Pennsylvania riparian buffers and Act 162 of 2014: the Chapter 102 options
Quick answer: Act 162 of 2014 lets an applicant for an NPDES construction stormwater permit use a riparian buffer or practices substantially equivalent to one. The 150 foot trigger in section 102.14(a) is unchanged, and disturbance within 100 feet of surface water with alternatives requires a 1 to 1 replacement buffer offset in special protection watersheds.
What Act 162 changed
Act 162 of 2014 amended Section 402 of the Clean Streams Law by adding a new subsection (c). According to the unofficial copy of the act on DEP’s site, it applies to earth disturbance activities that need an NPDES stormwater discharge permit under 25 Pa. Code Chapter 102. Permittees may use or install either a riparian buffer or riparian forest buffer, or other best management practices, design standards or alternatives that together are substantially equivalent to a riparian buffer or riparian forest buffer in effectiveness. The stated goal is to limit accelerated erosion and sedimentation and protect the water quality and designated uses of perennial or intermittent rivers, streams, creeks, lakes, ponds and reservoirs, consistent with Chapter 93.
DEP’s FAQ stresses that the act does not eliminate riparian buffers. It gives applicants two options: implement a buffer, or use practices equivalent in effectiveness.
Which permits it covers
The FAQ says Act 162 applies only to NPDES permits under Chapter 102, meaning the NPDES stormwater construction permit under section 102.5. It does not apply to non-NPDES Chapter 102 permits, including the erosion and sediment control permit for timber harvesting and road maintenance, or the oil and gas permit known as ESCGP-2. Permits issued before December 21, 2014 are not covered and must meet the requirements in place before the act took effect. The act is not retroactive, so renewing a permit that included riparian buffer practices from a prior term does not make a project eligible for the new options.
Distances that matter
| Distance | What it triggers, per DEP |
|---|---|
| Within 150 feet of a special protection water | The trigger for the section 102.14(a) buffer requirement stays at 150 feet. Act 162 changed only the compliance options. |
| Earth disturbance within 100 feet of surface water, where alternative practices are used | A replacement buffer offset is required under section 402(c)(2) |
The act text describes the offset for projects in the special protection watersheds listed in 25 Pa. Code 93.9. Any reduction in buffer square footage that would otherwise serve as a practice must be offset by a replacement buffer located elsewhere along special protection waters in the same drainage list, as close as feasible to the disturbance, at a 1 to 1 ratio. Projects using an alternative must also include other post-construction stormwater practices, and replacement planting costs are calculated using the Department’s guidance in BMP 6.7.1, Riparian Buffer Restoration, of the Pennsylvania Stormwater Best Management Practices Manual.
How far the 100 foot offset reaches
DEP’s FAQ says that when alternative practices are used under section 402(c)(1)(ii), the offset applies to earth disturbance within 100 feet of all surface waters, including perennial and intermittent streams, rivers, lakes, reservoirs, ponds, wetlands, springs, natural seeps and estuaries. It also says the offset applies only to applicants who are subject to section 102.14(a) and who choose alternate on-site practices. It does not apply to all earth disturbance. No waiver or exception exists for the offset requirements. The offset is required in addition to on-site post-construction stormwater practices, and those on-site practices must be substantially equivalent to a riparian or riparian forest buffer.
Waivers and exceptions in section 102.14
Exceptions under section 102.14(d)(1) remain available. An applicant who qualifies for an exception has no mandatory buffer requirement and does not need the act’s options. The FAQ says applicants after December 21, 2014 who do not meet section 102.14(a) cannot seek the older waivers under section 102.14(d)(2), because the act allows only equivalent alternatives. For a project within 150 feet of high quality or exceptional value waters, requirements depend on whether a Chapter 102 permit is needed and which type, and DEP suggests evaluating the (d)(1) exceptions and requesting a pre-application meeting.
Equivalency and offset demonstrations
The FAQ says an equivalency demonstration must be done on site, on the same project site covered by the permit application, and that the equivalency and offset demonstrations are independent of each other. How DEP judges substantially equivalent was to be covered in forthcoming policy documents numbered 310-2135-002 for equivalency and 310-2135-003 for offsetting. The FAQ is dated December 18, 2014, so check DEP’s current guidance before relying on those details.
Other Chapter 102 duties still apply
Using a buffer does not relieve an applicant of other requirements. Erosion and sediment control under section 102.4(b) and post-construction stormwater management under section 102.8 still apply. The FAQ also notes that riparian buffers remain nondischarge practices under section 102.8(h)(1), and that the alternative option carries no antidegradation presumption like the one in section 102.14(e). Under section 102.14(e)(1), buffers that meet the chapter’s requirements are presumed to prevent thermal impacts and to serve as a non-discharge alternative, while an applicant using alternatives must demonstrate equivalent thermal and water quality protection. In the FAQ, DEP and the Environmental Quality Board were still evaluating whether Chapter 102 should be amended to conform to the act.
Where this fits
For when a Chapter 102 plan or NPDES permit is needed at all, see our Chapter 102 page and the NPDES construction stormwater permit overview. The county conservation district and DEP decide how these rules apply to a given site.
Sources
- PA DEP, Frequently Asked Questions for Act 162 of 2014 Implementation (Dec. 18, 2014)
- PA DEP, Unofficial Copy of Act 162 of 2014
Sources checked Nov 23, 2026.
Related
Chapter 102 erosion and sediment control · NPDES construction stormwater permit · Chapter 105 waterways and wetlands · All PA site work regulations
FAQ
Did Act 162 of 2014 eliminate riparian buffers in Pennsylvania?
No. DEP’s FAQ says it does not. Applicants either implement a riparian or riparian forest buffer or use practices substantially equivalent in effectiveness.
Which permits does Act 162 apply to?
Only NPDES stormwater construction permits under Chapter 102, section 102.5. It does not apply to non-NPDES Chapter 102 permits such as timber harvesting and road maintenance permits.
What is the 100 foot rule in Act 162?
For special protection watersheds, earth disturbance within 100 feet of surface water that uses alternative practices must be offset by a replacement buffer at a 1 to 1 ratio, per the act text.
Does a buffer replace erosion and sediment control?
No. DEP’s FAQ says section 102.4(b) erosion and sediment control and section 102.8 post-construction stormwater management still apply.
General information only, not legal advice. Your county conservation district, DEP and your municipality decide what applies to a specific project. Source pages checked Nov 23, 2026.