State guides · Permits · Erosion and sediment control

Erosion and sediment control permit thresholds by state

The land-disturbance number that triggers a construction stormwater permit (1 acre in the states we confirmed), the lower state triggers that catch small patio, wall and regrading jobs, and the agency to call. Last checked November 22, 2026.

Read this first

Almost every state follows the federal 1-acre rule for construction stormwater permits, but a handful of states and towns set a much lower trigger for an erosion and sediment plan. Your county or town can be stricter than the state. Where we could not confirm a number from an official page, the cell says so. Not legal advice.

1 acre is the usual trigger

In the states we confirmed, a permit is needed at 1 acre or more of land disturbance, or less if the site is part of a larger common plan of development or sale of 1 acre or more.

Lower triggers exist

Examples from official pages: D.C. at more than 50 sq ft, Maryland at 5,000 sq ft or 100 cubic yards, New York at 5,000 sq ft East of the Hudson, Michigan within 500 feet of a lake or stream.

EPA issues it in four places

In D.C., Massachusetts, New Hampshire and New Mexico, EPA, not a state agency, is the construction stormwater permitting authority. EPA also covers Indian country and some federal sites in other states.

Related guides: drainage laws by state (neighbor runoff rules and stormwater permits) and Pennsylvania county conservation districts (E&S plans and contacts for all 66 districts).

