Georgia Mechanics Lien Deadlines, Notices and Lien Waivers

In Georgia, a contractor, subcontractor, supplier or laborer has 90 days after completing the work or furnishing the materials to file a claim of lien with the superior court clerk in the county where the property sits, must send the owner a copy within two business days, and must start a lien action within 365 days after filing, then file a notice of that action within 30 days of starting it. Owners protect themselves from paying twice with Georgia’s statutory lien waiver forms and the contractor’s sworn statement of payment at final payment.

Quick answer

  • File the claim of lien: Within 90 days after completing work or furnishing materials, with the superior court clerk
  • Copy to the owner: Within 2 business days, by registered or certified mail or statutory overnight delivery
  • Enforce: Lien action within 365 days after filing; notice of the action filed within 30 days after starting it
  • Notice of commencement: Optional; filed within 15 days after the contractor physically starts work
  • Notice to contractor: Subs and suppliers without a contract with the GC, within 30 days, only if a notice of commencement was filed
  • Waivers: Statutory forms only; 90 days to file an affidavit of nonpayment or the waiver becomes binding

Who can file a mechanics lien in Georgia?

Under O.C.G.A. § 44-14-361(a), a special lien on real estate goes to contractors, subcontractors and materialmen, laborers working for them, mechanics who took no personal security, suppliers of rental tools and equipment used on the improvement, and registered architects, engineers, land surveyors, foresters and interior designers. Two conditions apply before any of it matters:

Georgia mechanics lien deadlines

StepDeadlineWhoLaw
Notice of commencement (optional)No later than 15 days after the contractor physically starts work; filed with the superior court clerk and posted on siteOwner, owner’s agent or contractor361.5
Preliminary notice of lien rights (optional)Within 30 days after first furnishing labor or materials; non-contractor filers send a copy within 7 daysAny lien claimant361.3
Notice to contractorWithin 30 days after the later of the notice of commencement filing or first furnishing; only if a notice of commencement was filedSubs and suppliers not in privity with the contractor361.5
File the claim of lienWithin 90 days after completing the work or furnishing materialsAll claimants361.1(a)(2)
Send the owner a copyNo later than 2 business days after filingAll claimants361.1(a)(2)
Start the lien actionWithin 365 days after filing the claim of lienLienholder361.1(a)(3)
File notice of the lien actionWithin 30 days after starting the action, in the county where the lien was recordedLienholder361.1(a)(3)

The 90-day clock runs from completion of your work or delivery, not from your invoice. Miss any of the 361.1(a) steps and the lien is not effective or enforceable.

What a Georgia claim of lien has to include

  • Owner’s rights notice: the claim must state that it expires under § 44-14-367 and give the owner notice of the right to contest it. Without that language, the lien is invalid.
  • 395-day warning: liens filed after March 31, 2009 must state on their face that they can be disregarded if no notice of a lien action is filed within 395 days (§ 44-14-367).
  • Delivery: the owner’s copy goes by registered or certified mail or statutory overnight delivery. If the owner’s address can’t be found, it goes to the contractor as the owner’s agent; an owner registered with the Secretary of State can be served at its entity or registered agent address. If a notice of commencement was filed, a copy also goes to the contractor at the address on that notice.

Notice of commencement and notice to contractor

A notice of commencement lists the contractor, the project and its legal description, the true owner, any bond surety and any construction lender (§ 44-14-361.5). Once one is filed, subcontractors and suppliers who don’t have a contract directly with the contractor must send the owner and contractor a notice to contractor within 30 days, by certified or registered mail or overnight delivery. If no notice of commencement is filed, that section doesn’t apply, so those subs and suppliers don’t need a notice to contractor to keep lien rights. The contractor has to give a copy of the notice to anyone who asks in writing; if it doesn’t within 10 days, the notice requirement doesn’t apply to that requester.

A preliminary notice of lien rights is different and always optional. It costs $5 to file with the clerk, who indexes it under the owner’s name, and lienholders can enforce a lien without one (§ 44-14-361.3). Its real value shows up at final payment, below.

