PNDI environmental review in Pennsylvania: receipts, fees and screening buffers
Quick answer: PNDI review checks a project footprint against Pennsylvania rare species and habitat data. The Conservation Explorer charges a $40 convenience fee per project, a receipt is valid for two years, and four agencies take part: DCNR, the Fish and Boat Commission, the Game Commission and the U.S. Fish and Wildlife Service.
What PNDI is
PNDI is the Pennsylvania Natural Diversity Inventory, a database of rare, threatened and endangered species and special habitats. The FAQ says the Pennsylvania Natural Heritage Program maintains it from verified species occurrence data. Program and agency scientists map populations and natural communities, drawing habitat boundaries with aerial imagery and GIS. For animals the habitat includes areas needed for breeding, feeding, nesting and dispersal. Because plants do not move, the surrounding community that supports them forms the habitat polygon. Four agencies set the mapping parameters: the Department of Conservation and Natural Resources, the Pennsylvania Fish and Boat Commission, the Pennsylvania Game Commission and the U.S. Fish and Wildlife Service.
Two tools on one site
| Tool | What it does | Account needed |
|---|---|---|
| Conservation Planning | Reports on natural heritage areas and protected lands for early planning | No |
| PNDI Environmental Review | Compares your project footprint to species locations and recommends conservation measures and other steps for an environmental permit | Yes, registration and login |
The FAQ is clear that a Conservation Planning report does not replace a PNDI receipt or required agency consultation, although it helps with early planning.
The PNDI receipt
A project submitted through the Explorer produces a PNDI receipt. The receipt lists conservation measures, avoidance measures or next steps for further review. The first receipt is a draft. It stays a draft until the project type and area are finalized and the receipt is either submitted to the agencies or printed for a DEP application. If a draft receipt shows no impacts, the FAQ says no agency clearance letters are needed and no further review is required before permitting.
A species polygon near your site does not always mean an impact. The review also considers each species’ habitat requirements, the expected disturbance for your project type and your answers to the project questions, so the result may be avoidance or conservation measures, or no known or potential impact.
Drawing the footprint
The FAQ says to use the polygon tool for most projects. Lines are for linear projects such as roads, pipelines and transmission lines, because the calculation only includes the area immediately around a line. Drawing a footprint as a line is the likely reason a receipt shows too little acreage. A shapefile or KML that will not accept is usually a closed polyline, common in CAD exports, and converting it to a polygon fixes the problem.
Screening buffers by project type
Each project type adds a buffer around the drawn footprint. The Explorer analyzes every project within a minimum 50 acre screening area, so a small footprint is expanded to reach 50 acres. Categories most relevant to site work include these buffers from the Explorer table:
| Project type | Buffer |
|---|---|
| Single-family unit, not in a subdivision | 200 feet |
| Subdivision of one or two lots | 200 feet |
| Subdivision with more than two lots or units | 200 feet |
| Additions or maintenance to existing facilities | 200 feet |
| Roads, ditch cleaning and culvert replacement under 36 inches | 200 feet |
| Roads, new construction on a new alignment | 2,640 feet |
| Water line construction | 1,320 feet |
| Well under 1,000 gallons a day or serving a single-family unit | 200 feet |
| Act 537 sewage plans, new or repaired sewer lines | 200 feet |
| Dredging or channel maintenance | 5,280 feet |
| Voluntary cleanup under Act 2 and Chapter 250 | 2,500 feet |
If a project does not fit one category, or fits several, the FAQ says to choose a general category such as Other and coordinate with the agencies listed on the receipt. A change in project type needs a new review and another fee.
Fees, the free option and validity
The Explorer charges a $40 convenience fee per project to create a project online, generate receipts and submit them through the tool, paid by credit card when the first draft receipt is generated. The fee applies per project, not per receipt, so footprint edits and finalization cost nothing more. A free alternative exists: download the Manual Project Submission Form and coordinate directly with all four jurisdictional agencies. A receipt is valid for two years unless the footprint or project type changes, and a receipt nearing expiration can be re-analyzed with the Update Receipt button. The database is updated quarterly, and species and habitat areas can be added or removed.
Submitting to the agencies and to DEP
Finalizing a project in the Explorer sends the receipt to the Game Commission, the Fish and Boat Commission and DCNR. The Fish and Wildlife Service requires submissions by email or mail, with a narrative and supporting documents, and wants a signed final receipt. For DEP permits that require PNDI review, the FAQ says to submit a signed final receipt with the application, along with any agency documentation showing how potential impacts were resolved. Agencies then communicate directly with the applicant. Projects longer than 10 miles or larger than 5,165 acres count as large and have their own submission path.
When this comes up on site work
PNDI review is tied to permits and approvals, not to every project. DEP’s Act 537 page, for example, says most sewage planning proposals need coordination with DCNR. See our pages on Act 537 and the NPDES construction stormwater permit. Whether a particular job needs a PNDI receipt is decided by the permitting agency, county conservation district or municipality handling it.
Sources
- PA Conservation Explorer, Environmental Review
- PA Conservation Explorer, FAQ
- PA Conservation Explorer, Project Types and Screening Area Buffers
Sources checked Nov 23, 2026.
Related
Act 537 sewage facilities planning · NPDES construction stormwater permit · Chapter 105 waterways and wetlands · All PA site work regulations
FAQ
What is a PNDI receipt?
It is the report the Conservation Explorer generates after you submit a project footprint. It lists conservation measures, avoidance measures or next steps, and it is used for planning and permitting.
How much does PNDI environmental review cost?
The Explorer charges a $40 convenience fee per project, paid by credit card. A free offline option exists, but you must coordinate with all four jurisdictional agencies.
How long is a PNDI receipt valid?
Two years, unless the project footprint or project type changes, according to the Conservation Explorer FAQ.
Which agencies review PNDI projects?
The Department of Conservation and Natural Resources, the Pennsylvania Fish and Boat Commission, the Pennsylvania Game Commission and the U.S. Fish and Wildlife Service.
General information only, not legal advice. Your county conservation district, DEP and your municipality decide what applies to a specific project. Source pages checked Nov 23, 2026.