Guides · Retaining wall installation · Step 3
Drainage aggregate behind a retaining wall
The stone zone behind the block lets water move down to the drain pipe instead of building up against the wall. Sources agree on clean, free-draining crushed stone and differ on the width. Here are the numbers.
Fill the space behind the wall face with clean, free-draining crushed stone and compact it in lifts. Belgard and NCMA call for at least 12 in. behind the wall. Unilock calls for at least 14 in. Belgard specifies 3/4-inch stone; NCMA specifies clean 1 in. minus crushed stone. Use your block’s manual for the width and stone size.
Steps
Use crushed stone with few or no fines so water passes through. Unilock names 3/4-inch open-graded gravel (ASTM No. 57). See drainage aggregate and crushed stone.
Place the stone from the back of the block back at least the distance your system calls for. See the table below. Allan Block’s stair guidance puts wall rock 12 in. behind the blocks.
Fill and compact as each course goes up. Unilock says never stack more than 18 in. of wall before backfilling. See backfill and compaction.
Unilock says to fold filter fabric over the drainage layer at the top, once it is filled to 6 in. below the coping, before topsoil goes on.
The stone zone feeds a perforated pipe at the base. See drain pipe and outlets.
Native clay or topsoil in the drainage zone defeats the purpose. Allan Block says to replace clay, wet or disturbed soil with granular material.
Width and stone by source
| Source | Stone | Width behind wall |
|---|---|---|
| Belgard | 3/4-inch free-draining aggregate | At least 12 in. |
| NCMA | Clean 1 in. minus crushed stone | At least 12 in. from the back of the unit |
| Unilock | 3/4-inch open-graded gravel (ASTM No. 57) | At least 14 in. behind the face |
| Allan Block | “Wall rock”; size not stated in the pages reviewed | 12 in. behind the blocks (stair guidance) |
Questions
What kind of stone goes behind a retaining wall?
Clean, free-draining crushed stone. Belgard names 3/4-inch aggregate, NCMA names clean 1 in. minus, and Unilock names 3/4-inch open-graded gravel (ASTM No. 57).
How much stone goes behind a retaining wall?
At least 12 in. per Belgard and NCMA, and at least 14 in. per Unilock. Check your block’s manual.
Can I use pea gravel or sand?
The sources reviewed here specify crushed or open-graded stone. They do not approve rounded pea gravel or sand for the drainage zone, so check with your block maker.
Does the stone need filter fabric?
Unilock folds filter fabric over the top of the drainage layer before topsoil. Fabric placement elsewhere is not detailed in the pages reviewed.
Sources: Belgard SRW Quick Reference Install Guide (2023); Unilock, How to Build Retaining Walls; NCMA retaining wall installation guide; Allan Block, Stairs in a Retaining Wall and Basic Installation. Checked Nov. 22, 2026.
Muthler Landscaping & Construction · Lock Haven, PA
Need a wall built in central PA?
We build segmental retaining walls from the base up. If your job is in our area, we can walk the site and quote it.
Get a quoteAll guidesMuthler Landscaping & Construction LLC · 913 Bellefonte Ave, Lock Haven, PA 17745 · (570) 397-9800 · PA HIC #PA212584.