Skip to content Groundwork Design Co.Want a design?Custom patio, wall, deck and yard plans, drawn by builders. Anywhere in the U.S. From $349.Start here
LOCK HAVEN, PA · PA HIC #PA212584 · INSURED FREE ESTIMATES · CALL OR TEXT
PAGE
Punch List
Project: [Project name] · [Property address]
Walk-through date: [Date] · List #[1]

1. Job and walk-through

Owner: [Owner name] · Contractor rep: [Name] · Others present: [designer, inspector, sub]

Scope reference: contract dated [date], plan sheet(s) [L-1, W-1], change orders [none / #1, #2].

2. Punch list

#ItemLocationTrade / responsiblePriorityPhoto refDate foundDate fixedSign-off
1[e.g. low joint sand at 3 paver joints][NE corner of patio][paver crew][H / M / L][IMG_0412][date][date][initials]
2[item][location][who][H / M / L][photo][date][date][initials]
3[item][location][who][H / M / L][photo][date][date][initials]
4[item][location][who][H / M / L][photo][date][date][initials]

Priority key: H = safety, water or structural, fix first. M = visible defect or missing item. L = cosmetic touch-up. Add rows as needed, and number every item so the owner and the crew refer to the same one.

3. Landscape and hardscape starter checklist

General good-practice items to check before you call the job done. Delete what does not apply and add what the plan calls for. Where the manufacturer’s instructions or the plan say otherwise, they govern.

AreaCheckOKPunch
Paver joint sandJoints full to the product’s instructions, surface swept clean, polymeric sand (if used) activated and set per the bag, no haze left on the pavers☐☐
Edge restraintInstalled along every open edge, tight to the pavers, secured, covered with soil or stone to finish grade, no gaps or movement☐☐
Compaction and settlementNo dips, rocking pavers or soft spots when walked; surface drains as planned; look again after the first heavy rain and note any low spots☐☐
Paver surfaceEven joint widths and lines, no chips or cracks, no lippage you can catch with a toe, cuts clean and tight to walls and edges☐☐
Wall units and capsCourses level and straight, batter as drawn, no cracked or chipped units, caps secured with the adhesive the manufacturer specifies and no loose caps☐☐
Wall drainageDrainage stone and outlet in place as drawn, pipe daylights and is clear, no water pooling at the base of the wall☐☐
Drainage testRun a hose at downspouts, drains and the top of slopes; water moves away from the house and off the hardscape, outlets flow, nothing ponds☐☐
GradingFinish grades match the plan, soil slopes away from the foundation, no low spots, transitions to walks and lawn are smooth☐☐
Steps and walksRisers and treads even, no trip edges, surfaces stable, handrails or guards in place where the plan or code requires them☐☐
Planting and mulchPlants as listed on the plan, watered in, mulch at the specified depth and pulled back from stems and trunks☐☐
Lawn restorationDisturbed areas seeded or sodded as agreed, ruts and tracks repaired, watering instructions left with the owner☐☐
Existing propertyDriveway, walks, irrigation heads, lighting, fences and utilities near the work checked for damage and noted☐☐
CleanupSpoils, scrap block, pallets, bags and fabric removed; surfaces washed or swept; gutters, drains and catch basins free of debris; tools gone☐☐
PaperworkPhotos of finished work saved, warranty and care instructions given to the owner, final change orders signed☐☐

4. Sign-off

The items above marked “Punch” will be corrected by [target date]. Final payment and warranty terms follow the contract. Signing below confirms the list is complete as of the walk-through date; new items found later will be added to a new list.

Owner signature · Date
Contractor signature · Date
All items corrected: owner initials · Date
Contractor initials · Date

How to run a punch list walk-through

Walk it with the owner, plan in hand

Walk the whole job together with the contract and the plan. Check against what was drawn and agreed, not against what the owner or you would build today. Anything the owner wants that was not in the scope is a new request, not a punch item, and belongs on a change order.

Write each item so someone else can fix it

Item, exact location, who fixes it, a photo, the date found. “Fix patio” cannot be signed off. “Re-sand joints, NE 4 ft of patio, see photo 412” can.

Set dates and close the list

Give every item a target date and sign it off when fixed. Keep one list per walk-through, so late complaints become a new list rather than a moving target. Your daily field logs show when items were built and checked, which helps if the owner remembers things differently.

Do not wait for the end

Check base, edge restraint, drainage and wall backfill while they are still visible. Fixing a base is a crew-day; fixing it after the pavers are down is a rebuild.

Where to find real inspection standards

The starter checklist above is general good practice from running jobs, not a published standard. For segmental retaining walls, the Concrete Masonry & Hardscapes Association publishes an Inspection Guide for Segmental Retaining Walls, described by CMHA as covering how to inspect these gravity walls. For interlocking pavers, check the installation instructions from your paver manufacturer and the Interlocking Concrete Pavement Institute (ICPI) technical specifications; we did not copy numbers from them here, so confirm tolerances in the current documents or on your plan. Manufacturer instructions for adhesives, polymeric sand and sealers always override a generic checklist.

Use it with your estimate and plan

A punch list is easier when the plan is specific: quantities, grades, drainage and wall sections drawn. If you want drawings under your logo, we draw plans for contractors. See also paver edging: which edge restraint to use, polymeric sand vs regular sand, retaining wall caps and adhesive, and the French drain calculator for drainage checks. The proposal template sets the scope you check against.

More free templates

This list is part of our free contractor templates. Also see the change order form template and the daily field log template.

Sources: CMHA, Inspection Guide for Segmental Retaining Walls (srw-tec-008), cited only as a pointer to the guide. Checklist items are general practice; manufacturer instructions and your plan govern.

Questions

What is a punch list?

A list of small items that remain to be fixed or finished at the end of a job, created in a walk-through with the owner, each with a location, a person responsible, and a sign-off when done.

When do I make a punch list?

When the work is substantially complete, before final payment. For longer jobs, do a mid-job check of hidden work such as base, drainage and wall backfill before covering it.

What is the difference between a punch list item and a change order?

A punch list item is something in the agreed scope that is missing or defective. Something new the owner wants is outside the scope and belongs on a change order.

Should I hold final payment until the punch list is done?

That depends on your contract’s payment terms. Write the terms into the contract before the job starts, and ask your attorney how they interact with your state’s home improvement rules.

Template by Groundwork Design Co., the design studio of Muthler Landscaping & Construction LLC, Lock Haven, PA. A practice guide, not legal advice.