Home / Drainage guides / Infiltration basin

Infiltration basin: what the PA BMP Manual requires

Quick answer: In the Pennsylvania Stormwater BMP Manual, an infiltration basin is a shallow, vegetated, impounded area that stores runoff and lets it soak in. The manual calls for 2 feet of separation to bedrock and the seasonal high water table, a maximum 5:1 impervious-to-infiltration ratio, and a positive overflow.

What it is

The Pennsylvania Stormwater Best Management Practices Manual (BMP 6.4.2) describes an infiltration basin as a shallow impounded area that temporarily stores runoff and lets it soak in. Size and shape can vary from one large basin to several smaller ones. It relies on the existing soil mantle, so the key is enough surface area to absorb the runoff volume, plus an engineered overflow for larger storms. The manual says infiltration and evapotranspiration reduce volume, and that soil and vegetation improve runoff quality.

Key design elements from the manual

  • At least 2 feet of separation to bedrock and to the seasonally high water table.
  • A maximum 5:1 ratio of impervious area to infiltration area.
  • Uncompacted, natural soils with acceptable infiltration capacity.
  • A design to hold or infiltrate the volume difference from a 2-year storm or a 1.5-inch storm.
  • A positive overflow through an engineered outlet structure.
  • No construction on fill placed less than 5 years ago.

Site and layout rules

ItemWhat the manual says
Bottom slopeLevel, or no steeper than 1%
Berm side slopesNo steeper than 3:1 (horizontal to vertical)
Berm top widthAt least 2 feet
FreeboardAt least 1 foot above the 100-year water surface elevation
Poor-infiltration soilsAdd a 6-inch sand or gravel layer on the bottom, or amend the soil
FertilizerAvoid

Soil investigation and infiltration testing are required, and the design must follow the manual’s Infiltration Systems Guidelines for water table depth, setbacks and loading rates. The manual rates the basin High for volume reduction, recharge and water quality, and Medium to High for peak rate control. It lists removal of 85% for total suspended solids, 85% for total phosphorus and 30% for nitrate.

Plants and surface

The manual recommends planting, from a meadow mix to woodland species, with native plants preferred because longer roots increase permeability. Turf grass is discouraged because frequent mowing compacts soil. Informal recreation is acceptable in dry periods, but vehicles and heavy machinery should stay off the basin. Where lawn is being retrofitted and the existing soil has enough infiltration capacity, a berm can enclose the area without excavation.

How infiltration volume is figured

Infiltration volume equals bottom area times the design infiltration rate (inches per hour) times the infiltration period (hours) times 1/12. For this practice the manual sets the infiltration period at 2 hours or the time of concentration, whichever is larger. A backup underdrain or low-flow orifice may be considered if the basin does not drain within the manual’s criteria, with the valve kept shut unless drainage is needed.

Construction sequence in brief

  1. Protect the basin area from compaction before work starts, and install late in the construction schedule if possible.
  2. Install and maintain erosion and sediment controls, and keep sediment-laden water out of inlets and pipes.
  3. Excavate only as needed to an uncompacted subgrade free of rock and debris.
  4. Install the outlet control structures.
  5. Seed and stabilize, using native plantings where appropriate, and keep inlet protection until the site is fully stabilized.

Maintenance

The manual says to clean catch basins and inlets upgradient of the basin at least twice a year and after runoff events. Inspect after storms: water should drain within 72 hours, which also limits mosquito breeding. Look for sediment buildup, outlet damage, erosion, spills and berm slope stability. Revegetate bare spots quickly, and remove sediment as needed to restore the original cross-section and infiltration rate.

Where the manual is inconsistent or silent

  • Missing numbers: the section gives no drainage area limit, no maximum ponding depth, no berm height and no drawdown time in its design criteria. The 72-hour figure appears only in the maintenance text, and the only separation figure is the 2 feet to bedrock and water table.
  • Infiltration period: the basin uses 2 hours or the time of concentration, while the pervious pavement section caps its infiltration period at 72 hours. The manual does not reconcile the two.
  • Cross-references: the basin text cites a BMP 6.3.3 for overflows and berms that does not exist in Section 6.3, and cites soil amendment under a different number than the table of contents does.
  • Cost: costs are 2005 figures. The manual lists meadow mix planting at $2,500 to $3,500 per acre and says other costs vary widely.

Pennsylvania approvals and who designs it

A basin sized for stormwater control is an engineered facility. It needs a qualified professional for soil testing, sizing, berm and outlet design, and it may need approval from your municipality, the county conservation district or DEP. Check whether an erosion and sediment plan or NPDES permit applies (see Chapter 102 and NPDES overview). Our soil guides on percolation testing and infiltration rate explain the testing side.

Sources

  • Pennsylvania Department of Environmental Protection, Pennsylvania Stormwater Best Management Practices Manual (363-0300-002, December 30, 2006), BMP 6.4.2 Infiltration Basin, via the PA DEP eLibrary (greenport.pa.gov). Checked Nov 23, 2026.

Related

All drainage guides · Infiltration trench · Build a rain garden · Positive overflow

Get a quote

FAQ

What is the maximum impervious-to-infiltration area ratio for a PA infiltration basin?

The PA BMP Manual lists a maximum 5:1 ratio of impervious area to infiltration area.

How far above bedrock and the water table must the basin bottom be?

The manual lists a minimum of 2 feet of separation to bedrock and to the seasonally high water table.

Should an infiltration basin be planted in turf?

The manual discourages turf grass because frequent mowing compacts soil, and recommends meadow mix to woodland plantings, with native plants preferred.

How fast should the basin drain?

The manual’s maintenance section says water should drain within 72 hours, which also limits mosquito breeding. Its design criteria do not state a separate drawdown time.

Planning information only. Design must be done by a qualified professional and approved by your municipality and, where required, DEP. Source checked Nov 23, 2026.