Soil amendment and restoration: how the PA BMP Manual describes it
Quick answer: In the Pennsylvania Stormwater Best Management Practices Manual (BMP 6.7.3), soil amendment and restoration means loosening compacted soil and mixing in compost so the ground can take in water again. The manual says to loosen subsoil to 20 inches where compaction is serious, do it only in dry soil, and not use the method on slopes over 30%. Stormwater credit is a flat 0.50 inch over the treated area.
What it is
The manual describes restoration as improving disturbed or low-organic soils by bringing back porosity and adding amendments such as compost, so the area can again infiltrate water and remove pollutants. It says subsoiling combined with an amendment is often more effective than either one alone, and compost helps the soil hold water. Ratings are low to medium for volume reduction and recharge, and medium for peak rate control and water quality. The listed removal values are 85% for total suspended solids, 85% for total phosphorus and 50% for nitrate.
How compaction happens
The manual blames animals, farm equipment, trucks, construction machinery, cars and foot traffic, and notes that wet soil compacts more easily than dry soil. It describes minor compaction as surface compaction within the top 8 to 12 inches, and major compaction as deep compaction. Axle loads over 10 tons can compact the root zone to about a foot, and loads over 20 tons can compact to about 2 feet. Trouble starts when air space falls to 10 to 15% of the soil volume. Higher bulk density means less infiltration and more runoff. The manual says the best restoration of all is full revegetation of woodland. For prevention rather than repair, see minimizing soil compaction.
Bulk density table
The manual reproduces a USDA-NRCS bulk density table (grams per cubic centimeter). It lists an ideal value, a value that may affect root growth, and a value that restricts root growth.
| Soil texture | Ideal | May affect roots | Restricts roots |
|---|---|---|---|
| Sands, loamy sands | under 1.60 | 1.69 | 1.8 |
| Sandy loams, loams | under 1.40 | 1.63 | 1.8 |
| Silt, silt loams | under 1.30 | 1.6 | 1.75 |
| Clays (over 45% clay) | under 1.10 | 1.39 | 1.47 |
The manual’s full table has more texture rows. Credit is given for soil amended under the manual or soil that meets the ideal values.
Compost amendment: design numbers
- Minor compaction: add 6 inches of compost and till up to 8 inches.
- Major compaction: add 10 inches of compost and till up to 20 inches.
- Ratio: the design list gives a compost rate of 2:1 soil to compost.
- Slopes: do not use on slopes greater than 30%; use deep-rooted vegetation there.
- Tree drip lines: do not restore within them.
- Reuse: on-site soil with at least 5% organic content can be stockpiled and reused.
Subsoiling and ripping rules
Subsoiling works only on dry soil. The manual calls for a solid-shank ripper to 20 inches, or 8 inches for minor compaction, done after excavation and before compost goes down. Disk and chisel plows are too shallow and are not acceptable. Do not subsoil within a tree drip line, over utilities within 30 inches of the surface, where trenches or drainage lines go, or where compaction is intentional, as under footings. The informational specification asks for soil loosened to less than 1,400 kPa (200 psi) to 20 inches, worked in a two-way grid with spacing from 12 to 36 inches, and a pause if soil holds a ball when squeezed. It allows one pass only on erodible slopes steeper than 1 vertical to 3 horizontal and sets a 20-foot setback at the exceptions.
Installation in the specification
- Finish and stabilize all construction first.
- Rip or loosen the subsoil, remove rocks.
- Spread 2 to 3 inches of approved compost, till to 6 inches with a rotary tiller, then add 4 more inches to reach grade.
- After seeding or planting, add a 2 to 3 inch compost blanket where grass or plants do not protect the surface.
Compost should come from a producer meeting state and federal rules on contaminants and pathogens, and very coarse compost is to be avoided. The manual recommends Seal of Testing certification.
The stormwater credit
Volume credit is the amended area in square feet times 0.50 inch times 1/12, giving cubic feet. The manual gives no derivation for the 0.50 inch. Tilling, including scarifying subsoil, is listed at $800 to $1,000 per acre and compost amending at $860 to $1,000 per acre, with no cost year stated, so treat both as dated.
Maintenance
Restoration may need repeating where use or settling re-compacts the ground. The manual points to playfields and parks as examples. It also suggests low irrigation rates, limited mowing for more evapotranspiration, and deep-rooted perennials where compaction is mild, though that takes several years.
Where the manual conflicts
- Compost depth: the design list says 6 inches for minor compaction, while the specification says 2 to 3 inches plus 4 inches.
- Tilling depth: up to 8 inches in the design list, 6 inches on the tiller in the specification.
- The 2:1 ratio: it does not say whether this is by volume or weight, and it does not line up with the depths.
- Slope limits: 30% in the design list and 1 to 3 in the specification serve different purposes.
- Silt loam density: two table rows give different ideal values for similar silt loams.
Pennsylvania approvals and who designs it
A homeowner can till and amend a lawn, but using restoration for stormwater credit means a designer writes project-specific specifications, as the manual itself says. Municipal review and Chapter 102 rules may apply. Restoration also repairs compaction at the bottom of a dry detention basin or rain garden.
Sources
- Pennsylvania Department of Environmental Protection, Pennsylvania Stormwater Best Management Practices Manual (363-0300-002, December 30, 2006), BMP 6.7.3 Soil Amendment and Restoration, read from a municipal copy hosted at indianlakepa.gov. Checked Nov. 23, 2026.
Related
All drainage guides · Minimize disturbed area · Riparian forest buffer · Soil infiltration rate
FAQ
How deep should compacted soil be loosened?
The manual calls for a solid-shank ripper to 20 inches, or 8 inches for minor compaction, and only when the soil is dry.
How much compost does the manual call for?
The design list says 6 inches of compost tilled up to 8 inches for minor compaction and 10 inches tilled up to 20 inches for major compaction, but the specification gives a different 2 to 3 inches plus 4 inches.
Where should soil restoration not be done?
Not on slopes over 30%, not within a tree drip line, and not where utilities lie within 30 inches of the surface.
How much stormwater credit does amended soil earn?
The volume formula is amended area in square feet times 0.50 inch times 1/12, giving cubic feet.
Planning information only. Design must be done by a qualified professional and approved by your municipality and, where required, DEP. Source checked Nov. 23, 2026.