We dig the trench, set the bedding and backfill in compacted lifts. Pipe, conduit and structures are installed by whichever trade the plans assign. We price pipe laying only when the plans put it in our scope.
Call (570) 397-9800How we bidWhat a trench bid covers
| Item | What we price |
|---|---|
| Locate and layout | PA One Call (811) before every dig, then trench layout from the plans |
| Trenching | Excavation to the invert depth and width the plans specify |
| Bedding | Specified stone or sand bedding and pipe zone material |
| Backfill and compaction | Placed in lifts and compacted, with surface restoration as drawn |
Trench depth drives the cost and the safety plan. Deep trenches need shoring or sloping under OSHA excavation rules, and we price the method the plans or the competent person call for. Dewatering and rock are carried as allowances or unit prices.
What we need to price it
- Profiles with inverts and lengths
- Crossings and existing utilities
- Bedding and backfill spec
- Who supplies pipe and structures
- Road or lawn restoration limits
- Permit and inspection holds
General background: what OSHA says about trenches
This section is general education from public sources. It is not a statement about a specific project.
OSHA calls trench collapse, or cave-in, the greatest risk to workers’ lives in trenching. Its prevention methods are to slope or bench the trench walls, shore them with supports, or shield workers with trench boxes. Under 29 CFR 1926.652, protection is required unless the trench is in stable rock or is less than 5 feet deep with a competent person finding no potential for a cave-in. The designer of a sloping or support system is the employer or its designee, and systems outside the listed options must be approved by a registered professional engineer.
Day-to-day rules matter for pricing. Trenches 4 feet or more deep need a stairway, ladder, ramp or other safe exit, with no more than 25 feet of lateral travel to reach it. A competent person must inspect daily, before work starts, and after every rainstorm or other hazard-increasing event. Excavated material and equipment must stay at least 2 feet from the edge. Workers may not stay in a trench with accumulating water unless precautions are in place, and a competent person must monitor any water removal equipment (29 CFR 1926.651).
General background: finding utilities before the bucket goes in
OSHA requires estimated utility locations to be determined before digging, with utility owners contacted in advance to mark exact locations. If they cannot respond within 24 hours, unless state or local law requires longer, or cannot pinpoint the lines, work may proceed cautiously using detection equipment or other acceptable means. As digging nears an estimated location, the exact location must be found by safe means. In Pennsylvania, the Public Utility Commission says contractors must call 811 at least three business days before starting any excavation, and PA One Call then notifies the facility owners so they can mark their buried lines.
General background: unit prices and allowances for the unknowns
AIA’s contract guidance describes unit prices as the cost per unit of a particular item of work, usually per square foot, linear foot, cubic yard or piece, so that payment follows the quantity actually installed. Trench length, rock and extra bedding are the kind of quantities that can move.
Sources: OSHA Trenching and Excavation page; OSHA 29 CFR 1926.651 and 1926.652 (osha.gov); Pennsylvania Public Utility Commission, PA One Call page (puc.pa.gov); AIA Contracts, “What are unit price items in construction contracts” (learn.aiacontracts.com). Checked Nov 23, 2026. General information, not engineering or legal advice.
Questions
Do you call 811 before digging?
Yes. We call Pennsylvania One Call before every dig.
Do you install the pipe?
Only when the plans put pipe in our scope. Otherwise we trench, bed and backfill for the trade that installs it.
How deep can a trench be before OSHA requires protection?
Protection from cave-ins is required unless the trench is in stable rock or is less than 5 feet deep and a competent person finds no potential for a cave-in.