current source, which governs.