Erosion and sediment control triggers, state by state

StateWho issuesConstruction stormwater (NPDES) permit triggerLower state erosion or sediment plan triggerOfficial source
AlabamaAlabama Dept. of Environmental Management (ADEM)1 acre or more of land disturbance, or less if part of a common plan of 1 acre or more (ALR100000)None stated on the ADEM page; regulated sites follow a Construction BMP PlanADEM
AlaskaAlaska DEC (APDES program)Total land disturbance of 1 acre or moreNone stated on the DEC pageAlaska DEC
ArizonaArizona DEQ (AZPDES)1 or more acres, or less if part of a larger common plan that will disturb 1 acre or more (AZG2025-001)None stated on the ADEQ pageADEQ
ArkansasArkansas DEQ1 acre or more, or less if part of a larger common plan (General Permit ARR150000)None stated in the DEQ fact sheetADEQ fact sheet
CaliforniaState Water Resources Control Board and regional boards1 acre or more, or less if part of a larger common plan that disturbs 1 acre or more (Order WQ 2022-0057-DWQ)None stated; the Board’s page notes a rainfall erosivity waiver for sites of 1 to 5 acresState Water Board
ColoradoColorado Dept. of Public Health and Environment (COR400000)Not confirmed – check your local codeCDPHE’s page says a site under 5 acres that is not part of a larger 5-acre plan should contact the applicable cityCDPHE
ConnecticutConnecticut DEEPDisturb a total of 1 acre or more (CTR100000)Not confirmed – check your local codeDEEP fact sheet
DelawareDNREC, Sediment and Stormwater ProgramLand disturbance of 1 acre or more; covered sites need an approved Sediment and Stormwater Management PlanNot confirmed – check your local codeDNREC fact sheet
District of ColumbiaU.S. EPA for the NPDES permit (DCR100000); D.C. DOEE for erosion and sediment control plansEPA Construction General Permit (1 acre or more under the CGP)Erosion and sediment control plan for projects that disturb more than 50 sq ft; DOEE approves and stamps the planDOEE
FloridaFlorida DEP1 or more acres, or less if part of a common plan of development or sale (Construction Generic Permit 62-621.300(4)(a))None stated in the permitFlorida DEP
GeorgiaGeorgia EPD1 acre or more (GAR100001, Part I.C.1)Not confirmed – check your local codeGeorgia EPD permit
HawaiiHawaii Dept. of Health, Clean Water Branch1 acre or more of total land area, or less if part of a larger common plan of 1 acre or more (Appendix C general permit)None stated on the DOH pageHawaii DOH
IdahoIdaho DEQ (IPDES program)Disturb 1 acre or more of landNone stated on the DEQ pageIdaho DEQ
IllinoisIllinois EPA1 acre or more (General NPDES Permit for Construction Site Activities)None stated on the Illinois EPA pageIllinois EPA
IndianaIndiana IDEM1 acre or more, or less if part of a larger common plan of development or saleNone stated on the IDEM pageIDEM
IowaIowa DNR1 acre or more (NPDES General Permit No. 2)None stated on the DNR pageIowa DNR
KansasKansas Dept. of Health and Environment (KDHE)Not confirmed – check your local codeNot confirmed – check your local codeKDHE
KentuckyKentucky Energy and Environment Cabinet, Division of WaterClearing, grading or excavating that disturbs 1 acre or moreNone stated in the fact sheetKY Division of Water
LouisianaLouisiana DEQ1 to under 5 acres: small construction general permit LAR200000; 5 acres or more: LAR100000None stated on the LDEQ pageLDEQ
MaineMaine DEPStormwater Management Law applies to 1 acre or more of disturbed area in organized areas, with exemptions; the DEP page gives no acreage for the Maine Construction General PermitThe Erosion and Sedimentation Control Law (38 M.R.S. 420-C) applies; DEP’s page states no size thresholdMaine DEP
MarylandMaryland Dept. of the Environment (MDE); local jurisdictions approve plansNot confirmed – check your local codeGrading permit and sediment control plan not required if less than 5,000 sq ft or 100 cubic yards is disturbed; local jurisdictions can be stricterMDE
MassachusettsU.S. EPA (MAR100000)EPA Construction General Permit: greater than 1 acre, or part of a larger common plan greater than 1 acre, with a stormwater path to waters of the U.S. (Mass.gov wording)None stated on the Mass.gov pageMass.gov
MichiganMichigan EGLE (Part 91 SESC permits)Not confirmed – check your local codePart 91 soil erosion and sedimentation control permit generally required for earth changes disturbing 1 or more acres, or within 500 feet of a lake or streamEGLE
MinnesotaMinnesota Pollution Control Agency1 acre or more of soil disturbance, or less if part of a larger plan covering more than 1 acreNone stated on the MPCA pageMPCA
MississippiMississippi DEQSmall construction 1 to under 5 acres; large construction 5 acres and greaterNone stated on the MDEQ pageMDEQ
MissouriMissouri DNR1 or more acres, or less if part of a larger common plan that will disturb 1 or more acresNone stated on the DNR pageMissouri DNR
MontanaMontana DEQ (MPDES)Not confirmed – check your local codeNot confirmed – check your local codeMontana DEQ
NebraskaNebraska Dept. of Water, Energy, and Environment (permit NER210000)Not confirmed – check your local codeNot confirmed – check your local codeNebraska DWEE
NevadaNevada Division of Environmental Protection (NVR100000)Disturb 1 acre or more of landNone stated on the NDEP pageNDEP
New HampshireU.S. EPA for the NPDES permit (NHR100000); NHDES for Alteration of TerrainEPA Construction General Permit (1 acre or more under the CGP)Alteration of Terrain: more than 100,000 sq ft of contiguous area (50,000 sq ft within protected shoreland), or more than 2,500 sq ft within 50 feet of surface water on slopes of 25% or more (Env-Wq 1502.58(b); 2025 law changes mean you should confirm current numbers with NHDES)NH Env-Wq 1500
New JerseyNJDEP; local Soil Conservation Districts certify plansDisturb 1 acre or more: construction general permit 5G3Soil Erosion and Sediment Control Plan certified by the local Soil Conservation District; square-foot trigger: Not confirmed – check your local codeNJ Dept. of Agriculture
New MexicoU.S. EPA (NMR100000); NMED provides state certification1 acre or more, or less if part of a common plan that will ultimately disturb 1 acre or moreNone stated in the permitEPA CGP (NMED copy)
New YorkNew York State DEC (SPDES GP-0-25-001)Soil disturbance of 1 or more acres5,000 sq ft or more (under 1 acre) in the New York City East of Hudson watershed; 20,000 sq ft or more within New York CityNYSDEC
North CarolinaNC DEQ (some local programs); NCG01 certificate after plan approvalErosion and sedimentation control plan for a site of 1 acre or larger, submitted at least 30 days before land disturbance; then an NCG01 Notice of IntentLocal programs may set lower acreage thresholdsNC DEQ
North DakotaNorth Dakota DEQConstruction projects that disturb 1 or more acresNone stated on the DEQ pageND DEQ
OhioOhio EPA, Division of Surface WaterProject disturbs 1 or more acres of groundNone stated on the Ohio EPA pageOhio EPA
OklahomaOklahoma DEQ (OKR10)Sites of 1 acre or more, or less if part of a larger common plan that will disturb 1 acre or moreNone stated in the permit textOklahoma DEQ permit
OregonOregon DEQ (1200-C permit)Construction activities of 1 acre or moreNone stated on the DEQ pageOregon DEQ
PennsylvaniaPennsylvania DEP, Bureau of Clean Water (Chapter 102 program)Earth disturbances greater than or equal to 1 acreNot confirmed – check your local code; see our PA conservation districts guide for the E&S plan rule and district contactsPA DEP
Rhode IslandRhode Island DEM (RIPDES)A project that disturbs more than 1 acre must apply (RIDEM wording); the 2026 CGP runs Sept. 27, 2026 to Sept. 27, 2031Expedited review is for projects disturbing less than 5 acresRIDEM
South CarolinaSouth Carolina Dept. of Environmental Services1 acre or more of land disturbanceWork within one-half mile of a receiving water body in the Coastal Zone also needs a permit, even below 1 acreSC DES
South DakotaSouth Dakota DANRConstruction activities disturbing 1 or more acresNone stated on the DANR pageSD DANR
TennesseeTennessee Dept. of Environment and ConservationArea of disturbance of 1 or more acres, or less if part of a larger common planNone stated on the TDEC pageTDEC
TexasTexas Commission on Environmental Quality (TXR150000)Small sites: at least 1 but less than 5 acres; large sites: 5 or more acresNone stated on the TCEQ pageTCEQ
UtahUtah DEQ, Division of Water Quality (UPDES)Soil disturbances of an acre or moreNone stated on the DEQ pageUtah DEQ
VermontVermont DEC (EPA covers federal facilities only)Total earth disturbance of 1 acre or moreNone stated on the DEC pageVermont DEC
VirginiaVirginia DEQ; localities run local programsLand disturbance of 1 acre or more, or less if part of a larger common plan that will disturb 1 acre or moreLocalities under the Chesapeake Bay Preservation Act may regulate single-family homes at 2,500 sq ft or more of disturbanceVirginia DEQ
WashingtonWashington Dept. of EcologySites that disturb 1 acre or moreNone stated on the Ecology pageWA Ecology
West VirginiaWest Virginia DEPEarth disturbance of 1 acre or moreNone stated on the WVDEP pageWVDEP
WisconsinWisconsin DNR (WPDES)1 or more acres of land disturbedNot confirmed – check your local codeWisconsin DNR
WyomingWyoming DEQ (WYPDES)Small construction: at least 1 but less than 5 acres; large construction: 5 or more acresNone stated on the DEQ pageWyoming DEQ

