Vegetated Swale: What the PA Stormwater BMP Manual Says (BMP 6.4.8)

Home / Drainage guides / Vegetated swale

Vegetated swale: how the PA BMP Manual describes it

Quick answer: BMP 6.4.8 in the Pennsylvania Stormwater Best Management Practices Manual describes a vegetated swale as a broad, shallow channel covered in dense, mixed vegetation that slows runoff, filters sediment and may infiltrate some of the volume from nearby impervious surfaces. The manual lists side slopes of 3:1 to 5:1, a bottom width of 2 to 8 feet, and a 10-year storm conveyance with at least 6 inches of freeboard.

The figures below come from the manual chapter (Pennsylvania Department of Environmental Protection, December 30, 2006). Verify against the current source before relying on any number.

What it is

The manual calls the swale a trapezoidal or parabolic channel. Pollutants are removed through vegetative filtering on the side slopes and bottom, filtering through the subsoil, and infiltration. It presents swales as a more environmentally sound alternative to curb-and-gutter conveyance, and says they also pretreat runoff for downstream practices. Check dams can be added on steeper slopes. For the short definition, see the glossary entry on a vegetated swale. For a homeowner-scale build guide, see how to build a drainage swale.

Where the manual lists it

Listed applications are parking areas, commercial and light industrial sites, roads and highways, residential developments, pretreatment for volume-based practices, and alternatives to curb, gutter and storm sewer.

Ratings in the manual

FunctionRating
Volume reductionLow/Medium
RechargeLow/Medium
Peak rate controlMedium/High
Water qualityMedium/High
Total suspended solidsAbout 50%
Total phosphorusAbout 50%
NitrateAbout 20%

Key design elements

  • Plant dense, low-growing, water-resistant native vegetation that tolerates drought and salt.
  • Longitudinal slope of 1% to 6% in the key elements list.
  • Side slopes of 3:1 to 5:1.
  • Bottom width of 2 to 8 feet, with wider bottoms possible when berms or walls prevent braiding.
  • Convey the 10-year storm with at least 6 inches of freeboard and without erosive velocities.
  • Check dams give limited detention and can enhance infiltration, but erosion around the dam must be prevented.

Variations

  • Swale with infiltration trench: adds a 12 to 24 inch aggregate bed or trench wrapped in nonwoven geotextile, which improves volume control and water quality but raises cost. Trench storage can count toward the 1-inch storm storage requirement.
  • Grass swale: essentially a conventional drainage ditch with milder slopes. It is cheaper but gives less infiltration and pollutant removal, and the manual says to use it only as pretreatment for other structural practices.
  • Wet swale: a linear wetland cell with shallow permanent pools. It needs a high water table or poorly drained soils, may breed mosquitoes, and provides minimal infiltration when water stands for long periods.

See our infiltration trench guide for the trench element.

Design considerations

Sizing and ponding

The manual says to store and infiltrate the 1-inch storm and convey up to the 10-year storm with freeboard and without erosion. Maximum ponding depth is 18 inches at the channel end, with a 12-inch average. Residence time of 5 to 9 minutes is acceptable without check dams. Maximum ponding time is 48 hours, with about 24 hours preferred and a 30-minute minimum. Filtering is greatest at depths below 6 inches, and vegetation should not be submerged.

Check dams

Check dams are recommended above a 3% slope, at 6 to 12 inches high and regularly spaced. Materials include natural wood, concrete, stone and earth, though earthen dams are generally not recommended because they erode. Pools behind dams must drain within 72 hours. For stone dams the manual suggests a larger stone, such as R-4, on the downstream face and a smaller stone, such as AASHTO #57, upstream. See the glossary entry on a check dam.

Siting and drainage area

Use natural low points where suitable and avoid very flat or steep areas and sharp bends. Development above about four units per acre may make swales impractical because driveway culverts become excessive. Swales work best for 1 to 2 acres and can handle 5 to 10 acres; areas over 10 acres get less treatment unless special measures are added. Curb cuts should be at least 12 inches wide, with a 2 to 3 inch drop at the pavement edge. Oversizing driveway culverts reduces snow clogging; see culverts under driveways.

Soils and pretreatment

The manual calls for at least 24 inches of permeable soil, with media that infiltrates at least 0.5 inch per hour. Aggregate beneath the soil can be 12 to 24 inches. Unsuitable soils, such as clayey, rocky or coarse sand, may have about 12 inches replaced. Pretreatment options include vegetated filter strips, sediment forebays, pea gravel diaphragms and plunge pools. A level spreader is a related inflow device, though the manual does not list it for swales.

Stability

The manual refers to the Pennsylvania Erosion and Sediment Pollution Control Program Manual for stability checks. Velocities above 5 feet per second are allowed only with good cover and maintenance.

Construction sequence

  1. Install upgradient temporary erosion and sediment controls first, and build and stabilize the swale early, before mass grading and paving.
  2. Rough-grade with minimal compaction, operating equipment from the side and not the bottom.
  3. Build check dams if required, then fine-grade carefully.
  4. Seed or plant and install the protective lining, with temporary irrigation if dry.
  5. Once contributing areas are stabilized, remove temporary controls. Do not route upland runoff into the swale until stabilized.

Maintenance

As needed, repair side-slope erosion and rills, mow and trim, remove litter before mowing, and inspect inlets and outlets. Annually and within 48 hours after major storms, address erosion, damaged vegetation and sediment or debris over 3 inches deep, and rototill and replant if drawdown exceeds 48 hours. In winter, remove sand and residue after spring melt and use salt-tolerant vegetation. Simpler swales can be handled by homeowners, while complex ones with check dams may need an agency and a legally binding maintenance agreement.

Costs (undated)

For a 15-foot top width, the manual lists seeded swale construction at $4.50 to $8.50 per linear foot and sodded swale at $15 to $20, with annual maintenance about $0.75 per linear foot and a lifetime of about 50 years. The costs are estimates for design only and exclude clearing, grubbing, leveling, filling and sodding. They are old figures, not current prices.

Where the manual text conflicts or is unclear

  • Slope: the key elements say 1% to 6%, while the design considerations recommend 1% to 3% and call for check dams above 3%.
  • Not stated in the manual: depth to seasonal high water table for standard swales, setbacks from buildings or wells, and a specific mowing height.

Pennsylvania approvals and who designs it

This page does not say who must approve a swale. If it is part of a permitted site, the plan contents and review are covered in our PCSM plan contents page.

Sources

  • Pennsylvania Department of Environmental Protection, Pennsylvania Stormwater Best Management Practices Manual (363-0300-002, December 30, 2006), BMP 6.4.8 Vegetated Swale. Checked Nov 23, 2026.

Related

All drainage guides · Vegetated filter strip · Infiltration trench · Rain garden

Get a quote

FAQ

What side slopes does the manual list for a vegetated swale?

3:1 to 5:1.

When are check dams recommended?

The manual recommends check dams above a 3% slope, 6 to 12 inches high, with pools draining within 72 hours.

How long can water pond in a swale?

Maximum ponding time is 48 hours, with about 24 hours preferred and a 30-minute minimum.

What drainage area suits a swale?

The manual says swales work best for 1 to 2 acres and can handle 5 to 10 acres.

Planning information only. Design must be done by a qualified professional and approved by your municipality and, where required, DEP. Source checked Nov 23, 2026; verify against the current source.