Home / Commercial / How we bid
For general contractors
How we bid: unit prices and alternates
We price only our own trades, from your drawings, specs and every addendum. The proposal states what is included, what is excluded, and how the unknowns are handled, so your bid leveling is quick.
Call (570) 397-9800Cover letter templateHow a proposal is built
| Part | How we handle it |
|---|---|
| Base bid | Lump sum by scope, for the work the drawings and specs show |
| Unit prices | For quantities that can move, such as rock, undercut of soft subgrade, extra stone or extra concrete |
| Alternates | Priced separately and listed by number, so you can add or deduct without re-bidding |
| Allowances | Stated as an amount and what it covers, such as winter protection or dewatering |
| Exclusions | Listed plainly: other trades’ work, testing, permits, bonds unless priced, and anything not on the drawings |
| Addenda | We list the addenda we priced by number so there is no doubt which set we bid |
Time-and-material work is available at stated rates for changes. Prevailing wage work is priced from the wage determination. See prevailing wage in PA.
Terms we state in the proposal
We ask for payment within 14 days. We state our terms up front rather than after award.
Written change orders, priced before the work is done wherever the schedule allows.
Small stand-alone scopes far from Lock Haven are only practical when bundled with a larger package that covers the travel.
General background: what a unit price is
This section is general education from public sources. It describes how construction contracts and Pennsylvania law work in general. It is separate from the terms we state above.
AIA’s contract guidance defines unit prices as the cost per unit of a particular item included in the contractor’s work, usually stated per square foot, linear foot, cubic yard or piece. They fit work where the final quantity is not known at contracting, so the contractor measures the actual quantities and multiplies them by the unit price, and payment follows the real quantities even when they differ from the estimate. If scope or quantities change through change orders, the contract is adjusted using the unit prices already stated in it. Under A201-2017 Section 9.1.2, unit prices may be equitably adjusted when material changes in quantity cause substantial inequity, and the parties may agree on a percentage variation that defines a material change. AIA describes unit prices as a way to manage changes and reduce disputes.
General background: Pennsylvania prompt payment (CASPA)
Pennsylvania’s Contractor and Subcontractor Payment Act sets timing between the parties on a project. Under section 7(c) (73 P.S. § 507), per FindLaw, a contractor must pay a subcontractor within 14 days after receiving each progress or final payment, or 14 days after receiving the subcontractor’s invoice, whichever is later. Under subsection (b), if a contractor or subcontractor does not accurately disclose the owner’s due date before a subcontract is signed, it must pay as though the owner’s due dates were met. For retainage, interest accrues from the date the retainage was due and owing, which FindLaw says is generally 30 days after final acceptance of the work (73 P.S. § 509). FindLaw notes its posted code may not reflect the latest version, so confirm current law with an attorney.
General background: bonds as an exclusion or a line item
Because bonds can be excluded unless priced, it helps to know when they are mandatory. Under Pennsylvania’s Public Works Contractors’ Bond Law (8 P.S. § 193.1), per FindLaw, public construction contracts exceeding $10,000 require performance and payment bonds, each at 100 percent of the contract amount.
Sources: AIA Contracts, “What are unit price items in construction contracts” (learn.aiacontracts.com); FindLaw, 73 P.S. §§ 507 and 509 and 8 P.S. § 193.1 (codes.findlaw.com). Checked Nov 23, 2026. General information, not legal advice.
Questions
Do you bid lump sum or unit price?
Both. A lump sum for the defined scope, and unit prices for the quantities that can change.
Will you price alternates?
Yes. Alternates are priced separately and numbered so you can add or deduct them.
How do I get you on a bid list?
Call (570) 397-9800. We also accept invitations through the usual bid platforms.
Does Pennsylvania law set a deadline for paying subcontractors?
Under the Contractor and Subcontractor Payment Act, per FindLaw, a contractor must pay a subcontractor within 14 days after receiving each progress or final payment, or after receiving the subcontractor’s invoice, whichever is later.
What does a unit price do to the contract sum?
Per AIA, payment follows the quantity actually installed, multiplied by the stated unit price, even when it differs from the estimate.
Related: Prevailing wage in PA · Site work subcontractor · All commercial pages
Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.