Topsoil Stripping

Topsoil stripping is removing the surface layer of soil from an area before grading or building, so the topsoil can be stockpiled and put back later.

What the rules say

Pennsylvania’s Chapter 102 does not define topsoil stripping. Its definition of earth disturbance does include moving or stockpiling soil or rock, so stripping and stockpiling count as earth disturbance toward the 5,000 square foot and 1 acre thresholds. DEP’s E&S FAQ says permanent stabilization requires topsoil to be restored, replaced or amended, and that designers should specify the topsoil to be used, which may mean importing it. The FAQ and DEP’s single-family fact sheet do not cover how deep to strip or how to stockpile, so we do not quote a depth.

Why replacing it matters

Penn State Extension’s guidance on soil compaction (written for natural gas sites) says topsoil compaction can last from about one year on sandy soils to five years on clay soils, while deep subsoil compaction is virtually permanent on all soil types. It recommends deep subsoiling before topsoil goes back, to the depth of the compaction. Compacted subsoil slows water movement, which means longer saturated periods and more runoff.

In the field

When topsoil is stripped, the stockpile and the stripped area both need erosion controls such as a silt fence. Stripped material that is not reused becomes spoil. After work, DEP says pervious areas need a minimum uniform 70% perennial vegetative cover, or another acceptable BMP, for permanent stabilization. See also compaction and subgrade.

What is left when the topsoil is gone

A Penn State Extension article on planting in construction-damaged soils says that in most developments the organic A horizon is removed, often leaving compacted, mostly clay soil. After stripping, only the clay B horizon may remain, and when compacted it forms a barrier to water, air and root growth. The article says most root growth is restricted at a penetration resistance of 300 pounds per square inch, and it treats the top 3 to 10 inches of soil as presumed fertile. It describes a desirable topsoil as about 45% mineral material, 50% pore space and 5% organic material.

Putting soil back without creating layers

The same article warns that where one soil type is dumped on another, the transition zone is often an impermeable barrier to water, air and roots, so replacement soil and amendments must be mixed in with the original soil at the bottom and sides. It says working soil that is too wet increases compaction, and that soil which smears or shows visible water in its pores is too wet. For poor soils it recommends replacing them with high-quality topsoil and testing texture, fertility and pH through the county extension office. On the compaction side, the other Penn State article says to find the depth of the compacted layer with a penetrometer or a test pit, fracture only to that depth, and subsoil in summer or fall at optimal moisture, with its effects staying temporary unless roots and soil organisms move into the new pore space.

Chapter 102 itself lists minimizing soil compaction among its general planning goals for post-construction stormwater plans, to the extent practicable. That goal is one reason to keep equipment off soil that will be replanted.

Frequently asked questions

Does Pennsylvania require topsoil to be saved?

The DEP documents we reviewed do not require saving it as such, but they require topsoil to be restored, replaced or amended for permanent stabilization.

How deep is topsoil?

It varies by site. A soil survey or soil test for your lot gives the real depth, and none of the rules we reviewed set one.

What does 70% cover mean?

DEP’s FAQ describes it as a minimum uniform 70% perennial vegetative cover on pervious areas, or an acceptable BMP, once work is complete.