What Is a Vapor Barrier Under a Slab? 6-Mil Poly, Laps and IRC R506 Exceptions
A vapor barrier under a slab is a sheet of polyethylene or similar material placed between a concrete slab and its base or subgrade to block moisture moving up from the ground. The model International Residential Code calls it a vapor retarder and says to use 6-mil polyethylene or an approved equivalent, with joints lapped at least 6 inches. The same section exempts garages, unheated accessory buildings, driveways, walks, patios and similar flatwork.
Vapor barrier and the terms around it
- Vapor retarder: the term used in IRC Section R506.2.3 for the layer between the slab and the base course, or the prepared subgrade if there is no base course.
- Capillary break: per the Pacific Northwest National Laboratory guide, a layer that stops water from wicking up through a slab. It is a drainage pad of aggregate or sand with geotextile matting, covered by a vapor barrier of polyethylene or extruded polystyrene foam.
- Base course: the compacted stone or sand layer under the slab. See base course.
- Geotextile fabric: the fabric used with a sand capillary break. See geotextile fabric.
- Subgrade: the soil under the base. See subgrade.
Why it matters on a job
The U.S. Department of Energy’s Building America case study says polyethylene sheeting over aggregate beneath a slab helps protect the slab from water and preserve the home’s durability. It describes protection against water wicking into cracks and spaces in the slab by capillary action, which the page says could cause structural damage during freeze-thaw cycles. The case study applies to both crawlspace and basement homes.
What the IRC says
These points come from the 2015 International Residential Code, Section R506, as published by the International Code Council:
- R506.1: slab-on-ground floors follow this section or ACI 332, with a minimum thickness of 3 1/2 inches.
- R506.2.2: where the slab is below grade, place a 4-inch base course of clean graded sand, gravel, crushed stone, crushed concrete or crushed blast-furnace slag passing a 2-inch sieve. The base is not required on well-drained or sand-gravel soils classified as Group I under Table R405.1.
- R506.2.3: place a 6-mil (0.006 inch) polyethylene or approved vapor retarder between the slab and the base course. Joints must lap at least 6 inches.
R506.2.3 lists four cases where the vapor retarder is not required: garages, utility buildings and other unheated accessory structures, unheated storage rooms under 70 square feet and carports, driveways, walks, patios and other flatwork not likely to be enclosed and heated later, and cases the building official approves based on local site conditions.
Guidance from DOE and PNNL
- Thickness: both sources use 6-mil polyethylene. PNNL says at least 6-mil.
- Aggregate under it: PNNL gives 4 inches of half-inch aggregate, or a 4-inch layer of clean sand with geotextile matting. The DOE case study used 8 inches of half-inch aggregate, says to place aggregate at least 4 inches deep, and notes that new construction often uses only 4. DOE says the extra depth gives water more room and allows a passive radon pipe.
- Laps: PNNL says to overlap sheets at least 6 inches, with a tip to use 12 inches to allow for uneven cuts. DOE’s case study overlapped sheets 12 inches and sealed the joints with tape.
- Seam sealing: PNNL says to seal overlaps with a continuous bead of acoustical sealant, butyl rubber or butyl acrylic caulk, or with tape made for polyethylene. Rigid foam joints must be taped.
- At walls: PNNL says the sheeting must touch each perimeter wall, joints with walls and around posts, pipes and radon piping should be sealed, and the sheeting should be lapped up the sides of walls and pillars and taped. The DOE case study is different. It says its sheeting was not lapped up the walls and instead ran over the foundation wall.
- Under the footing: PNNL says polyethylene should extend under the footing or between the footing and stem wall to block rising damp. DOE’s case study also ran the sheeting over the footer as an added capillary break.
Protecting it before the pour
PNNL says to keep the barrier complete, well secured and unbroken before the slab is poured, to walk carefully on the polyethylene so it does not tear or pull apart at seams, and to pour the slab directly on the poly or foam. DOE says the sheeting must stay intact during the pour. For the concrete itself, see concrete curing and control joint.
Common mistakes
- Using thinner film than 6-mil. The IRC and both guides name 6-mil.
- Short laps. The IRC minimum is 6 inches, and PNNL suggests 12.
- Stopping the sheet short of the aggregate edge. PNNL says that defeats the barrier against rising damp.
- Tearing it while working. Both sources say it must stay intact until the pour.
- Assuming flatwork needs one. R506.2.3 exempts driveways, walks and patios not likely to be enclosed and heated later.
What the sources do not say
This page uses the 2015 model IRC, not the edition Pennsylvania currently enforces, and state amendments are not covered. PNNL’s page does not give an R506 section number, and the DOE page cites the 2009 IRC (Section R506.2.3) for its basic language. The two guides disagree on whether to lap the sheeting up the walls, and this page does not pick one. Neither source gives a perm rating. The DOE page notes rigid foam board may become more common in this role as codes change, and the PNNL page already lists extruded polystyrene as an option. Which product suits a given slab is not answered here.
Vapor barrier FAQ
How thick should a slab vapor barrier be?
The 2015 IRC says 6-mil polyethylene or an approved vapor retarder. PNNL says at least 6-mil.
How much should the seams overlap?
The IRC minimum is 6 inches. PNNL tips to use 12 inches for uneven cuts, and DOE’s case study used 12 inches with taped joints.
Does a patio or driveway slab need a vapor retarder?
Under IRC R506.2.3, not for driveways, walks, patios and other flatwork not likely to be enclosed and heated later. Garages and unheated accessory buildings are also exempt, and the building official may approve other cases.
What goes under the polyethylene?
The IRC places it over a 4-inch base course where the slab is below grade. PNNL describes 4 inches of half-inch aggregate or clean sand with geotextile matting. DOE’s example used 8 inches of half-inch aggregate.
Sources
- International Code Council, 2015 International Residential Code, Chapter 5: Floors (Section R506). Model code, not a Pennsylvania-adopted text.
- U.S. Department of Energy, Building America Technology Solutions: capillary break case study. Federal source, not specific to Pennsylvania.
- Pacific Northwest National Laboratory, Building America Solution Center: Capillary Break Beneath Slab. Federal source, not specific to Pennsylvania.
Verify thicknesses, laps and code sections against the current source before you rely on them.
Keep reading
- Hardscape and Site Work Glossary
- Related terms: base course, geotextile fabric, subgrade, concrete curing and control joint
Planning a slab in central PA? Contact Muthler Landscaping & Construction for a straight answer. Planning information, not engineering advice.