Guides · Retaining wall installation · Step 1

Retaining wall trench and leveling pad

Every segmental wall sits on a compacted aggregate pad in a trench. Block makers and NCMA agree on the idea and differ on the numbers, so here are their published figures side by side. Your block’s manual and your wall design win.

Quick answer

Dig the trench wider than the block, bury the first course below finished grade, and build a compacted crushed-stone pad. Belgard calls for a trench 12 in. wider than the block and a pad at least 6 in. deep after compaction. NCMA says the pad is at least 6 in. thick and extends at least 6 in. past the toe and heel. Follow your manufacturer’s manual for the exact depth.

Steps

1. Mark and dig

Lay out the face with string or paint. Dig the trench to the depth of the pad plus the buried block. Start the layout at the lowest elevation, because the wall steps up from there (see steps and stepping up the base).

2. Check the soil

Allan Block says to replace clay, wet or disturbed soil behind the wall with granular material. Whether the same applies under the pad is a question for your block’s manual and your design.

3. Place the pad

Spread the base stone and compact it. Belgard specifies 3/4-inch minus with fines. Unilock specifies 3/4-inch open-graded gravel (ASTM No. 57), compacted. Allan Block allows coarse sand up to 0.5 in. for the final leveling.

4. Compact

Allan Block calls for at least two plate-compactor passes on the base. See plate compactor and compaction.

5. Level both ways

Belgard calls for the first course to be level front to back and side to side, so the pad has to be level before any block goes down.

6. Bury the first course

Belgard calls for at least 6 in. of the wall buried below finished grade. See embedment. Next: setting the first course.

What each source says

SourceTrenchPad
Belgard12 in. wider than the block3/4-inch minus with fines, at least 6 in. deep after compaction, extends at least 6 in. in front of and behind the first course
Unilock8 in. deeper than one block and twice as wide6 in. of 3/4-inch open-graded gravel (ASTM No. 57), compacted
NCMANot stated as a widthAt least 6 in. thick, extending at least 6 in. from the toe and heel
Allan Block24 in. wide (18 in. for walls under 4 ft); depth 6 in. plus 1 in. per 1 ft of wall height (4 in. for walls under 4 ft)Compacted with at least two passes; coarse sand up to 0.5 in. for leveling

These are different systems, so the figures are not interchangeable. Use the numbers from the manual for the block you are installing.

Planning information, not engineering advice. Tall walls, walls with slopes or loads above, and wet or weak soils need a site-specific design. Check local code and call 811 before you dig. See when a wall needs an engineer.

Questions

How deep should the base be for a retaining wall?

NCMA and Belgard both give at least 6 in. of compacted base stone. Allan Block’s trench depth is 6 in. plus 1 in. per foot of wall height for walls 4 ft and over. Check your block’s manual.

How wide should the leveling pad be?

NCMA says the pad extends at least 6 in. from the toe and heel. Belgard says at least 6 in. in front of and behind the first course. Allan Block specifies a 24 in. wide trench for most walls.

Can I use sand under a retaining wall?

Allan Block allows coarse sand up to 0.5 in. for final leveling on top of the compacted base. Belgard and Unilock specify crushed or open-graded stone for the pad itself.

Does the pad have to go below the frost line?

The sources reviewed here do not give a frost-depth rule for the pad. Allan Block’s embedment guidance says burial generally need not reach below frost depth. See embedment and confirm with local code.

Sources: Belgard SRW Quick Reference Install Guide (2023); Unilock, How to Build Retaining Walls; NCMA retaining wall installation guide (current edition: CMHA SRW-MAN-003); Allan Block, Stepping Up the Base and Basic Installation. Checked Nov. 22, 2026.

Muthler Landscaping & Construction · Lock Haven, PA

Need a wall built in central PA?

We build segmental retaining walls from the base up. If your job is in our area, we can walk the site and quote it.

Get a quoteAll guides

Muthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.