“None stated” means the official page gave no lower statewide number, not that none exists. Cities, counties and conservation districts often set their own grading and erosion rules, so call your local code office before you dig.

Where EPA is the permitting authority

EPA’s 2022 Construction General Permit Appendix B lists D.C., Massachusetts, New Hampshire and New Mexico as EPA-permitted, plus Indian country in most states and federal facilities in Colorado, Delaware, Vermont and Washington. Everywhere else in the table, the state agency named issues the permit.

Questions

Do I need a permit to build a patio or retaining wall?

The federal-style construction stormwater permit starts at 1 acre in the states we confirmed, so most single patios and walls fall below it. A lower state or local erosion and sediment plan trigger can still apply, such as D.C. at more than 50 sq ft or Maryland at 5,000 sq ft or 100 cubic yards. Check the table and your local code office.

What counts as a larger common plan of development?

Many state permits cover a site under 1 acre if it is part of a larger plan, such as a subdivision, that will disturb 1 acre or more in total. Individual lots can fall under the developer’s permit or need their own coverage, depending on the state.

Who do I call first?

Your local building or code office, then the state agency in the table. In Pennsylvania, start with the county conservation district; see our conservation district guide.

How does this relate to neighbor drainage rules?

A permit threshold is about runoff leaving your site during construction. Liability to a neighbor for changed drainage is a separate question, covered in our drainage laws by state guide.

Sources: the state agency pages linked in each row, plus EPA 2022 Construction General Permit, Appendix B, Areas of Permit Coverage and EPA, authorization status of construction and industrial stormwater programs. Last checked November 22, 2026.

Muthler Landscaping & Construction · Lock Haven, PA

Moving dirt on your property?

We handle the grading, erosion controls and permit paperwork on patio, wall and drainage jobs across Clinton, Centre, Lycoming and Union counties.

Get a quoteRetaining wall permits by state

Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.

Using this guide? Link to it or cite it. It’s free to use with a link back, and we keep it updated against official sources.

Cite as: Muthler Landscaping & Construction, “Erosion and Sediment Control Permit Thresholds by State,” https://muthlerlandscaping.com/state-guides/erosion-control-permits/ (page updated November 23, 2026).