Pennsylvania Act 167 stormwater plans: what counties and towns must do

Quick answer: Act 167 of 1978 requires each Pennsylvania county to adopt a watershed stormwater management plan, and requires municipalities to adopt ordinances consistent with it. Plans must be reviewed at least every five years, and DEP and DCED have 90 calendar days to act on one.

What Act 167 is

The Pennsylvania Storm Water Management Act, Act 167 of 1978, was passed in response to faster runoff from land development. DEP’s Act 167 FAQ says the law has three goals. It encourages stormwater planning and management that fits sound water and land use practices. It authorizes a comprehensive program to preserve and restore the flood-carrying capacity of streams, keep natural runoff patterns to the maximum extent practicable, and protect groundwater and recharge areas. And it encourages local administration, consistent with the Commonwealth’s duty as trustee and citizens’ constitutional right to environmental values.

Who does what

PartyRole under Act 167, per DEP
CountyPrepares and adopts a watershed stormwater management plan for each watershed in the county, or for the county as a whole
MunicipalityAdopts and implements ordinances that regulate land development consistently with the county plan
DEPReviews and approves plans, in consultation with the Department of Community and Economic Development
County conservation districtHas a seat on the watershed plan advisory committee

DEP’s Act 167 page adds that counties prepare plans in consultation with the municipalities in each watershed, and that DEP designates the watersheds. The FAQ says many designated watersheds are at the HUC-10 scale, though counties may use smaller HUC-12 watersheds, and a county with several watersheds is encouraged to consider one countywide plan so every municipality adopts the same ordinance.

What a county plan must contain

At a minimum a plan must meet Section 5 of the Act and include provisions reasonably necessary so that development in one municipality does not harm health, safety and property in other municipalities in the watershed. DEP lists these components, noting the list may not be exhaustive:

  • A survey of existing runoff characteristics in small and large storms, including the effects of soils, slopes, vegetation and existing development.
  • A survey of significant obstructions and their capacities.
  • An assessment of projected and alternative land development patterns and their effect on runoff quantity, velocity and quality.
  • An analysis of present and projected development in flood hazard areas.
  • A survey of existing drainage problems and proposed solutions.
  • A review of existing and proposed stormwater collection systems.
  • An assessment of alternative runoff control techniques.
  • An identification of existing and proposed flood control projects.
  • A designation of areas to be served by stormwater collection and control facilities within a 10-year period, with design capacity, costs and a schedule.
  • An identification of floodplains in the watershed.
  • Criteria and standards for controlling runoff from existing and new development.
  • Implementation priorities.
  • Provisions for periodic review, revision and updating.

Two phases: scope of study, then the plan

Plan development has two phases. In Phase 1 the county prepares a scope of study and submits it to DEP for approval. The requirements are in 25 Pa. Code 111.14 and include the level of effort and cost for Phase 2. DEP lists six items for the scope: a description of each major task under Section 5, a time schedule, the level of effort and personnel, a cost estimate for each task, a narrative justifying any consultant services, and a list of outside funding sources. Phase 2 is the detailed plan, prepared or updated based on the approved level of effort.

Advisory committee, hearing and DEP review

Section 6 of the Act requires a watershed plan advisory committee that the county forms at the start of planning. It must include at least one representative from each municipality in the watershed and one from the county conservation district. Before adoption, each municipality, the county planning commission and regional planning agencies review the draft for consistency with other planning, and the county holds a public hearing, adopts the plan and submits it to DEP. The FAQ notes the hearing and adoption are required by the Act but are not required before the plan goes to DEP, although DEP strongly encourages holding the hearing first.

DEP and DCED approve a plan when it is consistent with municipal floodplain management plans, state programs regulating dams, encroachments and water obstructions, and state and federal flood control programs, and when it is compatible with other watershed plans in the basin. They have 90 calendar days to approve or disapprove, and a plan with no action in 90 calendar days is deemed approved.

After approval: ordinances within six months

The FAQ says a county should tell its municipalities they must amend local ordinances to be consistent with the plan within six months of plan adoption or DEP approval, whichever is later, and that DEP must take enforcement action against municipalities that do not. It also says that once a plan is approved and adopted, anyone engaged in land development must implement stormwater measures consistent with the plan and the Act. Municipalities must adopt or amend zoning, subdivision and land development, building code, and erosion and sedimentation control ordinances consistent with the plan. DEP’s page adds that stormwater systems, subdivisions and major land developments, highways and public utilities owned or financed in whole or part by the Commonwealth must be consistent with the plan.

Five-year updates and what makes a plan current

Plans must be reviewed and revised at least every five years, using the same two-step process. DEP treats a plan as current if it was developed or updated within the last five years. The FAQ explains that DEP funding for plan development ended in 2009 but that recent state budgets have appropriated money through the Clean Streams Fund, so the status of a given county’s plan varies. DEP publishes a statewide map and an approval-date list of plans on its Act 167 page.

How a current plan connects to construction stormwater permits

For a project that needs a construction stormwater permit, the FAQ says standards in an Act 167 plan, including consistent ordinances, may be used for the stormwater analysis required by 25 Pa. Code 102.8(g) for a post-construction stormwater management plan, if DEP has approved the plan and it is current. If the plan is not current, its standards may be proposed as an alternative design standard, and the applicant must show they give equal or better protection than the Chapter 102 standards. See our pages on Chapter 102 and the NPDES construction stormwater permit.

Money for counties and municipalities

Under Section 17 of the Act, DEP may award grants of up to 75 percent of allowable costs for preparing or updating a plan and for county or municipal administration, enforcement and implementation, when the General Assembly appropriates funds. DEP’s page says recent budgets included about $2 million a year, and that a municipality’s reimbursement for adopting ordinances from a current plan is capped at $9,999, subject to available funds. Only municipalities that adopted an ordinance consistent with the model ordinance in a current approved plan qualify.

What Act 167 does not do

The FAQ states plainly that Act 167 does not regulate land use. Municipalities control land use through zoning and subdivision and land development ordinances. It also says the Act has no explicit pollutant load reduction requirement, although the plan must set criteria and standards for controlling runoff and assess runoff quality. Act 15 of 2018 amended Act 167 on high tunnels, and DEP says municipalities should talk to their own legal counsel about their ordinances.

Where to check for a specific property

The plan and its model ordinance are local documents. DEP says other plans are available from the local county planning commission, and its page lists regional office contacts and a bureau email for general questions. For a real job, ask the municipality which stormwater ordinance applies and whether it was adopted from a county plan, and ask the county conservation district about erosion and sediment control and permit triggers.

Sources

Sources checked Nov 23, 2026.

Related

Chapter 102 erosion and sediment control · NPDES construction stormwater permit · Floodplain development basics · All PA site work regulations

Talk to us about your project

FAQ

What is Act 167?

It is the Pennsylvania Storm Water Management Act of 1978. It requires counties to prepare watershed stormwater plans and municipalities to adopt consistent ordinances, according to DEP.

How often must an Act 167 plan be updated?

DEP says plans must be reviewed and revised at least every five years, and a plan counts as current if it was developed or updated within the last five years.

How long do municipalities have to adopt ordinances?

DEP’s FAQ says municipalities must amend local ordinances to be consistent with the plan within six months of plan adoption or DEP approval, whichever is later.

Does Act 167 regulate land use?

No. DEP’s FAQ says municipalities control land use through zoning and subdivision and land development ordinances.

General information only, not legal advice. Your county conservation district, DEP and your municipality decide what applies to a specific project. Source pages checked Nov 23, 2026.