A 10×10 slab poured 4 inches thick is 100 sq ft and takes 1.23 cubic yards of concrete. Here is the full list: yards, bags, rebar, base stone and the cost range.
- 1.23 cu yd at 4 in
- 56 80-lb bags
- 2.1 tons of base stone
Materials for a 10×10 concrete slab
| Item | Quantity | Notes |
|---|---|---|
| Slab area | 100 sq ft | 10 ft × 10 ft, 4 in thick |
| Concrete, exact | 1.23 cu yd | 100 sq ft × 4 in ÷ 12 ÷ 27 |
| Concrete to order (+10%) | 1.36 cu yd | extra for uneven subgrade and spillage; round up to the plant’s increment |
| Bags, 80 lb | 56 bags | 62 with 10% extra; 0.60 cu ft per bag |
| Bags, 60 lb | 75 bags | 0.45 cu ft per bag |
| Rebar grid, 16 in on center | 160 lin ft | 8 sticks of 20 ft, plus tie wire and chairs; confirm the spec for your use |
| Base: compacted 2A stone, 4 in | 2.1 tons | 1.4 tons per cu yd plus 20% for compaction |
| Form lumber | 40 ft | perimeter, staked and braced |
Volume is length × width × thickness. Bag yields are the Quikrete label figures (80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45 cu ft). Stone uses our 2A weight page (1.25 to 1.55 tons per yard; we plan 1.4). Rebar count assumes a 16 in grid each way; use our rebar and wire mesh calculator for other spacings. Planning estimates only.
4 in or 6 in?
| Thickness | Cubic yards | Typical use |
|---|---|---|
| 4 in | 1.23 | patio, walkway pad, small shed pad |
| 6 in | 1.85 | heavier loads; confirm with your engineer or the shed maker’s spec |
What it costs
- Our concrete patio cost guide puts finished concrete at $5 to $10 per sq ft, so a 10×10 runs about $500 to $1,000.
- At this size, a bag job is realistic: 56 bags is about 4,500 lb of bags to mix. For larger slabs, ready-mix is usually the better call.
- Check whether you can pour concrete today before you book the truck.
Does a 10×10 slab need control joints?
Probably not in the middle. A Concrete in Practice sheet on joints gives maximum spacing as 24 to 36 times the slab thickness, which for 4 inches is 8 to 12 ft (24 × 4 in = 96 in; 36 × 4 in = 144 in). It recommends capping spacing at 15 ft, keeping panels square or nearly so, with length no more than 1.5 times width. A 10 ft square slab is a 1.0 ratio panel and sits inside the 8 to 12 ft band, so by these figures it does not need an interior joint. That is our reading of the sheet, not a code ruling.
| Slab thickness | Joint spacing in the JLC guide | 10 ft slab inside it? |
|---|---|---|
| 4 in | 8 to 12 ft | yes |
| 5 in | 10 to 15 ft | yes, at the low end |
| 6 in | 12 to 18 ft | yes, with room to spare |
Spacing figures come from the table in the JLC Field Guide on structural slabs, which agrees with the CIP 6 multiples for 4 in. Sources: CIP 6, Joints in Concrete Slabs on Grade and JLC Field Guide: Structural Slabs. Verify against the current sources.
Bag math for a small pad
A 10×10 is one of the few slabs where mixing bags yourself is reasonable. The weight of bags to move and mix before the batch stiffens climbs fast with thickness.
| Thickness | Cubic feet | 80 lb bags | Weight of 80 lb bags |
|---|---|---|---|
| 4 in | 33.3 | 56 | 4,480 lb |
| 5 in | 41.7 | 70 | 5,600 lb |
| 6 in | 50.0 | 84 | 6,720 lb |
Cubic feet = 100 sq ft × thickness ÷ 12; bags = cubic feet ÷ 0.60, rounded up; weight = bags × 80 lb. No waste allowance is included. A 6 in base under the slab, instead of 4 in, takes 3.1 tons of 2A rather than 2.1.
Subgrade checks before you pour
The JLC guide lists well-drained native soil, or granular fill if the soil is unsuitable, compacted to typically 95% or more, with the surface level to within 1/2 in across the slab. It lists a vapor barrier of at least 4 to 6 mil poly with seams lapped at least 6 in. On wire mesh, it says to keep 6×6 wire no closer than 2 in to the top surface and to stop it several inches back from each joint. If the slab will touch a building or footing, the CIP 6 sheet describes premolded filler as an isolation joint.
Questions
How many yards of concrete for a 10×10 slab?
1.23 cubic yards at 4 inches thick. Order about 1.36 yards with 10% extra.
How many 80 lb bags for a 10×10 slab?
56 bags at 4 inches, or 62 with 10% extra. Each 80 lb bag yields about 0.60 cubic feet.
Does a 10×10 slab need rebar?
It depends on the use and local code. Many residential slabs use rebar, wire mesh or fiber. A 16 in grid is 160 linear feet for this size. See our rebar calculator.
How much base stone for a 10×10 slab?
About 2.1 tons of 2A at 4 inches compacted, using 1.4 tons per cubic yard and 20% for compaction.
Does a 10×10 slab need control joints?
Probably not in the middle. For a 4 inch slab the guides give 8 to 12 ft spacing, and a 10 ft square panel falls inside that. This is our reading of the sources, so confirm with your inspector or engineer.
Nearby sizes
16×16 concrete slab
10×10 paver patio
Concrete calculator
Concrete weight per yard
Shed slab thickness
Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.