A 12×12 slab poured 4 inches thick is 144 sq ft and takes 1.78 cubic yards of concrete. Here is the full list: yards, bags, rebar, base stone and the cost range.

  • 1.78 cu yd at 4 in
  • 80 80-lb bags
  • 3.0 tons of base stone
Concrete calculator →Concrete patio cost guide

Materials for a 12×12 concrete slab

ItemQuantityNotes
Slab area144 sq ft12 ft × 12 ft, 4 in thick
Concrete, exact1.78 cu yd144 sq ft × 4 in ÷ 12 ÷ 27
Concrete to order (+10%)1.96 cu ydextra for uneven subgrade and spillage; round up to the plant’s increment
Bags, 80 lb80 bags89 with 10% extra; 0.60 cu ft per bag
Bags, 60 lb107 bags0.45 cu ft per bag
Rebar grid, 16 in on center240 lin ft12 sticks of 20 ft, plus tie wire and chairs; confirm the spec for your use
Base: compacted 2A stone, 4 in3.0 tons1.4 tons per cu yd plus 20% for compaction
Form lumber48 ftperimeter, staked and braced

Volume is length × width × thickness. Bag yields are the Quikrete label figures (80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45 cu ft). Stone uses our 2A weight page (1.25 to 1.55 tons per yard; we plan 1.4). Rebar count assumes a 16 in grid each way; use our rebar and wire mesh calculator for other spacings. Planning estimates only.

4 in or 6 in?

ThicknessCubic yardsTypical use
4 in1.78patio, walkway pad, small shed pad
6 in2.67heavier loads; confirm with your engineer or the shed maker’s spec

What it costs

  • Our concrete patio cost guide puts finished concrete at $5 to $10 per sq ft, so a 12×12 runs about $720 to $1,440.
  • 80 bags is about 6,400 lb of bags to mix and place before it sets. Past this size, ready-mix is usually the better call.
  • Check whether you can pour concrete today before you book the truck.

12 ft is the edge of the 4 in joint band

A 12 ft slab sits right at the limit where joint guidance starts to matter. The JLC Field Guide on structural slabs gives control joint spacing of 8 to 12 ft for a 4 in slab and 10 to 15 ft for a 5 in slab. A Concrete in Practice sheet on joints says to keep panels square or nearly so, with length no more than 1.5 times width, and to avoid L-shaped panels. The layout options below apply those two rules to 12×12.

LayoutPanel sizeLength to widthSaw cut length
No interior joint12 x 12 ft1.00 ft
One cut, one direction6 x 12 ft2.0, over the 1.5 limit12 ft
One cut each way6 x 6 ft1.024 ft

The single cut in one direction is the layout to avoid, because it makes 2:1 panels. Whether 12×12 needs joints at all is a judgment at the edge of the guidance, and the answer is not the same as for a 10×10 or 16×16 page. Our reading, not a code ruling. Sources: CIP 6, Joints in Concrete Slabs on Grade and JLC Field Guide: Structural Slabs. Verify against the current sources.

Joint depth and sawing window

CIP 6 gives a contraction joint depth of at least one quarter of the slab thickness, and not less than 1 in. For a 4 in slab that is 1 in, and for a 5 in slab it is 1.25 in. The JLC guide lists 3/4 to 1 in for 4 in and 1 to 1 1/4 in for 5 in, so the two sources differ slightly at 4 in. CIP 6 says conventional saw cuts should go in within 4 to 12 hours after finishing, and JLC warns that random cracks can appear in as little as six hours in hot weather. Plan the saw before you place the concrete.

Thickness changes the order fast

ThicknessCubic yardsWith 10% extra80 lb bagsWeight of bags
4 in1.781.96806,400 lb
5 in2.222.441008,000 lb
6 in2.672.931209,600 lb

Cubic yards = 144 sq ft × thickness ÷ 12 ÷ 27. Bags = 144 × thickness ÷ 12 ÷ 0.60, rounded up. A 4 in 12×12 is 80 bags, but a 6 in one is 120. The JLC guide lists 4 in for its lighter floor classes (1 through 3) and 5 in for its heavier ones (4 and 5).

Questions

How many yards of concrete for a 12×12 slab?

1.78 cubic yards at 4 inches thick. Order about 1.96 yards with 10% extra.

How many 80 lb bags for a 12×12 slab?

80 bags at 4 inches, or 89 with 10% extra. Each 80 lb bag yields about 0.60 cubic feet.

Does a 12×12 slab need rebar?

It depends on the use and local code. Many residential slabs use rebar, wire mesh or fiber. A 16 in grid is 240 linear feet for this size. See our rebar calculator.

How much base stone for a 12×12 slab?

About 3.0 tons of 2A at 4 inches compacted, using 1.4 tons per cubic yard and 20% for compaction.

Does a 12×12 slab need control joints?

It sits at the edge of the guidance: a 4 inch slab has an 8 to 12 ft joint spacing range, and a 5 inch slab has 10 to 15 ft. If you cut, one cut each way gives 6 ft squares; a single cut makes 2:1 panels, which the CIP 6 sheet advises against.