Record Drawings (As-Built Drawings)

Record drawings, also called as-built drawings or as-builts, show a project as it was actually built, including changes made from the original plans.

How Pennsylvania uses them

Under 25 Pa. Code 102.8(l), the permittee submits record drawings with the notice of termination, and a licensed professional signs a final certification stating that the drawings accurately reflect the as-built conditions. The permittee keeps a copy as part of the approved PCSM plan and gives a copy to the person responsible for long-term operation and maintenance of the PCSM BMPs. The section uses the phrase record drawings, with as-built conditions in the certification wording. It does not set a drawing format.

Where it comes up

On permitted sites, record drawings document where drainage, basins and other stormwater facilities ended up, which helps whoever maintains them later. They also come up in commercial closeout packages and in elevation verification. What a given contract or owner requires is set by that contract, not by Chapter 102.

What the certification says

The certification under 102.8(l) is made under the penalties of 18 Pa.C.S. 4904. It states that the record drawings reflect as-built conditions and that the site was built according to the approved PCSM plan and any approved changes. DEP’s Notice of Termination FAQ says the notice cannot be approved without a licensed professional’s certification. That professional decides when construction of the stormwater control measures is complete and signs the SCM Construction Certification Form (3800-PM-BCW0271j) within 30 days of completion. If an underground measure was not observed during construction, it may have to be excavated to verify that it was installed.

Timing and review

The same FAQ says the notice of termination is due once permanent stabilization and BMP installation are complete, not when the permit expires, and that permanent stabilization typically means a minimum uniform 70% perennial vegetative cover, so seeding and mulching alone do not qualify. DEP or the conservation district reviews the record drawings along with the notice and inspects to confirm the measures are installed and maintained per the approved plans. Even an expired permit still needs a notice of termination, and the permittee stays jointly and severally responsible until it is approved.

When the as-built differs from the plan

DEP’s FAQ says changes to the type, size, location or construction details of a stormwater control measure, or to its drainage area including impervious area, must be recorded in record drawings submitted for review and approval. If the record drawings do not match the approved plan, the permittee must show that the site still meets PCSM requirements, or install the measure or a replacement. DEP’s instrument filing guidance adds that unless the BMPs match the plan, there are no subsurface BMPs, all BMPs are non-engineered with minimal maintenance and the maintenance plan is unchanged, the recorded instrument must be amended before the permit is terminated. The amended instrument is recorded with the record drawings and the operation and maintenance plan.

Who holds the copies

Section 102.8(m)(2) requires a recorded instrument with the county recorder of deeds for any property with a PCSM BMP. It must identify the BMP, provide access for maintenance, and state that the maintenance duty is a covenant running with the land, binding on later owners. DEP’s FAQ also says the permittee and any co-permittee must keep monitoring records for 3 years after permit coverage ends. This is planning information, not legal advice, so confirm requirements with your conservation district.

Frequently asked questions

Are record drawings the same as as-builts?

In everyday use, yes. Chapter 102 uses the term record drawings and ties them to as-built conditions.

Who has to sign them in PA?

A licensed professional signs the final certification that accompanies the record drawings under 25 Pa. Code 102.8(l).

Does a small patio job need them?

The rule applies to permitted PCSM projects. A small residential job without a permit usually does not, unless your contract or township asks for them.

Sources

Related

Bidding or planning site work? Contact Muthler Landscaping & Construction. Planning information, not legal advice.