Georgia lien waivers after the 2021 changes

Georgia only recognizes lien waivers written on its statutory forms, and the rules were rewritten effective January 1, 2021 (§ 44-14-366):

  • Two forms: an interim waiver (“Waiver and Release of Lien and Payment Bond Rights Upon Interim Payment”) for progress payments and a final waiver to induce final payment. Each must substantially follow the statutory text, be in at least 12-point type and include the statutory notice paragraph, or it is unenforceable.
  • Lien and bond rights only: since 2021 the waivers release lien and payment bond rights, not the claimant’s other remedies such as a breach of contract claim.
  • No advance waivers: a waiver signed before the labor or materials are furnished is void.
  • When it becomes binding: on the earliest of actual receipt of the funds, a separate written acknowledgment of full payment, or 90 days after the waiver is signed unless an affidavit of nonpayment is filed first.
  • Affidavit of nonpayment: a claimant who signed a waiver but wasn’t paid files a sworn affidavit on the statutory form in the county where the property sits within those 90 days, then sends the owner a copy within 7 days. Before 2021 the window was 60 days, so older guides are out of date.

How Georgia homeowners avoid paying twice

Under § 44-14-361.2, a lien is dissolved if the owner shows either a written waiver from the claimant, or a sworn statement from the contractor, obtained at final payment of the contract price, that the claimant has been paid or has waived in writing. The sworn statement only protects you if no valid preliminary notice or claim of lien was on record at that time. Put together:

  1. Collect an interim waiver from the contractor, and from major subs and suppliers, with each progress payment.
  2. Before final payment, check the superior court clerk’s records under your name for preliminary notices or liens.
  3. Get the contractor’s sworn statement and final waivers when you make final payment.
  4. Pay in traceable ways. Georgia’s consumer office also suggests tying payments to finished stages, holding back 10% until the job is done and asking for a bond covering subs and suppliers (choosing a contractor).

How to remove or challenge a lien in Georgia

  • Bond it off: the owner or contractor can file a bond with the clerk for double the amount claimed, or the lien amount when the lien is on the owner’s home. Once the clerk approves it, the property is released, and notice goes to the claimant within 7 days (§ 44-14-364).
  • Notice of contest: the owner or contractor can record a notice of contest to shorten the claimant’s time; under § 44-14-368(c), the lien is extinguished 90 days after the contest is filed unless a notice of a lien action is filed first. The statute’s sample form speaks of 60 days from receipt, so claimants shouldn’t wait (§ 44-14-368).
  • Let it expire: without a lien action within 365 days, or a notice of that action, the lien is unenforceable, and it can be disregarded after 395 days with no release needed (§ 44-14-367).

Common mistakes by contractors

  • Counting 90 days from the invoice instead of the last day of work or delivery.
  • Filing the lien but not mailing the owner’s copy within 2 business days.
  • Signing a waiver before the check clears and missing the 90-day affidavit of nonpayment.
  • Suing within 365 days but forgetting the separate notice of the action 30 days later.

Sources

Last checked November 14, 2026.

Common questions

How long do you have to file a mechanics lien in Georgia?

Ninety days after completing the work or furnishing the materials. The claim of lien is filed with the superior court clerk in the county where the property is located, and a copy must be sent to the owner within two business days.

How long does a mechanics lien last in Georgia?

The claimant must start a lien action within 365 days after filing the lien and file a notice of that action within 30 days of starting it. Otherwise the lien is unenforceable, and it can be disregarded after 395 days.

How long do you have to file an affidavit of nonpayment in Georgia?

Ninety days after signing the lien waiver. If no affidavit of nonpayment is filed in that time, the statutory waiver becomes binding even if the money was never received. The window was 60 days before January 1, 2021.

Can a subcontractor put a lien on my house if I paid my contractor in Georgia?

Possibly. The lien is dissolved if you hold the subcontractor’s written waiver, or if at final payment you got the contractor’s sworn statement that the subcontractor was paid and no preliminary notice or claim of lien was on record.

This is a plain-English summary, not legal advice.

See every Georgia building, digging and contractor rule on our Georgia guide. Related: Georgia contractor license requirements · Georgia building code · Georgia permits for decks, sheds and retaining walls.

Groundwork Design Co. · designed by builders

Plans drawn for Georgia’s rules

Groundwork Design Co. draws patios, walls, decks and planting plans to scale for any U.S. home, with the layout, sizes and materials any local contractor can price.

See design plansSee sample plans

Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.

Cite as: Muthler Landscaping & Construction, “Georgia Mechanics Lien Deadlines, Notices and Lien Waivers,” https://muthlerlandscaping.com/state-guides/georgia/mechanics-lien/ (page updated November 14, 2026).