Pennsylvania Act 537 sewage facilities planning for new land development
Quick answer: Act 537 requires every Pennsylvania municipality to keep an official sewage facilities plan. New land development generally starts with a planning module reviewed by the municipality and DEP, unless an exemption applies. Local agencies permit on-lot systems of 10,000 gallons per day or less.
What Act 537 requires
DEP describes its Act 537 Sewage Facilities Program as the way the state implements the Pennsylvania Sewage Facilities Act, to help address existing sewage disposal needs and prevent future problems through planning, permitting and design. Municipalities must develop and keep current a comprehensive official sewage facilities plan, also called the base plan or Act 537 plan. DEP says it addresses existing sewage problems, the needs created by new land development, and the municipality’s future sewage needs. Municipalities must also develop and maintain a sewage management program, which in areas that rely on on-lot systems makes sure those systems are properly managed.
Planning comes before permitting
DEP’s program description says new land development proposals must show assurance of long-term sewage disposal, using a municipal centralized system, individual or community on-lot systems, or land application. Planning comes first, and facility designs are permitted only after sufficient planning has taken place. The three disposal methods DEP’s guidance names as typical are an on-lot system, a private sewage facility, or a connection to a centralized treatment facility. A plan revision is required when a new land development project is proposed, unless the project is exempt from planning.
Where a project starts
The first step for new land development, except projects that qualify for a Component 1 module, is the Sewage Facilities Planning Module Application Mailer, form 3800-CD-BCW0359. The developer sends it to the DEP regional office that covers the site, and DEP uses it to decide whether planning is required and which type applies. DEP’s page stresses that local municipal involvement is required and that planning module forms should not go straight to DEP without municipal coordination. The completed module goes to the municipality first and reaches DEP only after the municipality adopts it by resolution.
Planning forms by type of project
| Component | Used for, per DEP |
|---|---|
| Component 2 | On-lot disposal |
| Component 2m | Sewage management programs |
| Component 3 | Collection and treatment facilities |
| Component 3m | Minor Act 537 updates |
| Component 3s | Small flow treatment facilities |
DEP also lists Component 4 for agency review, a transmittal letter, a plan revision resolution, a Task/Activity Report, an Act 537 content and environmental checklist, and a planning waiver request form, 3850-FM-BCW0349.
Exemption from planning: on-lot proposals
DEP’s new land development FAQ says commercial on-lot proposals use either a Component 2 module or an exemption. An exemption requires all five of these:
- The official plan designates the area for on-lot service.
- The area is not over carbonate geology and is not within one quarter mile of water supplies documented above 5 parts per million nitrate-nitrogen.
- The area is outside high quality or exceptional value watersheds.
- Subdivided lots and the remaining tract are 1 acre or larger, confirmed by the applicant’s signature.
- Soils testing and site evaluation show separate permittable primary and replacement absorption or spray areas on each lot.
If DEP finds the proposal ineligible, a Component 2 is required.
Exemption from planning: connecting to existing sewers
An exemption for connecting to publicly owned facilities also requires all five of these:
- The existing facilities comply with the Clean Streams Law and its rules and regulations.
- Chapter 94 information from the permittees shows no existing or five-year projected hydraulic or organic overload.
- The municipality has a current approved sewage facilities plan update that is being implemented.
- The permittees certify in writing that capacity exists and no overload is projected from the new flows.
- No new or modified Water Quality Management or NPDES permit is needed for the connection.
When no exemption is granted, flows under 2,000 gallons per day that use a small flow treatment facility with a stream discharge use Component 3s, and every other proposal uses Component 3.
Permitting after planning
DEP’s program description says local agencies permit individual and community on-lot systems that treat 10,000 gallons per day or less. DEP issues all other on-lot and sewage treatment and disposal permits as Water Quality Management permits under the Clean Streams Law, and an NPDES permit is also required for a facility that discharges to waters of the Commonwealth. Three Pennsylvania Code chapters are cited: Chapter 71 on administration of the sewage facilities planning program, Chapter 72 on administration of the permitting program, and Chapter 73 on standards for on-lot sewage treatment facilities. The Small Flow Treatment Facilities Manual covers facilities treating 2,000 gallons per day or less. For setback distances on a typical lot, see our PA septic and well setbacks guide.
Timing and species and historic coordination
The FAQ tells developers to plan for steps that happen before the municipality submits anything: planning commission review, coordination with agencies on endangered species and historic resources, and capacity sign-off from the facility owner. Municipal board meeting schedules affect timing, and local approvals must be in place before DEP can review. DEP’s page says most proposals need coordination with DCNR to avoid or minimize impacts on threatened, endangered and special concern species, done through the Pennsylvania Conservation Explorer or an offline form. See our page on PNDI environmental review.
What the FAQ itself says about its weight
DEP’s new land development FAQ, version 1.0 dated July 2025, describes itself as interpretive guidance that does not change regulatory requirements. DEP’s page also notes that a commercial development that generates sewage, such as a data center, requires sewage planning, so the planning rule is not limited to housing.
Sources
- PA DEP, Sewage Facilities Planning
- PA DEP, Act 537 New Land Development FAQ
- PA DEP, Sewage Facilities Planning and Permitting Program Description
- PA DEP, Act 537 Sewage Facilities Program
Sources checked Nov 23, 2026.
Related
PA septic and well setbacks · PNDI environmental review · Chapter 102 erosion and sediment control · All PA site work regulations
FAQ
What is an Act 537 plan?
It is the comprehensive official sewage facilities plan a Pennsylvania municipality must keep current. DEP says it covers existing sewage problems, new land development needs and future needs.
Where does a new land development project start under Act 537?
With the Sewage Facilities Planning Module Application Mailer, which DEP uses to decide whether planning is required and what type applies. Municipal involvement is required.
Who permits on-lot systems?
DEP’s program description says local agencies permit individual and community on-lot systems treating 10,000 gallons per day or less, and DEP issues the other permits.
Is the 1 acre lot size a rule for every septic system?
No. In DEP’s FAQ, 1 acre is one of five criteria for a planning exemption for commercial on-lot proposals. Check with your municipality and sewage enforcement officer for a specific lot.
General information only, not legal advice. Your county conservation district, DEP and your municipality decide what applies to a specific project. Source pages checked Nov 23, 2026.